Cost Estimation & Control

Estimate Class B

Understanding Class B Estimates: Your Roadmap to Early Project Success

In the world of project management, accurate cost estimations are crucial for successful planning and execution. While there are various levels of detail and precision in estimations, Class B estimates offer a valuable middle ground, striking a balance between detailed analysis and timely completion.

What is a Class B Estimate?

A Class B estimate, also known as a Preliminary Estimate, is a detailed cost projection based on at least two levels of a documented work breakdown structure (WBS). It typically carries an expected precision variance of 25% or less, meaning the final cost is likely to be within a range of 25% above or below the estimate.

Key Characteristics of Class B Estimates:

  • Based on a WBS: A detailed WBS allows for better understanding and breakdown of project tasks, leading to more accurate cost projections.
  • Developed by Experts: Class B estimates are usually developed by project managers and subject matter experts, leveraging their experience and knowledge of similar projects.
  • Moderate Level of Detail: They provide a good balance between detail and time constraints, ensuring the estimate is reasonably accurate without being overly burdensome.
  • 25% Variance: The expected precision variance of 25% allows for some flexibility, acknowledging potential uncertainties in the early stages of a project.

Why Use Class B Estimates?

Class B estimates provide several advantages:

  • Early Cost Projections: They offer a good understanding of the project's overall cost before detailed planning and design phases.
  • Feasibility Assessment: These estimates help determine project feasibility and identify potential cost overruns early on.
  • Budgeting and Resource Allocation: They enable effective resource allocation and budget planning for the project.
  • Stakeholder Communication: They facilitate clear communication with stakeholders regarding expected costs and project scope.

Limitations of Class B Estimates:

While valuable, Class B estimates have limitations:

  • Not as Detailed as Class A: They may not capture all project complexities and nuances.
  • Potential for Inaccuracy: While aiming for 25% variance, unforeseen events or changes in scope could impact the accuracy.
  • Early Stage Development: As they are developed early on, they may be subject to revisions as more information becomes available.

In Conclusion:

Class B estimates are a valuable tool for project managers seeking early cost projections and feasibility assessment. They strike a balance between detail and speed, allowing for informed decisions and budget planning before moving into more detailed planning stages. By understanding their characteristics and limitations, project teams can leverage Class B estimates for better project management and execution.


Test Your Knowledge

Class B Estimates Quiz

Instructions: Choose the best answer for each question.

1. What is the expected precision variance for a Class B estimate?

a) 10% b) 15% c) 25% d) 50%

Answer

c) 25%

2. Which of the following is NOT a key characteristic of a Class B estimate?

a) Based on a WBS b) Developed by experts c) Provides a high level of detail d) 25% variance allowed

Answer

c) Provides a high level of detail

3. What is a primary advantage of using Class B estimates?

a) Providing a detailed cost breakdown b) Eliminating the need for further cost estimations c) Enabling early feasibility assessment d) Guaranteeing accurate cost projections

Answer

c) Enabling early feasibility assessment

4. Which of the following is a potential limitation of Class B estimates?

a) They are always accurate. b) They are not detailed enough to capture all project complexities. c) They are time-consuming to develop. d) They are only useful for small projects.

Answer

b) They are not detailed enough to capture all project complexities.

5. What is another term used to describe a Class B estimate?

a) Definitive Estimate b) Preliminary Estimate c) Rough Order of Magnitude Estimate d) Class A Estimate

Answer

b) Preliminary Estimate

Class B Estimates Exercise

Scenario: You are a project manager tasked with developing a preliminary cost estimate for a new software development project. The project involves creating a mobile application for a client.

Task:

  1. Identify at least 5 key tasks or components of the project that would be included in a WBS for this project.
  2. For each task, provide a brief description and an estimated cost based on your knowledge of similar projects.
  3. State the overall estimated cost for the project, acknowledging the potential 25% variance.

Exercice Correction

**Possible WBS tasks and estimated costs:**

  • **Requirement Gathering & Analysis:** Define user requirements, create wireframes, and document functional specifications. **Estimated Cost: $5,000**
  • **UI/UX Design:** Design user interfaces and interactions, create mockups and prototypes. **Estimated Cost: $7,000**
  • **Development:** Build the mobile app using chosen technologies. **Estimated Cost: $15,000**
  • **Testing & Quality Assurance:** Conduct thorough testing, identify and resolve bugs. **Estimated Cost: $3,000**
  • **Deployment & Release:** Deploy the app to app stores and configure necessary settings. **Estimated Cost: $1,000**

**Overall Estimated Cost:** $31,000

**Potential Variance:** +/- $7,750 (25% of $31,000)

**Therefore, the final cost of the project is expected to be between $23,250 and $38,750.**


Books

  • "A Guide to the Project Management Body of Knowledge (PMBOK® Guide)" - Provides a comprehensive overview of project management best practices, including cost estimating and different classes of estimates.
  • "Project Management: A Systems Approach to Planning, Scheduling, and Controlling" by Harold Kerzner - Offers detailed information about project cost estimation, including various methods and techniques.
  • "Effective Project Management: Traditional, Agile, and Hybrid Approaches" by David Cleland - This book explores different project management approaches, including the use of different classes of estimates in various contexts.

Articles

  • "Class B Estimates: A Powerful Tool for Project Success" - This article discusses the benefits of Class B estimates and how to effectively develop and use them for project planning and execution.
  • "Understanding the Different Types of Cost Estimates" - This article provides a detailed overview of various types of cost estimates, including Class A, B, and C estimates, and explains their key characteristics and applications.
  • "Cost Estimating for Project Managers: A Comprehensive Guide" - This comprehensive guide covers various aspects of project cost estimation, including the use of different classes of estimates, risk analysis, and cost management techniques.

Online Resources

  • Project Management Institute (PMI): PMI website offers numerous resources on project management, including articles, webinars, and training materials related to cost estimating and various classes of estimates.
  • "Cost Estimating" from the PMBOK Guide website: This section on the PMBOK Guide website provides specific guidance on cost estimation techniques, including the use of different classes of estimates and their applications.
  • "Cost Estimating Techniques" from the International Project Management Association (IPMA): IPMA website offers a variety of resources on project management, including insights into cost estimation techniques and best practices.

Search Tips

  • Use specific keywords like "Class B estimate definition", "Class B estimate vs Class A estimate", "Class B estimate template", "Class B estimate example", "benefits of Class B estimate".
  • Combine keywords with relevant project management terms like "project management", "cost estimation", "project planning", "budgeting", "resource allocation".
  • Use quotation marks around specific phrases to refine your search results.
  • Utilize "site:pmi.org" or "site:ipma.ch" to search within specific websites like PMI or IPMA.

Techniques

Chapter 1: Techniques for Developing Class B Estimates

This chapter delves into the practical techniques employed in creating effective Class B estimates.

1.1 Work Breakdown Structure (WBS): The Foundation of Detail

The WBS serves as the cornerstone for any Class B estimate. It breaks down the project into manageable tasks, providing a clear structure for cost analysis.

  • Level 1: The highest level of the WBS defines the major project deliverables.
  • Level 2: Each level 1 deliverable is further broken down into sub-tasks.
  • Level 3: (Optional) For more complex projects, sub-tasks can be broken down further.

1.2 Bottom-Up Estimation: Building from the Ground Up

The bottom-up approach is commonly used for Class B estimates. It involves:

  • Detailed Task Analysis: Each task in the WBS is analyzed for its resource requirements (labor, materials, equipment) and estimated duration.
  • Resource Costing: The estimated cost of resources is applied to each task.
  • Total Cost Calculation: The individual task costs are summed to arrive at the overall project cost.

1.3 Analogous Estimating: Leveraging Past Experiences

This technique relies on historical data from similar projects to estimate costs.

  • Identify Comparable Projects: Projects with similar scope, complexity, and resource requirements are chosen.
  • Adjust for Differences: The historical data is adjusted to account for differences between the past projects and the current one.
  • Apply Adjustment Factors: Factors like inflation, technological advancements, and changes in labor costs are considered.

1.4 Parametric Estimating: Utilizing Historical Data and Metrics

This technique combines historical data with project parameters like size, complexity, and duration.

  • Identify Relevant Metrics: Metrics like square footage, number of units, or functional points are used.
  • Develop Regression Models: Statistical models are used to correlate historical data with project parameters.
  • Apply Model to Current Project: The model is applied to the current project based on its specific parameters.

1.5 Expert Judgement: Tap into Collective Knowledge

Involving subject matter experts and project managers in the estimation process is crucial.

  • Brainstorming Sessions: Experts contribute their knowledge and experience through collaborative discussions.
  • Delphi Technique: A structured approach where experts provide anonymous estimates, which are then reviewed and refined.

1.6 Combining Techniques:

A combination of techniques often leads to the most accurate Class B estimates.

  • Bottom-up for Detailed Tasks: This provides a detailed breakdown of costs.
  • Analogous/Parametric for High-Level Tasks: These can be used for tasks with historical data or predictable parameters.
  • Expert Judgement for Uncertainty: This helps address unforeseen factors or areas of ambiguity.

1.7 Documentation and Communication:

  • Document the Estimation Process: Record the techniques used, assumptions made, and justifications for cost estimates.
  • Communicate Clearly: Present the estimates to stakeholders with clear explanations and supporting documentation.

By employing these techniques, project managers can create robust and accurate Class B estimates, laying the groundwork for successful project planning and execution.

Similar Terms
Drilling & Well Completion
Process Engineering
General Technical Terms
Quality Control & Inspection
Safety Training & Awareness
HSE Management Systems
Emergency Response Planning
Project Planning & Scheduling
Communication & Reporting
Oil & Gas Processing
Contract & Scope Management
Foundations & Earthworks
Most Viewed

Comments

No Comments
POST COMMENT
captcha
Back