Project Planning & Scheduling

Program Evaluation and Review Technique ("PERT")

Navigating Complexity: Program Evaluation and Review Technique (PERT) in Project Planning

In the dynamic world of project management, navigating complexity is key to achieving success. One powerful tool that helps project managers effectively plan and schedule intricate projects is the Program Evaluation and Review Technique (PERT).

PERT, developed in the 1950s for the Polaris missile program, is a technique for planning and managing complex projects with uncertain activity durations. Its core value lies in providing a framework to:

  • Estimate project completion time: By breaking down the project into smaller tasks and assigning a range of time estimates (optimistic, pessimistic, and most likely), PERT helps calculate the expected duration and potential delays.
  • Identify critical path: PERT identifies the sequence of tasks with the longest combined duration, known as the critical path. This critical path determines the minimum project completion time and highlights tasks that need careful attention to avoid delaying the entire project.
  • Track progress and manage risks: By monitoring the completion of tasks against the planned schedule, project managers can proactively identify potential issues and adjust plans accordingly. This allows for effective risk management and resource allocation.

How PERT works:

  1. Project Decomposition: The first step involves breaking down the project into smaller, manageable tasks. These tasks are then organized in a network diagram, showcasing their dependencies and sequence.
  2. Time Estimation: For each task, three time estimates are determined:
    • Optimistic (O): The shortest possible time for task completion, assuming everything goes smoothly.
    • Pessimistic (P): The longest possible time for completion, considering potential delays and unforeseen issues.
    • Most Likely (M): The most realistic time estimate for the task's completion.
  3. Expected Time Calculation: The expected time (TE) for each task is calculated using the formula: TE = (O + 4M + P) / 6
  4. Critical Path Identification: Using the calculated expected times, the network diagram helps identify the critical path – the sequence of tasks with the longest total duration.
  5. Project Completion Time Estimation: The total expected time for project completion is calculated by summing the expected times of tasks on the critical path.
  6. Monitoring and Control: PERT allows for regular updates and adjustments to the schedule as the project progresses. This helps identify potential delays and adjust resource allocation to ensure on-time completion.

Benefits of using PERT:

  • Improved project planning: A structured approach to project breakdown and time estimation.
  • Enhanced risk management: Identifies potential delays and allows for proactive mitigation strategies.
  • Better communication and coordination: Provides a shared understanding of project timelines and dependencies.
  • Increased efficiency: Optimizes resource allocation and task prioritization.

Limitations of PERT:

  • Subjective time estimates: The accuracy of PERT relies on accurate time estimates, which can be subjective and prone to bias.
  • Complexity in large projects: Managing a large number of tasks and dependencies can be complex and challenging.
  • Limited flexibility: PERT can be rigid and inflexible in responding to sudden changes in project requirements.

In conclusion:

PERT is a valuable tool for managing complex projects, but it's crucial to understand its limitations. When used effectively, PERT can help project managers create robust plans, mitigate risks, and achieve project goals within the planned timeline.


Test Your Knowledge

PERT Quiz

Instructions: Choose the best answer for each question.

1. What does PERT stand for? a) Program Evaluation and Risk Technique b) Project Evaluation and Review Technique c) Program Evaluation and Review Technique d) Project Evaluation and Risk Technique

Answer

c) Program Evaluation and Review Technique

2. What is the primary purpose of PERT? a) To estimate project costs. b) To identify and manage project risks. c) To plan and manage complex projects with uncertain activity durations. d) To allocate resources efficiently.

Answer

c) To plan and manage complex projects with uncertain activity durations.

3. Which of the following is NOT a time estimate used in PERT? a) Optimistic b) Pessimistic c) Probable d) Most Likely

Answer

c) Probable

4. What is the critical path in a PERT network diagram? a) The sequence of tasks with the shortest combined duration. b) The sequence of tasks with the longest combined duration. c) The sequence of tasks that are most likely to be completed on time. d) The sequence of tasks that are most likely to be delayed.

Answer

b) The sequence of tasks with the longest combined duration.

5. Which of the following is a limitation of PERT? a) It can only be used for small projects. b) It requires highly accurate time estimates. c) It is not flexible enough to accommodate changes in project requirements. d) It does not consider the impact of resources on project completion.

Answer

c) It is not flexible enough to accommodate changes in project requirements.

PERT Exercise

Scenario: You are the project manager for a new software development project. The project has been broken down into the following tasks, with their estimated optimistic (O), pessimistic (P), and most likely (M) durations:

| Task | O (days) | M (days) | P (days) | |---|---|---|---| | Task A | 5 | 8 | 12 | | Task B | 3 | 5 | 7 | | Task C | 2 | 4 | 6 | | Task D | 6 | 10 | 14 | | Task E | 4 | 7 | 10 | | Task F | 1 | 2 | 3 | | Task G | 3 | 5 | 7 |

Dependencies:

  • Task B depends on Task A.
  • Task C depends on Task B.
  • Task D depends on Task C.
  • Task E depends on Task A.
  • Task F depends on Task E and Task D.
  • Task G depends on Task F.

Instructions:

  1. Calculate the expected duration (TE) for each task using the PERT formula: TE = (O + 4M + P) / 6
  2. Create a network diagram to represent the project dependencies.
  3. Identify the critical path and calculate the total expected project duration.

Exercice Correction

**1. Expected Task Durations (TE):** | Task | O (days) | M (days) | P (days) | TE (days) | |---|---|---|---|---| | Task A | 5 | 8 | 12 | 8 | | Task B | 3 | 5 | 7 | 5 | | Task C | 2 | 4 | 6 | 4 | | Task D | 6 | 10 | 14 | 10 | | Task E | 4 | 7 | 10 | 7 | | Task F | 1 | 2 | 3 | 2 | | Task G | 3 | 5 | 7 | 5 | **2. Network Diagram:** [Insert a network diagram here, representing the project dependencies as described in the exercise.] **3. Critical Path and Project Duration:** * **Critical Path:** A -> B -> C -> D -> F -> G * **Total Expected Project Duration:** 8 + 5 + 4 + 10 + 2 + 5 = **34 days**


Books

  • Project Management: A Systems Approach to Planning, Scheduling, and Controlling by Harold Kerzner - A comprehensive resource covering various project management techniques, including PERT.
  • A Guide to the Project Management Body of Knowledge (PMBOK® Guide) by the Project Management Institute (PMI) - The industry standard for project management, with a section dedicated to PERT and its applications.
  • The Complete Guide to Project Management: Proven Methods to Plan, Control, and Complete Projects on Time and Within Budget by Patrick M. Hull - Provides practical insights and examples of PERT implementation in project management.

Articles

  • "PERT: A Tool for Project Planning and Management" by William G. Duffy - An article published in the Journal of Systems Management, explaining the core concepts and applications of PERT.
  • "Critical Path Method (CPM) and Program Evaluation and Review Technique (PERT)" by Project Management Institute - An informative article on the similarities and differences between CPM and PERT, two popular project scheduling techniques.
  • "Using PERT to Manage Project Risk" by Project Management Institute - A detailed discussion on the use of PERT in identifying and mitigating project risks.

Online Resources

  • Project Management Institute (PMI): The PMI website offers a wealth of information on project management, including resources on PERT and other project planning techniques. (https://www.pmi.org/)
  • PERT Chart Tutorial: A comprehensive online tutorial on PERT, covering its principles, calculations, and applications. (https://www.tutorialspoint.com/projectmanagement/pertchart_tutorial.htm)
  • PERT Chart Calculator: A web-based calculator for automatically calculating the expected duration and critical path of a project using PERT. (https://www.omnicalculator.com/engineering/pert)

Search Tips

  • "PERT project management": Use this search term to find articles, tutorials, and case studies on the application of PERT in project management.
  • "PERT critical path": This search term will help you discover resources on identifying the critical path in a project network using PERT.
  • "PERT example": This search term will provide examples of PERT diagrams and calculations, helping you understand its practical application.

Techniques

Similar Terms
Drilling & Well Completion
Legal & Compliance
Quality Assurance & Quality Control (QA/QC)
Procurement & Supply Chain Management
Geology & Exploration
Project Planning & Scheduling
Oil & Gas Processing
Asset Integrity Management
Pipeline Construction
General Technical Terms
Reservoir Engineering
Most Viewed

Comments

No Comments
POST COMMENT
captcha
Back