Cost Estimation & Control

Field Cost

Understanding "Field Cost" in Oil & Gas: Beyond the Home Office

The term "field cost" in Oil & Gas refers to a crucial category of expenses directly associated with the project site rather than the home office. This distinction is vital because field costs represent the heart of operational expenditure and often drive project profitability.

Here's a breakdown of what field costs typically encompass:

1. Labor:

  • Direct Labor: Wages for skilled and unskilled workers directly involved in construction, maintenance, and operations.
  • Indirect Labor: Wages for support personnel like supervisors, safety officers, and field engineers.

2. Materials:

  • Construction Materials: Everything needed to build and maintain infrastructure, including steel, concrete, pipe, and equipment.
  • Operating Supplies: Consumables used in day-to-day operations like drilling fluids, chemicals, and fuel.

3. Equipment:

  • Capital Equipment: Major machinery and tools used in construction and production, such as drilling rigs, compressors, and pumps.
  • Rental Equipment: Short-term equipment rentals for specific tasks.
  • Maintenance and Repair: Costs associated with keeping all equipment operational.

4. Transportation:

  • Freight: Costs of transporting materials and equipment to the site.
  • Site Transportation: Costs associated with moving personnel and equipment within the project area.

5. Subcontractor Services:

  • Specialized Services: Hiring external contractors for tasks requiring specific expertise, such as welding, electrical work, or environmental remediation.

6. Utilities:

  • Electricity, Water, and Gas: Costs for utilities needed to power and operate the project site.
  • Waste Disposal: Costs associated with managing and disposing of waste generated during operations.

7. Security and Safety:

  • Security Personnel: Costs for security personnel to protect the project site and personnel.
  • Safety Equipment and Training: Investing in safety measures and training to ensure a safe working environment.

8. Environmental Protection:

  • Environmental Monitoring: Costs associated with monitoring environmental impact and adhering to regulations.
  • Mitigation Measures: Expenses for measures to minimize environmental damage, such as spill prevention and waste management.

Field Orders: Managing Unforeseen Expenses

One aspect of field cost management often involves "Field Orders" or "Emergency Field Orders". These unplanned authorizations are issued when a construction contractor encounters unexpected situations requiring work outside the original scope of their contract.

Field Orders can be crucial for responding to unforeseen challenges but also pose potential risks:

  • Cost Overruns: Field Orders can lead to budget overruns if not managed effectively.
  • Contract Disputes: Contentious issues may arise if contractors and project owners disagree about the necessity or cost of a field order.

Effective Field Cost Management:

  • Accurate Budgeting: Carefully estimating and budgeting for all potential field costs is crucial.
  • Risk Management: Identifying and mitigating risks that could lead to unforeseen expenses.
  • Rigorous Tracking: Keeping meticulous records of all field costs and expenditures.
  • Communication: Open communication between the project team, contractors, and the home office is vital to ensure efficient field cost management.

Conclusion:

Field costs are the backbone of any successful Oil & Gas project. By understanding and managing these expenses effectively, companies can optimize project profitability and ensure operational efficiency. The use of Field Orders is a necessary tool to address unforeseen circumstances, but requires careful management to mitigate potential risks and ensure project success.


Test Your Knowledge

Quiz: Understanding Field Costs in Oil & Gas

Instructions: Choose the best answer for each question.

1. Which of the following is NOT typically considered a field cost in Oil & Gas?
a) Wages for drilling rig operators.
b) Rent for office space at the project headquarters.
c) Costs for transporting construction materials to the site.
d) Fuel for heavy machinery used in production.

Answer

The correct answer is **b) Rent for office space at the project headquarters**. This cost is associated with the home office, not the project site.

2. What are "Field Orders" in the context of Oil & Gas projects?
a) Orders placed by the home office for equipment and supplies.
b) Authorizations for work outside the original scope of a contractor's contract.
c) Orders for specific tasks assigned to individual workers on-site.
d) Orders for the transportation of personnel and equipment.

Answer

The correct answer is **b) Authorizations for work outside the original scope of a contractor's contract.** Field Orders are issued to address unforeseen situations during construction.

3. Which of these is NOT a potential risk associated with Field Orders?
a) Cost overruns.
b) Delays in project completion.
c) Increased efficiency in construction.
d) Disputes between contractors and project owners.

Answer

The correct answer is **c) Increased efficiency in construction.** Field Orders are often necessary to address unexpected issues, but they can also introduce complexities and potential inefficiencies.

4. Which of the following is a crucial aspect of effective field cost management?
a) Ignoring potential risks to save time and money.
b) Relying solely on the contractor's budget estimates.
c) Accurate budgeting and tracking of all field expenditures.
d) Minimizing communication between the project team and contractors.

Answer

The correct answer is **c) Accurate budgeting and tracking of all field expenditures.** Rigorous cost tracking and accurate budgeting are essential for effective field cost management.

5. What is the primary reason why effective field cost management is critical for Oil & Gas projects?
a) To ensure that the home office has enough budget for operational expenses.
b) To ensure the safety of personnel working on the project site.
c) To optimize project profitability and ensure operational efficiency.
d) To minimize the environmental impact of the project.

Answer

The correct answer is **c) To optimize project profitability and ensure operational efficiency.** Efficient field cost management directly impacts project success and profitability.

Exercise: Field Order Scenario

Scenario:

You are the project manager for an oil drilling project. During construction, unexpected geological conditions are encountered, requiring additional drilling depth and specialized equipment. This situation calls for a Field Order to be issued.

Task:

  1. Identify at least 3 potential risks associated with issuing a Field Order in this situation.
  2. Explain how you would mitigate these risks to ensure project success.

Exercice Correction

Here's a possible solution to the exercise:

1. Potential Risks: * Cost Overruns: The additional drilling depth and specialized equipment will undoubtedly increase project costs. * Project Delays: The need for new equipment and modifications to the drilling plan could delay project completion. * Contract Disputes: The contractor might argue that the unexpected conditions are not their responsibility, leading to disputes over the cost and responsibility of the Field Order.

2. Mitigation Strategies: * Thorough Assessment: Before issuing the Field Order, conduct a thorough assessment of the geological conditions and the required additional work to determine the actual cost and time implications. * Negotiation: Engage in open and transparent negotiations with the contractor to determine a fair price for the additional work and agree on a revised timeline for project completion. * Risk Sharing: Consider sharing some of the financial risk with the contractor, perhaps through a cost-sharing agreement or a revised contract. This can incentivize the contractor to work efficiently and minimize potential delays. * Documentation: Ensure all aspects of the Field Order, including the justification, cost estimates, and timeline adjustments, are meticulously documented and communicated to all stakeholders. This helps prevent future disputes and ensures transparency.


Books

  • "Oil and Gas Project Management" by A.K. Rao: This comprehensive book covers various aspects of project management in the oil & gas industry, including field cost management.
  • "Petroleum Engineering: Principles and Practices" by Tarek Ahmed: Provides a detailed overview of oil & gas engineering principles and practices, including cost management.
  • "Cost Engineering in the Oil and Gas Industry" by John A. T. Roberts: Focuses specifically on cost engineering techniques in the oil & gas industry.

Articles

  • "Field Costs: What They Are and How to Manage Them" by Energy Manager: Provides practical guidance on understanding and controlling field costs in oil & gas operations.
  • "Managing Field Costs in Oil and Gas Projects" by Project Management Institute: Discusses best practices for managing field costs in the context of project management principles.
  • "Field Order Management in Oil & Gas: A Critical Look" by Oil & Gas 360: Examines the challenges and best practices for managing field orders in oil & gas projects.

Online Resources

  • "Field Costs in Oil and Gas" by Offshore Technology: Offers a detailed overview of field costs, including factors influencing them and management strategies.
  • "Field Cost Management Software" by Oil & Gas Technology: Discusses the use of software tools for tracking and managing field costs in oil & gas operations.
  • "Field Order Management Systems" by Rigzone: Explores software systems designed specifically for managing field orders in oil & gas projects.

Search Tips

  • "Field Cost Management Oil & Gas": This search term will provide articles and resources related to field cost management in the oil & gas industry.
  • "Field Cost Budgeting Oil & Gas": Use this term to find articles and resources on budgeting for field costs in oil & gas projects.
  • "Field Order Management Software Oil & Gas": This search will direct you to resources about software solutions for managing field orders in oil & gas operations.
  • "Field Cost Examples Oil & Gas": Use this term to find specific examples of field costs and how they are calculated in oil & gas projects.

Techniques

Chapter 1: Techniques for Field Cost Management in Oil & Gas

This chapter explores the various techniques employed to effectively manage field costs within the Oil & Gas industry. Effective field cost management is crucial for ensuring project profitability and operational efficiency.

1.1 Budgeting and Cost Estimation:

  • Detailed Cost Breakdown Structure (CBS): Creating a comprehensive breakdown of all anticipated costs, categorized by activity, labor, materials, and equipment. This allows for precise budgeting and tracking of specific expenses.
  • Historical Data Analysis: Leveraging past project data to identify cost trends and inform future estimates. Historical data can provide valuable insights into labor rates, material costs, and equipment usage.
  • Cost Modeling and Simulation: Utilizing software tools to generate cost estimates based on various project parameters and scenarios. This allows for scenario planning and risk assessment.
  • Contingency Planning: Setting aside a percentage of the budget to cover unforeseen expenses or changes in project scope. This helps to mitigate potential budget overruns.

1.2 Procurement and Contract Management:

  • Competitive Bidding: Seeking bids from multiple vendors for materials and services to ensure competitive pricing and quality.
  • Negotiation Skills: Developing strong negotiation skills to achieve favorable terms with vendors and contractors.
  • Contract Management: Establishing clear contract terms, including payment schedules, performance metrics, and dispute resolution mechanisms.
  • Vendor Performance Tracking: Evaluating vendor performance based on cost, quality, and delivery timelines.

1.3 Labor Management:

  • Skilled Labor Sourcing: Identifying and securing qualified skilled labor, which can be a significant challenge in remote locations.
  • Labor Productivity Monitoring: Tracking worker productivity and identifying inefficiencies or bottlenecks.
  • Training and Development: Investing in training programs to enhance worker skills and safety practices.
  • Incentive Programs: Implementing performance-based incentives to motivate workers and improve productivity.

1.4 Equipment Management:

  • Equipment Optimization: Utilizing equipment efficiently and minimizing downtime through maintenance and scheduling.
  • Equipment Rental vs. Ownership: Analyzing the cost-effectiveness of renting equipment versus owning it for specific project needs.
  • Equipment Tracking and Maintenance: Implementing systems to track equipment usage, maintenance records, and repair costs.

1.5 Risk Management and Mitigation:

  • Risk Identification: Proactively identifying potential cost risks, such as weather delays, material shortages, or labor strikes.
  • Risk Assessment: Evaluating the likelihood and impact of each identified risk.
  • Risk Mitigation Strategies: Developing and implementing plans to minimize the impact of potential risks.
  • Contingency Plans: Creating backup plans to address unforeseen events or disruptions.

1.6 Data Analysis and Reporting:

  • Cost Tracking and Reporting: Maintaining detailed records of all field costs and generating regular reports for analysis.
  • Performance Metrics: Establishing key performance indicators (KPIs) to measure the effectiveness of cost management strategies.
  • Cost Variance Analysis: Identifying and explaining deviations from budget estimates to improve future planning.

1.7 Technology and Automation:

  • Field Cost Tracking Software: Utilizing specialized software solutions for automated cost tracking, data analysis, and reporting.
  • Remote Monitoring and Control: Implementing remote monitoring systems for equipment performance and operational efficiency.
  • Robotics and Automation: Exploring opportunities for automation to enhance efficiency and reduce labor costs.

Conclusion:

This chapter has provided an overview of key techniques for effective field cost management in Oil & Gas. By embracing these techniques, companies can optimize project profitability, enhance operational efficiency, and navigate the complex challenges associated with field operations.