Detail | Activity Code | Activity Name | Status | Critical | Percent Complete | Start | Finish |
---|---|---|---|---|---|---|---|
View Details | C1050 | Effective Contract Date (ECD) | Not Started | Yes | 0,0 | 2014-03-01T08:00:00 | 2014-03-01T08:00:00 |
View Details | C2500 | Engineering complete | Not Started | No | 0,0 | 2015-02-23T16:00:00 | 2015-02-23T16:00:00 |
View Details | C4500 | Pre-Commissioning completed | Not Started | No | 0,0 | 2016-01-03T16:00:00 | 2016-01-03T16:00:00 |
View Details | C7550 | Completion Date (CD) - Hand Over Certificate issued | Not Started | Yes | 0,0 | 2016-03-08T16:00:00 | 2016-03-08T16:00:00 |
View Details | C6000 | All Final Documentation issued | Not Started | No | 0,0 | 2016-03-01T16:00:00 | 2016-03-01T16:00:00 |
View Details | C3500 | Mechanical Completion | Not Started | Yes | 0,0 | 2015-12-06T16:00:00 | 2015-12-06T16:00:00 |
View Details | C2000 | Start Engineering | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-01T08:00:00 |
View Details | C3000 | Construction Work Commence | Not Started | No | 0,0 | 2014-05-01T08:00:00 | 2014-05-01T08:00:00 |
View Details | C7500 | PAC achieved | Not Started | Yes | 0,0 | 2016-03-08T16:00:00 | 2016-03-08T16:00:00 |
View Details | C5500 | Commissioning completed | Not Started | Yes | 0,0 | 2016-03-01T16:00:00 | 2016-03-01T16:00:00 |
View Details | C7050 | Performance Test completed | Not Started | Yes | 0,0 | 2016-03-08T16:00:00 | 2016-03-08T16:00:00 |
View Details | C1000 | Contract Award | Not Started | Yes | 0,0 | 2014-02-01T08:00:00 | 2014-02-01T08:00:00 |
View Details | F3220 | Project Execution Plan (Exhibit A, 4.2) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-30T16:00:00 |
View Details | F3230 | Procurement Plan (Exhibit A, 6.3.2) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-30T16:00:00 |
View Details | F3240 | Subcontracting Plan (Exhibit A, 4) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-30T16:00:00 |
View Details | F3250 | Quality Management Plan (Exhibit A, 6.14.1) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-30T16:00:00 |
View Details | F3260 | Alignment Workshops Schedule (Exhibit A, 4.11) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-30T16:00:00 |
View Details | F3270 | Organization Chart (Exhibit P, 1.3.2) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-30T16:00:00 |
View Details | F3280 | Job Roles and Responsibilities (Exhibit A, 4.2) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-30T16:00:00 |
View Details | F3290 | Integrity Management (Exhibit A, 8.8) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-30T16:00:00 |
View Details | F3300 | Reporting Plan (Exhibit P, 1.6.2) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-30T16:00:00 |
View Details | F3310 | Weekly Progress Report (Exhibit P, 1.6.4) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-30T16:00:00 |
View Details | F3320 | Monthly Progress Report (Exhibit P, 1.6.4) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-04-29T16:00:00 |
View Details | F3330 | Kick-Off Meeting Engineering and Procurement (Exhibit P, 1.6.4) | Not Started | No | 0,0 | 2014-03-15T08:00:00 | 2014-03-15T08:00:00 |
View Details | F3340 | Kick-Off Meeting HSSE (Exhibit P, 1.6.4) | Not Started | No | 0,0 | 2014-03-22T08:00:00 | 2014-03-22T08:00:00 |
View Details | M9040 | Kick-Off Meeting Construction (Exhibit P, 1.6.4) | Not Started | No | 0,0 | 2014-06-02T08:00:00 | 2014-06-02T08:00:00 |
View Details | F3360 | Construction Weekly Progress Meeting (Exhibit P, 1.6.4) | Not Started | No | 0,0 | 2014-06-19T08:00:00 | 2014-06-19T08:00:00 |
View Details | F3370 | Close Out Report (Exhibit P, 1.6.4) | Not Started | No | 0,0 | 2015-12-07T08:00:00 | 2016-02-14T16:00:00 |
View Details | F3400 | Work Breakdown Structures (Exhibit P, 2.3.2) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-30T16:00:00 |
View Details | F3410 | Schedule development and Control Plan (Exhibit P, 2.3.2) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-30T16:00:00 |
View Details | F3420 | 90 Days Look Ahead (Exhibit P, 2.3.2) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-30T16:00:00 |
View Details | F3430 | Basis of the Schedule (Exhibit P, 2.3.5) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-30T16:00:00 |
View Details | F3460 | Overall Project Execution Schedule (Exhibit P, 2.3.5) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-05-29T16:00:00 |
View Details | F3470 | Progress Measurement Plan for Engineering and Procurement Activities (Exhibit P, 2.3.6) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-04-14T16:00:00 |
View Details | F3480 | Progress Measurement Plan for Construction, Pre-Commissioning and Commissioning (Exhibit P, 2.3.7) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-06-28T16:00:00 |
View Details | F3490 | Cost Control and Accounting Plan (Exhibit P, 2.4.2) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-30T16:00:00 |
View Details | F3500 | Baseline for Cost Control and Reporting (Exhibit P, 2.4.5) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-30T16:00:00 |
View Details | F3510 | Mobilisation Plan | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-30T16:00:00 |
View Details | F3520 | Invoicing and Payment Procedure (Exhibit P, 2.4.7) | Not Started | No | 0,0 | 2014-02-01T08:00:00 | 2014-02-14T16:00:00 |
View Details | F3530 | Variation Change Control Plan (Exhibit P, 2.4.4) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-30T16:00:00 |
View Details | F3540 | Risk Management System (Plan, Procedure, Schedule, Matrix and Register) (Exhibit P, 2.5.2) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-30T16:00:00 |
View Details | F3550 | Mech. Completion, Pre-Comm., Comm., Start Up, Handover and Provisional Acceptance Plan (Exhibit K, 3.1) | Not Started | Yes | 0,0 | 2014-11-22T08:00:00 | 2014-12-19T16:00:00 |
View Details | F3560 | Performance Test Procedure (Exhibit D, 3.1) | Not Started | Yes | 0,0 | 2015-11-05T08:00:00 | 2015-12-02T16:00:00 |
View Details | F3570 | Information Management Plan (incl. Corresp. Plan and Procedures, Doc Distrib. Matrix, Master Doc Reg.) (Ex. P, 2.6.3) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-30T16:00:00 |
View Details | F3580 | Knowledge Management (KM) Plan (Exhibit P, 2.7.2) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-30T16:00:00 |
View Details | F3590 | Management of Change Procedure (Exhibit P, 2.8.1) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-05-29T16:00:00 |
View Details | F3600 | Equipment Testing and Matertial Inspection Program | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-04-09T16:00:00 |
View Details | F3610 | FEED Design Endorsement Certificate (Exhibit A, 5.4) | Not Started | Yes | 0,0 | 2014-03-30T16:00:00 | 2014-03-30T16:00:00 |
View Details | F3620 | Technical Documents Register (Exhibit A, 12.1) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-04-14T16:00:00 |
View Details | F3630 | Constructability Plan (Exhibit A, 5.13) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-30T16:00:00 |
View Details | F3640 | Interface Management Plan (Exhibit P, 2.10) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-30T16:00:00 |
View Details | F3650 | Interface Management Procedure (Exhibit P, 2.10) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-04-14T16:00:00 |
View Details | F3660 | Interface Data Submission Schedule (Exhibit P, 2.10.1) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-04-29T16:00:00 |
View Details | F3670 | Interface Data Requirements Schedule (Exhibit P, 2.10.1) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-04-29T16:00:00 |
View Details | F3680 | Interface Register (Exhibit P, 2.10.1) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-05-29T16:00:00 |
View Details | F3690 | Interface Definition Report (Exhibit P, 2.10.1) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-06-28T16:00:00 |
View Details | F3700 | HSSE Bridging Document (Exhibit J, 4.2) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-20T16:00:00 |
View Details | F3710 | Final Security Plan (Exhibit J, 4.9) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-06-28T16:00:00 |
View Details | F3720 | Final Community Relation Plan (Exhibit J, 4.14) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-06-28T16:00:00 |
View Details | F3730 | Final Environemental Management and Monitoring Plan (Exhibit J, Att. 3) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-06-28T16:00:00 |
View Details | F3740 | Final Emergency Response Plan (Exhibit J, 4.13) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-06-28T16:00:00 |
View Details | M2801 | Fire & Safety Design | Not Started | Yes | 0,0 | 2014-03-03T08:00:00 | 2014-04-09T16:00:00 |
View Details | M2802 | Fire Protection Layout/Dwgs | Not Started | Yes | 0,0 | 2014-03-03T08:00:00 | 2014-03-31T16:00:00 |
View Details | M2803 | Fire Escape Route & Safety sign Layouts | Not Started | Yes | 0,0 | 2014-03-03T08:00:00 | 2014-03-31T16:00:00 |
View Details | M2804 | Fire Water sys. P&IDs | Not Started | No | 0,0 | 2014-03-12T08:00:00 | 2014-04-09T16:00:00 |
View Details | M2806 | F&G Detection Layouts | Not Started | Yes | 0,0 | 2014-04-01T08:00:00 | 2014-04-18T16:00:00 |
View Details | M2807 | F&G Control & alarm system | Not Started | Yes | 0,0 | 2014-04-10T08:00:00 | 2014-04-29T16:00:00 |
View Details | M2808 | Equipment Data sheets | Not Started | No | 0,0 | 2014-04-30T08:00:00 | 2014-05-19T16:00:00 |
View Details | M2805 | Deluge system - Req | Not Started | No | 0,0 | 2014-04-10T08:00:00 | 2014-04-26T16:00:00 |
View Details | F5060 | Engineering - Civil | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2014-09-26T16:00:00 |
View Details | F5061 | First Submittal of first Civil Document acc. to DDS | Not Started | Yes | 0,0 | 2014-04-29T16:00:00 | 2014-04-29T16:00:00 |
View Details | F5062 | First Submittal of last Civil Document acc. to DDS | Not Started | No | 0,0 | 2014-06-28T16:00:00 | 2014-06-28T16:00:00 |
View Details | F5065 | Approval of Civil Documents by Client and Independent third Party | Not Started | Yes | 0,0 | 2014-04-30T08:00:00 | 2014-07-12T16:00:00 |
View Details | M2201 | BID Review for Civil Eng. Design Basis | Not Started | Yes | 0,0 | 2014-03-03T08:00:00 | 2014-05-02T16:00:00 |
View Details | M2202 | Civil & Str. Specs Review & update | Not Started | No | 0,0 | 2014-03-10T08:00:00 | 2014-04-07T16:00:00 |
View Details | M2203 | Site Investigation & Survey Reports | Not Started | Yes | 0,0 | 2014-04-10T08:00:00 | 2014-06-11T16:00:00 |
View Details | M2204 | Plot Plans - Prelim. | Not Started | Yes | 0,0 | 2014-03-03T08:00:00 | 2014-03-31T16:00:00 |
View Details | M2207 | Pilling Layout Dwgs | Not Started | No | 0,0 | 2014-06-12T08:00:00 | 2014-07-10T16:00:00 |
View Details | M2209 | Bldgs. | Not Started | Yes | 0,0 | 2014-04-01T08:00:00 | 2014-04-18T16:00:00 |
View Details | M2210 | Substation Bldgs. | Not Started | No | 0,0 | 2014-04-21T08:00:00 | 2014-05-08T16:00:00 |
View Details | M2212 | Equipment Structure Design | Not Started | Yes | 0,0 | 2014-03-03T08:00:00 | 2014-04-18T16:00:00 |
View Details | M2213 | Pipe Rack Design | Not Started | Yes | 0,0 | 2014-03-03T08:00:00 | 2014-04-18T16:00:00 |
View Details | M2215 | Steel Structure MTO/Req. | Not Started | No | 0,0 | 2014-03-21T08:00:00 | 2014-04-18T16:00:00 |
View Details | M2205 | Plot Plans | Not Started | Yes | 0,0 | 2014-04-22T08:00:00 | 2014-05-20T16:00:00 |
View Details | M2206 | Roads & Paving Plan | Not Started | No | 0,0 | 2014-05-13T08:00:00 | 2014-06-10T16:00:00 |
View Details | M2211 | Shelters | Not Started | No | 0,0 | 2014-05-13T08:00:00 | 2014-05-30T16:00:00 |
View Details | M2208 | Equipment Foundation Design | Not Started | No | 0,0 | 2014-06-12T08:00:00 | 2014-08-08T16:00:00 |
View Details | M2214 | Steel Structure 1st MTO/Req.(65%) | Not Started | No | 0,0 | 2014-03-03T08:00:00 | 2014-03-20T16:00:00 |
View Details | F5030 | Engineering - Rotating/Static Equipment, HVAC | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2015-02-23T16:00:00 |
View Details | F5031 | First Submittal of first Rotating/Static Equipment, HVAC Document acc. to DDS | Not Started | Yes | 0,0 | 2014-04-29T16:00:00 | 2014-04-29T16:00:00 |
View Details | F5032 | First Submittal of last Rotating/Static Equipment, HVAC Document acc. to DDS | Not Started | No | 0,0 | 2014-06-28T16:00:00 | 2014-06-28T16:00:00 |
View Details | F5035 | Approval of Rotating/Static Equipment, HVAC Documents by Client and Independent third Party | Not Started | Yes | 0,0 | 2014-04-30T08:00:00 | 2014-07-12T16:00:00 |
View Details | J2425 | Engineering - Nitrogen System | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2014-06-28T16:00:00 |
View Details | J3125 | Engineering - Gas Turbine System | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2014-07-28T16:00:00 |
View Details | J3330 | Engineering - Fuel Gas Supply System | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2014-06-28T16:00:00 |
View Details | J3520 | Engineering - Chlorination System | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2014-06-28T16:00:00 |
View Details | J4360 | Engineering - Aquifer / Plant Water System | Not Started | No | 0,0 | 2014-03-31T08:00:00 | 2014-06-28T16:00:00 |
View Details | J4530 | Engineering - Fresh Water System | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2014-06-28T16:00:00 |
View Details | J4640 | Engineering - Demin Water System | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2014-06-28T16:00:00 |
View Details | J4930 | Engineering - Instrument & Plant Air System | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2014-06-28T16:00:00 |
View Details | J5220 | Engineering - Emergency Power Generator | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2014-06-28T16:00:00 |
View Details | M2701 | Design Criteria for HVAC Design | Not Started | Yes | 0,0 | 2014-04-01T08:00:00 | 2014-04-29T16:00:00 |
View Details | M2702 | Design Load calculations | Not Started | Yes | 0,0 | 2014-04-30T08:00:00 | 2014-05-28T16:00:00 |
View Details | M2703 | Optimisation & Selection of system | Not Started | Yes | 0,0 | 2014-04-30T08:00:00 | 2014-05-28T16:00:00 |
View Details | M2704 | Equipment Sizing | Not Started | Yes | 0,0 | 2014-04-30T08:00:00 | 2014-05-28T16:00:00 |
View Details | M2705 | Specifications & Data sheets | Not Started | Yes | 0,0 | 2014-04-30T08:00:00 | 2014-05-28T16:00:00 |
View Details | M2706 | HVAC system drawings | Not Started | Yes | 0,0 | 2014-04-30T08:00:00 | 2014-05-28T16:00:00 |
View Details | M2707 | HVAC- MTO/Req. | Not Started | No | 0,0 | 2014-05-29T08:00:00 | 2014-06-17T16:00:00 |
View Details | M1100 | ENGINEERING | Not Started | Yes | 0,0 | 2014-03-01T08:00:00 | 2014-10-02T16:00:00 |
View Details | M2101 | Home Office Moilization Eng. Team | Not Started | Yes | 0,0 | 2014-03-03T08:00:00 | 2014-03-20T16:00:00 |
View Details | M2103 | Project management Procedure | Not Started | No | 0,0 | 2014-03-10T08:00:00 | 2014-04-07T16:00:00 |
View Details | M2110 | Early S/C Award for Geotech Survey | Not Started | Yes | 0,0 | 2014-03-21T08:00:00 | 2014-04-09T16:00:00 |
View Details | M2106 | Quality Plan | Not Started | No | 0,0 | 2014-03-10T08:00:00 | 2014-03-27T16:00:00 |
View Details | M2107 | HSE Plan | Not Started | No | 0,0 | 2014-03-12T08:00:00 | 2014-03-31T16:00:00 |
View Details | M2104 | Project Execution Plan | Not Started | No | 0,0 | 2014-03-10T08:00:00 | 2014-04-07T16:00:00 |
View Details | M2109 | Work Schedule Level -3 - 4 - 5 | Not Started | No | 0,0 | 2014-03-12T08:00:00 | 2014-04-09T16:00:00 |
View Details | M2102 | Contract Management Manual | Not Started | No | 0,0 | 2014-03-10T08:00:00 | 2014-04-07T16:00:00 |
View Details | M2108 | Materials Mgt./Procurement Plan | Not Started | No | 0,0 | 2014-03-12T08:00:00 | 2014-03-31T16:00:00 |
View Details | M2105 | Sub-Contracting Procedure | Not Started | No | 0,0 | 2014-03-12T08:00:00 | 2014-03-31T16:00:00 |
View Details | M2111 | Early S/C Award for Topographic Survey | Not Started | No | 0,0 | 2014-03-22T08:00:00 | 2014-04-06T16:00:00 |
View Details | F5020 | Engineering - Static Equipment | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2014-11-25T16:00:00 |
View Details | F5021 | First Submittal of first Static Equipment Document acc. to DDS | Not Started | Yes | 0,0 | 2014-04-29T16:00:00 | 2014-04-29T16:00:00 |
View Details | F5022 | First Submittal of last Static Equipment Document acc. to DDS | Not Started | No | 0,0 | 2014-06-28T16:00:00 | 2014-06-28T16:00:00 |
View Details | F5025 | Approval of Static Equipment Documents by Client and Independent Third Party | Not Started | Yes | 0,0 | 2014-04-30T08:00:00 | 2014-07-12T16:00:00 |
View Details | M2301 | Equipment Data Sheets | Not Started | Yes | 0,0 | 2014-03-03T08:00:00 | 2014-03-31T16:00:00 |
View Details | M2303 | Equipment Erection Procedure | Not Started | No | 0,0 | 2014-04-01T08:00:00 | 2014-04-18T16:00:00 |
View Details | M2302 | Vessels/Drums- Req. | Not Started | No | 0,0 | 2014-05-16T08:00:00 | 2014-06-13T16:00:00 |
View Details | M2402 | Vessel & Tanks Plates- Req. | Not Started | No | 0,0 | 2014-04-01T08:00:00 | 2014-04-29T16:00:00 |
View Details | M2401 | Tanks & Vessel Engg. Drawings | Not Started | Yes | 0,0 | 2014-03-03T08:00:00 | 2014-03-31T16:00:00 |
View Details | M2403 | Other Tanks Plates- Req. | Not Started | No | 0,0 | 2014-03-15T08:00:00 | 2014-03-30T16:00:00 |
View Details | M2404 | Other Plates- Req. | Not Started | No | 0,0 | 2014-04-01T08:00:00 | 2014-04-16T16:00:00 |
View Details | F5070 | Engineering - Steel Structures | Not Started | Yes | 0,0 | 2014-05-30T08:00:00 | 2015-01-24T16:00:00 |
View Details | F5071 | First Submittal of first Steel Structure Document acc. to DDS | Not Started | Yes | 0,0 | 2014-06-28T16:00:00 | 2014-06-28T16:00:00 |
View Details | F5072 | First Submittal of last Steel Structure Document acc. to DDS | Not Started | No | 0,0 | 2014-08-27T16:00:00 | 2014-08-27T16:00:00 |
View Details | F5075 | Approval of Steel Structure Documents by Client and Independent third Party | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2014-09-10T16:00:00 |
View Details | F5100 | Engineering - HSE | Not Started | Yes | 0,0 | 2014-08-28T08:00:00 | 2014-12-25T16:00:00 |
View Details | F5110 | First Submittal of first HSE Document acc. to DDS | Not Started | Yes | 0,0 | 2014-09-26T16:00:00 | 2014-09-26T16:00:00 |
View Details | F5120 | First Submittal of last HSE Document acc. to DDS | Not Started | No | 0,0 | 2014-11-25T16:00:00 | 2014-11-25T16:00:00 |
View Details | F5130 | Approval of HSE Documents by Client and Independent Third Party | Not Started | Yes | 0,0 | 2014-09-27T08:00:00 | 2014-12-09T16:00:00 |
View Details | F5040 | Engineering - Electrical | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2015-02-23T16:00:00 |
View Details | F5041 | First Submittal of first Electrical Engineering Document acc. to DDS | Not Started | Yes | 0,0 | 2014-04-29T16:00:00 | 2014-04-29T16:00:00 |
View Details | F5042 | First Submittal of last Electrical Engineering Document acc. to DDS | Not Started | No | 0,0 | 2014-06-28T16:00:00 | 2014-06-28T16:00:00 |
View Details | F5045 | Approval of Electrical Engineering Documents by Client and Independent third Party | Not Started | Yes | 0,0 | 2014-04-30T08:00:00 | 2014-07-12T16:00:00 |
View Details | J0995 | Engineering - MV System 6.6kV | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2014-06-28T16:00:00 |
View Details | J1095 | Engineering - LV System 400V | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2014-06-28T16:00:00 |
View Details | J1195 | Engineering - LV Trafos | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2014-05-29T16:00:00 |
View Details | J1295 | Engineering - Frequency Inverter | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2014-05-29T16:00:00 |
View Details | J1395 | Engineering - Battery System 220V DC | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2014-06-28T16:00:00 |
View Details | J1495 | Engineering - Small Power System | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2014-07-08T16:00:00 |
View Details | J1585 | Engineering - UPS 230V AC | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2014-06-28T16:00:00 |
View Details | J1685 | Engineering - Lighting and Grounding System | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2014-06-28T16:00:00 |
View Details | J1775 | Engineering - Plant Communication and Visualization System | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2014-06-28T16:00:00 |
View Details | J1865 | Engineering - Cables and Cable Trays | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2014-06-28T16:00:00 |
View Details | J2145 | Engineering - Field Cabling | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2014-06-28T16:00:00 |
View Details | F5010 | Engineering - Process | Not Started | Yes | 0,0 | 2014-03-01T08:00:00 | 2014-11-25T16:00:00 |
View Details | F5011 | First Submittal of first Process Engineering Document acc. to DDS | Not Started | Yes | 0,0 | 2014-03-30T16:00:00 | 2014-03-30T16:00:00 |
View Details | F5012 | First Submittal of last Process Engineering Document acc. to DDS | Not Started | No | 0,0 | 2014-05-29T16:00:00 | 2014-05-29T16:00:00 |
View Details | F5015 | Approval of Process Engineering Documents by Client and Independent Third Party | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2014-06-12T16:00:00 |
View Details | M2501 | Review CMS & Control Philosphy | Not Started | Yes | 0,0 | 2014-03-03T08:00:00 | 2014-03-20T16:00:00 |
View Details | M2502 | Corrosion control & Monitoring Sys. Specs | Not Started | Yes | 0,0 | 2014-03-21T08:00:00 | 2014-04-09T16:00:00 |
View Details | M2503 | Cath. Protn Design/Specs/D.sheets/Dwgs | Not Started | Yes | 0,0 | 2014-04-01T08:00:00 | 2014-04-29T16:00:00 |
View Details | M2504 | Protective coating /Lining Specs/Data sheets | Not Started | Yes | 0,0 | 2014-04-30T08:00:00 | 2014-05-28T16:00:00 |
View Details | M2505 | Cathodic Protn. - Req | Not Started | No | 0,0 | 2014-04-30T08:00:00 | 2014-05-17T16:00:00 |
View Details | M2506 | Coating/Lining - Req. | Not Started | Yes | 0,0 | 2014-05-29T08:00:00 | 2014-06-22T16:00:00 |
View Details | F5140 | Engineering - Auxiliary Equipment | Not Started | Yes | 0,0 | 2014-05-30T08:00:00 | 2014-11-25T16:00:00 |
View Details | F5150 | First Submittal of first Auxiliary Equipment Document acc. to DDS | Not Started | Yes | 0,0 | 2014-06-28T16:00:00 | 2014-06-28T16:00:00 |
View Details | F5160 | First Submittal of last Auxiliary Equipment Document acc. to DDS | Not Started | No | 0,0 | 2014-08-27T16:00:00 | 2014-08-27T16:00:00 |
View Details | F5170 | Approval of Auxiliary Equipment Documents by Client and Independent Third Party | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2014-09-10T16:00:00 |
View Details | F5050 | Engineering - Automation, Instrumentation and Control | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2015-02-23T16:00:00 |
View Details | F5051 | First Submittal of first Automation, I&C Engineering Document acc. to DDS | Not Started | Yes | 0,0 | 2014-04-29T16:00:00 | 2014-04-29T16:00:00 |
View Details | F5052 | First Submittal of last Automation, I&C Engineering Document acc. to DDS | Not Started | No | 0,0 | 2014-06-28T16:00:00 | 2014-06-28T16:00:00 |
View Details | F5055 | Approval of Automation, I&C Engineering Documents by Client and Independent third Party | Not Started | Yes | 0,0 | 2014-04-30T08:00:00 | 2014-07-12T16:00:00 |
View Details | J1945 | Engineering - ICSS System | Not Started | Yes | 0,0 | 2014-04-30T08:00:00 | 2014-07-28T16:00:00 |
View Details | J2045 | Engineering - Field Instruments | Not Started | Yes | 0,0 | 2014-04-30T08:00:00 | 2014-06-28T16:00:00 |
View Details | F5180 | Engineering - Piping | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2014-10-26T16:00:00 |
View Details | F5190 | First Submittal of first Piping Document acc. to DDS | Not Started | Yes | 0,0 | 2014-04-29T16:00:00 | 2014-04-29T16:00:00 |
View Details | F5200 | First Submittal of last Piping Document acc. to DDS | Not Started | No | 0,0 | 2014-06-28T16:00:00 | 2014-06-28T16:00:00 |
View Details | F5210 | Approval of Piping Documents by Client and Independent third Party | Not Started | Yes | 0,0 | 2014-04-30T08:00:00 | 2014-07-12T16:00:00 |
View Details | J2225 | Engineering - Condensate System Piping | Not Started | Yes | 0,0 | 2014-04-24T08:00:00 | 2014-08-16T16:00:00 |
View Details | J2325 | Engineering - Methanol injection Piping | Not Started | No | 0,0 | 2014-04-17T08:00:00 | 2014-08-09T16:00:00 |
View Details | J2525 | Engineering - Nitrogen Nitrogen System Piping | Not Started | No | 0,0 | 2014-03-31T08:00:00 | 2014-07-23T16:00:00 |
View Details | J3145 | Engineering - Fuel Gas Supply System Piping | Not Started | Yes | 0,0 | 2014-04-30T08:00:00 | 2014-08-22T16:00:00 |
View Details | J3635 | Engineering - Chlorination System Piping | Not Started | Yes | 0,0 | 2014-05-07T08:00:00 | 2014-08-29T16:00:00 |
View Details | J3715 | Engineering Ready for Procurement - Well head flow lines | Not Started | Yes | 0,0 | 2014-06-09T08:00:00 | 2014-06-09T08:00:00 |
View Details | J3770 | Engineering Ready for Procurement - Methanol lines | Not Started | Yes | 0,0 | 2014-06-09T08:00:00 | 2014-06-09T08:00:00 |
View Details | J3830 | Engineering - Condensate Piping | Not Started | Yes | 0,0 | 2014-04-07T08:00:00 | 2014-07-30T16:00:00 |
View Details | J3890 | Engineering - Off gas connection piping | Not Started | Yes | 0,0 | 2014-04-07T08:00:00 | 2014-07-30T16:00:00 |
View Details | J2725 | Engineering - Heat medium piping | Not Started | Yes | 0,0 | 2014-05-21T08:00:00 | 2014-09-12T16:00:00 |
View Details | J4010 | Engineering - Gas / Condensate Piping | Not Started | No | 0,0 | 2014-05-28T08:00:00 | 2014-09-19T16:00:00 |
View Details | J4070 | Engineering - Gas Piping | Not Started | Yes | 0,0 | 2014-05-28T08:00:00 | 2014-09-19T16:00:00 |
View Details | J4130 | Engineering - Condensate Piping | Not Started | No | 0,0 | 2014-04-07T08:00:00 | 2014-07-30T16:00:00 |
View Details | J2825 | Engineering - Chemical injection piping | Not Started | Yes | 0,0 | 2014-06-04T08:00:00 | 2014-09-26T16:00:00 |
View Details | J3025 | Engineering - Produced water piping | Not Started | Yes | 0,0 | 2014-05-07T08:00:00 | 2014-08-29T16:00:00 |
View Details | J3225 | Engineering - Inertgas Piping | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2014-07-23T16:00:00 |
View Details | J4185 | Engineering - Methanol injection interconnecting piping | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2014-07-23T16:00:00 |
View Details | J4240 | Engineering - Amine Piping | Not Started | Yes | 0,0 | 2014-05-14T08:00:00 | 2014-09-05T16:00:00 |
View Details | J4300 | Engineering - Glycol Piping | Not Started | Yes | 0,0 | 2014-05-14T08:00:00 | 2014-09-05T16:00:00 |
View Details | J4470 | Engineering - Plant Water Piping | Not Started | Yes | 0,0 | 2014-05-07T08:00:00 | 2014-08-29T16:00:00 |
View Details | J4750 | Engineering - Fresh Water System Piping | Not Started | Yes | 0,0 | 2014-05-07T08:00:00 | 2014-08-29T16:00:00 |
View Details | J4810 | Engineering - Demin Water System Piping | Not Started | Yes | 0,0 | 2014-05-07T08:00:00 | 2014-08-29T16:00:00 |
View Details | J5040 | Engineering - Plant Air Piping | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2014-07-23T16:00:00 |
View Details | J5100 | Engineering - Instrument Air Piping | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2014-07-23T16:00:00 |
View Details | J5160 | Engineering - Produced water treatment system piping | Not Started | Yes | 0,0 | 2014-04-07T08:00:00 | 2014-07-30T16:00:00 |
View Details | J3870 | data sheet and techn. requirements for purchasing available | Not Started | No | 0,0 | 2014-04-12T08:00:00 | 2014-04-12T08:00:00 |
View Details | J5355 | Engineering - interconecting piping (general) | Not Started | Yes | 0,0 | 2014-04-07T08:00:00 | 2014-07-30T16:00:00 |
View Details | M2601 | Insulation Specs/Data Sheet/Purch.Reqn. | Not Started | No | 0,0 | 2014-06-06T08:00:00 | 2014-07-04T16:00:00 |
View Details | M2901 | Typical Details | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-24T16:00:00 |
View Details | M2902 | Wall Thickness Study Specification | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-24T16:00:00 |
View Details | M2903 | Line Pipe Data Sheets & Req. | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-24T16:00:00 |
View Details | M2904 | Route Selection Study | Not Started | No | 0,0 | 2014-03-31T08:00:00 | 2014-05-01T16:00:00 |
View Details | M2905 | Ground Profile | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-05-08T16:00:00 |
View Details | M2906 | Stress Analysis & Calculations | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-24T16:00:00 |
View Details | M2907 | Location Class Report | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-24T16:00:00 |
View Details | M2908 | Detailed Drawings & Arrangements for critical area | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2014-06-08T16:00:00 |
View Details | M2909 | General Planimetry | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-24T16:00:00 |
View Details | F0900 | Basic Engineering | Not Started | Yes | 0,0 | 2014-03-01T08:00:00 | 2014-07-19T16:00:00 |
View Details | F0850 | Feed Endorsement | Not Started | Yes | 0,0 | 2014-03-01T08:00:00 | 2014-03-30T16:00:00 |
View Details | M3780 | Final Documentation - Water / Condensate Separator System | Not Started | No | 0,0 | 2015-08-16T08:00:00 | 2015-11-28T16:00:00 |
View Details | M3790 | Final Documentation - Condensate Stabilisation System | Not Started | No | 0,0 | 2015-08-16T08:00:00 | 2015-11-28T16:00:00 |
View Details | M3800 | Final Documentation - Test Separation and Metering System | Not Started | No | 0,0 | 2015-08-16T08:00:00 | 2015-11-28T16:00:00 |
View Details | M3810 | Final Documentation - Gas Reception System | Not Started | No | 0,0 | 2015-08-16T08:00:00 | 2015-11-28T16:00:00 |
View Details | M3820 | Final Documentation - Gas Separation System | Not Started | No | 0,0 | 2015-08-16T08:00:00 | 2015-11-28T16:00:00 |
View Details | M3830 | Final Documentation - Offgas Compression System | Not Started | No | 0,0 | 2015-08-16T08:00:00 | 2015-11-28T16:00:00 |
View Details | M3840 | Final Documentation - Gas Treatment System | Not Started | No | 0,0 | 2015-08-30T08:00:00 | 2015-12-12T16:00:00 |
View Details | M3850 | Final Documentation - Gas Conditioning (Dehydration) System | Not Started | No | 0,0 | 2015-09-02T08:00:00 | 2015-12-15T16:00:00 |
View Details | M3860 | Final Documentation - Gas Conditioning (Dew Pointing) System | Not Started | No | 0,0 | 2015-09-16T08:00:00 | 2015-12-29T16:00:00 |
View Details | M3870 | Final Documentation - Gas Export and Metering System | Not Started | No | 0,0 | 2015-07-20T08:00:00 | 2015-11-01T16:00:00 |
View Details | M3880 | Final Documentation - Gas Sweetening (Amine) System | Not Started | No | 0,0 | 2015-09-01T08:00:00 | 2015-12-14T16:00:00 |
View Details | M3890 | Final Documentation - Condensate Storage and Metering System | Not Started | No | 0,0 | 2015-07-26T08:00:00 | 2015-11-07T16:00:00 |
View Details | M3900 | Final Documentation - Cooling Medium (Propane) System | Not Started | No | 0,0 | 2015-09-16T08:00:00 | 2015-12-29T16:00:00 |
View Details | M3910 | Final Documentation - Heating Medium System | Not Started | No | 0,0 | 2015-07-04T08:00:00 | 2015-10-15T16:00:00 |
View Details | M3920 | Final Documentation - Chemical Injection System | Not Started | No | 0,0 | 2015-07-04T08:00:00 | 2015-10-15T16:00:00 |
View Details | M3960 | Final Documentation - Methanol Injection System | Not Started | No | 0,0 | 2015-09-23T08:00:00 | 2016-01-05T16:00:00 |
View Details | M3980 | Final Documentation - Utility Miscellaneous System | Not Started | No | 0,0 | 2015-09-09T08:00:00 | 2015-12-22T16:00:00 |
View Details | M3770 | Final Documentation - Gas Well System | Not Started | No | 0,0 | 2015-07-30T08:00:00 | 2015-11-11T16:00:00 |
View Details | M3895 | Final Documentation - Well Flowlines System | Not Started | No | 0,0 | 2015-07-05T08:00:00 | 2015-10-17T16:00:00 |
View Details | M3930 | Final Documentation - Flare System | Not Started | No | 0,0 | 2015-09-23T08:00:00 | 2016-01-05T16:00:00 |
View Details | M3940 | Final Documentation - Produced Water Treatment System and Evaporation Pond | Not Started | No | 0,0 | 2015-09-23T08:00:00 | 2016-01-05T16:00:00 |
View Details | M3950 | Final Documentation - Fuel Gas System | Not Started | No | 0,0 | 2015-09-23T08:00:00 | 2016-01-05T16:00:00 |
View Details | M3970 | Final Documentation - Chlorination System | Not Started | No | 0,0 | 2015-07-04T08:00:00 | 2015-10-15T16:00:00 |
View Details | M3990 | Final Documentation - Industrial Water System | Not Started | No | 0,0 | 2015-07-04T08:00:00 | 2015-10-15T16:00:00 |
View Details | M4000 | Final Documentation - Fresh / Potable / Demin Water System | Not Started | No | 0,0 | 2015-07-04T08:00:00 | 2015-10-15T16:00:00 |
View Details | M4010 | Final Documentation - Open Drains System | Not Started | No | 0,0 | 2015-07-04T08:00:00 | 2015-10-15T16:00:00 |
View Details | M4020 | Final Documentation - Closed Drains System | Not Started | No | 0,0 | 2015-07-04T08:00:00 | 2015-10-15T16:00:00 |
View Details | M4030 | Final Documentation - Diesel Oil System | Not Started | No | 0,0 | 2015-07-04T08:00:00 | 2015-10-15T16:00:00 |
View Details | M4040 | Final Documentation - Instrument and Plant Air System | Not Started | No | 0,0 | 2015-07-18T08:00:00 | 2015-10-29T16:00:00 |
View Details | M4050 | Final Documentation - Inert Gas (Nitrogen) System | Not Started | No | 0,0 | 2015-07-18T08:00:00 | 2015-10-29T16:00:00 |
View Details | M4060 | Final Documentation - Sewage Water System | Not Started | No | 0,0 | 2015-07-04T08:00:00 | 2015-10-15T16:00:00 |
View Details | M4070 | Final Documentation - Fire Water System | Not Started | No | 0,0 | 2015-07-04T08:00:00 | 2015-10-15T16:00:00 |
View Details | M4080 | Final Documentation - Main Power Generation System | Not Started | Yes | 0,0 | 2015-11-18T08:00:00 | 2016-03-01T16:00:00 |
View Details | M4090 | Final Documentation - Emergency Power Generators System | Not Started | No | 0,0 | 2015-07-04T08:00:00 | 2015-10-15T16:00:00 |
View Details | M4132608 | Mechanical Completion - System 570 | Not Started | Yes | 0,0 | 2015-06-17T16:00:00 | 2015-06-17T16:00:00 |
View Details | M4132602 | Piping - Cosed Drains System | Not Started | No | 0,0 | 2015-02-23T08:00:00 | 2015-05-24T16:00:00 |
View Details | M4132609 | Hydrotest | Not Started | Yes | 0,0 | 2015-06-11T08:00:00 | 2015-06-17T16:00:00 |
View Details | M4132601 | Prefabrication | Not Started | Yes | 0,0 | 2014-12-25T08:00:00 | 2015-02-22T16:00:00 |
View Details | M4132603 | Mechanical / Equipment - Cosed Drains System | Not Started | Yes | 0,0 | 2015-03-12T08:00:00 | 2015-06-10T16:00:00 |
View Details | M4132604 | Electrical - Cosed Drains System | Not Started | Yes | 0,0 | 2015-04-27T08:00:00 | 2015-06-17T16:00:00 |
View Details | M4132605 | Instrumentation & Telecomm - Cosed Drains System | Not Started | Yes | 0,0 | 2015-04-27T08:00:00 | 2015-06-17T16:00:00 |
View Details | M4132606 | Paiting & Insulation - Cosed Drains System | Not Started | No | 0,0 | 2015-06-18T08:00:00 | 2015-07-01T16:00:00 |
View Details | M4132607 | Pre-commissioning - Cosed Drains System | Not Started | No | 0,0 | 2015-06-18T08:00:00 | 2015-07-15T16:00:00 |
View Details | M4131808 | Mechanical Completion - System 440 | Not Started | Yes | 0,0 | 2015-10-06T16:00:00 | 2015-10-06T16:00:00 |
View Details | M4131800 | Civil Works - Evaporation pond | Not Started | No | 0,0 | 2014-08-31T08:00:00 | 2014-12-13T16:00:00 |
View Details | M4131802 | Piping - Produced Water and Evaporation Pond System | Not Started | No | 0,0 | 2015-04-30T08:00:00 | 2015-07-29T16:00:00 |
View Details | M4131809 | Hydrotest | Not Started | Yes | 0,0 | 2015-09-30T08:00:00 | 2015-10-06T16:00:00 |
View Details | M4131801 | Prefabrication | Not Started | Yes | 0,0 | 2015-03-01T08:00:00 | 2015-04-29T16:00:00 |
View Details | M4131804 | Electrical - Produced Water and Evaporation Pond System | Not Started | Yes | 0,0 | 2015-09-12T08:00:00 | 2015-10-05T16:00:00 |
View Details | M4131805 | Instrumentation & Telecomm - Produced Water and Evaporation Pond System | Not Started | No | 0,0 | 2015-09-12T08:00:00 | 2015-10-05T16:00:00 |
View Details | M4131806 | Paiting & Insulation - Produced Water and Evaporation Pond System | Not Started | No | 0,0 | 2015-10-07T08:00:00 | 2015-10-20T16:00:00 |
View Details | M4131807 | Pre-commissioning - Produced Water and Evaporation Pond System | Not Started | No | 0,0 | 2015-10-07T08:00:00 | 2015-10-27T16:00:00 |
View Details | M4131803 | Mechanical / Equipment - Produced Water System | Not Started | Yes | 0,0 | 2015-08-05T08:00:00 | 2015-09-29T16:00:00 |
View Details | M4131308 | Mechanical Completion - System 330 | Not Started | Yes | 0,0 | 2015-10-03T16:00:00 | 2015-10-03T16:00:00 |
View Details | M4131307 | Pre-commissioning - Condensate Storage and Metering System | Not Started | Yes | 0,0 | 2015-10-04T08:00:00 | 2015-10-24T16:00:00 |
View Details | M4131304 | Electrical - Condensate Storage and Metering System | Not Started | Yes | 0,0 | 2015-06-21T08:00:00 | 2015-10-03T16:00:00 |
View Details | M4131302 | Piping - Condensate Storage and Metering System | Not Started | No | 0,0 | 2015-01-19T08:00:00 | 2015-04-19T16:00:00 |
View Details | M4131309 | Hydrotest | Not Started | Yes | 0,0 | 2015-09-27T08:00:00 | 2015-10-03T16:00:00 |
View Details | M4131300 | Prefabrication (70%) | Not Started | Yes | 0,0 | 2014-12-20T08:00:00 | 2015-01-18T16:00:00 |
View Details | M4131301 | Prefabrication (100%) | Not Started | No | 0,0 | 2015-01-11T08:00:00 | 2015-02-09T16:00:00 |
View Details | M4131305 | Instrumentation & Telecomm - Condensate Storage and Metering System | Not Started | Yes | 0,0 | 2015-06-21T08:00:00 | 2015-10-03T16:00:00 |
View Details | M4131306 | Paiting & Insulation - Metering System | Not Started | No | 0,0 | 2015-10-04T08:00:00 | 2015-10-17T16:00:00 |
View Details | M4134097 | Paiting & Insulation - Condensate Storage | Not Started | No | 0,0 | 2015-06-21T08:00:00 | 2015-07-04T16:00:00 |
View Details | M4131303 | Mechanical / Equipment - Condensate Storage | Not Started | Yes | 0,0 | 2015-04-21T08:00:00 | 2015-06-08T16:00:00 |
View Details | M4131310 | Mechanical / Equipment - Metering System | Not Started | Yes | 0,0 | 2015-07-14T08:00:00 | 2015-09-26T16:00:00 |
View Details | M4131311 | Hydrotest - Condensate Storage | Not Started | Yes | 0,0 | 2015-06-09T08:00:00 | 2015-06-20T16:00:00 |
View Details | M413408 | Mechanical Completion - System 220A | Not Started | Yes | 0,0 | 2015-07-13T16:00:00 | 2015-07-13T16:00:00 |
View Details | M413402 | Piping - Gas Reception System | Not Started | Yes | 0,0 | 2015-01-03T08:00:00 | 2015-04-02T16:00:00 |
View Details | M413409 | Hydrotest | Not Started | No | 0,0 | 2015-04-03T08:00:00 | 2015-04-08T16:00:00 |
View Details | M413401 | Prefabrication | Not Started | No | 0,0 | 2014-11-03T08:00:00 | 2015-01-01T16:00:00 |
View Details | M413404 | Electrical - Gas Reception System | Not Started | Yes | 0,0 | 2015-02-18T08:00:00 | 2015-07-13T16:00:00 |
View Details | M413405 | Instrumentation & Telecommunication - Gas Reception System | Not Started | Yes | 0,0 | 2015-02-18T08:00:00 | 2015-07-13T16:00:00 |
View Details | M413407 | Pre-commissioning - Gas Reception System (Line 1-3) | Not Started | No | 0,0 | 2015-08-29T08:00:00 | 2015-09-24T16:00:00 |
View Details | M413411 | Pre-commissioning - Gas Reception System (Line 4-6) | Not Started | No | 0,0 | 2015-09-13T08:00:00 | 2015-10-10T16:00:00 |
View Details | M413412 | Pre-commissioning - Gas Reception System (Line 7-9) | Not Started | Yes | 0,0 | 2015-10-11T08:00:00 | 2015-11-07T16:00:00 |
View Details | M413403 | Mechanical / Equipment - Gas Reception System | Not Started | Yes | 0,0 | 2015-04-14T08:00:00 | 2015-07-13T16:00:00 |
View Details | M413406 | Paiting & Insulation - Gas Reception System | Not Started | No | 0,0 | 2015-07-14T08:00:00 | 2015-07-27T16:00:00 |
View Details | M4131408 | Mechanical Completion - System 400 | Not Started | Yes | 0,0 | 2015-09-28T16:00:00 | 2015-09-28T16:00:00 |
View Details | M4131402 | Piping - Cooling Medium (Propane) System | Not Started | No | 0,0 | 2015-02-23T08:00:00 | 2015-05-24T16:00:00 |
View Details | M4131409 | Hydrotest | Not Started | No | 0,0 | 2015-08-18T08:00:00 | 2015-08-23T16:00:00 |
View Details | M4131401 | Prefabrication | Not Started | Yes | 0,0 | 2014-12-25T08:00:00 | 2015-02-22T16:00:00 |
View Details | M4131404 | Electrical - Cooling Medium (Propane) System | Not Started | Yes | 0,0 | 2015-08-11T08:00:00 | 2015-09-28T16:00:00 |
View Details | M4131405 | Instrumentation & Telecomm - Cooling Medium (Propane) System | Not Started | Yes | 0,0 | 2015-08-11T08:00:00 | 2015-09-28T16:00:00 |
View Details | M4131406 | Paiting & Insulation - Cooling Medium (Propane) System | Not Started | No | 0,0 | 2015-09-29T08:00:00 | 2015-10-12T16:00:00 |
View Details | M4131403 | Mechanical / Equipment - Cooling Medium (Propane) System | Not Started | Yes | 0,0 | 2015-08-11T08:00:00 | 2015-09-28T16:00:00 |
View Details | M4131407 | Pre-commissioning - Cooling Medium (Propane) System | Not Started | No | 0,0 | 2015-09-29T08:00:00 | 2015-10-12T16:00:00 |
View Details | M411401 | Site Prepn.,Soil Stabilization,Grading etc. | Not Started | No | 0,0 | 2014-06-19T08:00:00 | 2014-10-01T16:00:00 |
View Details | M411104 | Contractor's Site Offices / Field Offices | Not Started | No | 0,0 | 2014-06-02T08:00:00 | 2014-08-10T16:00:00 |
View Details | M411111 | Personnel Camp Accomodation | Not Started | Yes | 0,0 | 2014-06-02T08:00:00 | 2014-08-10T16:00:00 |
View Details | M411101 | Access Roads & Parkings | Not Started | Yes | 0,0 | 2014-05-01T08:00:00 | 2014-06-01T16:00:00 |
View Details | M411113 | Warehouses & Laydown Areas | Not Started | No | 0,0 | 2014-06-19T08:00:00 | 2014-08-27T16:00:00 |
View Details | M411108 | Maintenance Shops | Not Started | No | 0,0 | 2014-07-24T08:00:00 | 2014-10-01T16:00:00 |
View Details | M411103 | Concrete Batching Plant | Not Started | No | 0,0 | 2014-06-02T08:00:00 | 2014-08-10T16:00:00 |
View Details | M411110 | Personnel & Materials Transport | Not Started | No | 0,0 | 2014-06-02T08:00:00 | 2014-06-25T16:00:00 |
View Details | M411112 | Utilities | Not Started | No | 0,0 | 2014-06-19T08:00:00 | 2014-08-27T16:00:00 |
View Details | M411105 | Crane Installation | Not Started | No | 0,0 | 2014-07-07T08:00:00 | 2014-08-31T16:00:00 |
View Details | M411102 | Camp 1st Occupancy | Not Started | Yes | 0,0 | 2014-06-02T08:00:00 | 2014-06-02T08:00:00 |
View Details | M411106 | Fabrication & Testing Facilities | Not Started | No | 0,0 | 2014-07-24T08:00:00 | 2014-08-27T16:00:00 |
View Details | M411109 | Medical Facilities | Not Started | No | 0,0 | 2014-07-07T08:00:00 | 2014-08-10T16:00:00 |
View Details | M411107 | Fire & Safety Facilities | Not Started | No | 0,0 | 2014-07-24T08:00:00 | 2014-08-27T16:00:00 |
View Details | M411114 | Waste Management Facilities | Not Started | No | 0,0 | 2014-06-19T08:00:00 | 2014-07-23T16:00:00 |
View Details | M411201 | Field Engineering works | Not Started | No | 0,0 | 2014-07-24T08:00:00 | 2015-09-10T16:00:00 |
View Details | M411301 | Mob. Complete Contruction Management Team | Not Started | Yes | 0,0 | 2014-06-02T08:00:00 | 2014-07-02T16:00:00 |
View Details | M411302 | Mob. Electrical Subcontractor | Not Started | No | 0,0 | 2014-07-03T08:00:00 | 2014-08-06T16:00:00 |
View Details | M411303 | Mob. Eqpt. Erection Subcontractors | Not Started | No | 0,0 | 2014-07-03T08:00:00 | 2014-08-06T16:00:00 |
View Details | M411316 | Mobilization Complete major works | Not Started | No | 0,0 | 2014-07-03T08:00:00 | 2014-08-06T16:00:00 |
View Details | M411314 | Mob.1st Project Management Team | Not Started | No | 0,0 | 2014-07-03T08:00:00 | 2014-08-06T16:00:00 |
View Details | M411304 | Mob. Hydrotest Subcontractors | Not Started | No | 0,0 | 2014-07-03T08:00:00 | 2014-08-06T16:00:00 |
View Details | M411310 | Mob. Project Management Team | Not Started | No | 0,0 | 2014-07-03T08:00:00 | 2014-08-06T16:00:00 |
View Details | M411305 | Mob. Instru & Control Sys. Subcontractor | Not Started | No | 0,0 | 2014-07-03T08:00:00 | 2014-08-06T16:00:00 |
View Details | M411308 | Mob. Pipeline Team | Not Started | No | 0,0 | 2014-07-03T08:00:00 | 2014-08-06T16:00:00 |
View Details | M411311 | Mob. Site Preparation Sub-contractor | Not Started | No | 0,0 | 2014-07-03T08:00:00 | 2014-08-06T16:00:00 |
View Details | M411307 | Mob. Painting/Lining S/Cr | Not Started | No | 0,0 | 2014-07-03T08:00:00 | 2014-08-06T16:00:00 |
View Details | M411312 | Mob. Steel Structure Subcontractor | Not Started | No | 0,0 | 2014-07-03T08:00:00 | 2014-08-06T16:00:00 |
View Details | M411306 | Mob. Insulation/Fireproofing S/Cr | Not Started | No | 0,0 | 2014-07-03T08:00:00 | 2014-08-06T16:00:00 |
View Details | M411309 | Mob. Piping Subcontractors | Not Started | No | 0,0 | 2014-07-03T08:00:00 | 2014-08-06T16:00:00 |
View Details | M411313 | Mob. Temp. Facilities Sub-contractors | Not Started | No | 0,0 | 2014-07-03T08:00:00 | 2014-08-06T16:00:00 |
View Details | M411315 | Mob.Tank Foundation & Erection Teams | Not Started | No | 0,0 | 2014-07-03T08:00:00 | 2014-08-06T16:00:00 |
View Details | M411501 | Civil Roads & Drains Tie-ins | Not Started | No | 0,0 | 2014-07-01T08:00:00 | 2014-08-27T16:00:00 |
View Details | M411502 | E & I & Telecomm. Tie-ins | Not Started | No | 0,0 | 2014-07-01T08:00:00 | 2014-08-27T16:00:00 |
View Details | M4133308 | Mechanical Completion - System 830 | Not Started | Yes | 0,0 | 2015-05-31T16:00:00 | 2015-05-31T16:00:00 |
View Details | M4133302 | Piping - Emergency Power Generator | Not Started | Yes | 0,0 | 2015-02-23T08:00:00 | 2015-05-24T16:00:00 |
View Details | M4133309 | Hydrotest | Not Started | Yes | 0,0 | 2015-05-25T08:00:00 | 2015-05-31T16:00:00 |
View Details | M4133301 | Prefabrication | Not Started | Yes | 0,0 | 2014-12-25T08:00:00 | 2015-02-22T16:00:00 |
View Details | M4133303 | Mechanical / Equipment - Emergency Power Generator | Not Started | Yes | 0,0 | 2015-02-16T08:00:00 | 2015-05-17T16:00:00 |
View Details | M4133304 | Electrical - Emergency Power Generator | Not Started | Yes | 0,0 | 2015-04-02T08:00:00 | 2015-05-31T16:00:00 |
View Details | M4133306 | Paiting & Insulation - Emergency Power Generator | Not Started | No | 0,0 | 2015-06-01T08:00:00 | 2015-06-14T16:00:00 |
View Details | M4133307 | Pre-commissioning - Emergency Power Generator | Not Started | No | 0,0 | 2015-06-01T08:00:00 | 2015-06-28T16:00:00 |
View Details | M4133305 | Instrumentation & Telecomm - Emergency Power Generator | Not Started | Yes | 0,0 | 2015-04-02T08:00:00 | 2015-05-31T16:00:00 |
View Details | M4132808 | Mechanical Completion - System 630 | Not Started | Yes | 0,0 | 2015-09-21T16:00:00 | 2015-09-21T16:00:00 |
View Details | M4132802 | Piping - Instrument & Plant Air System | Not Started | Yes | 0,0 | 2015-06-16T08:00:00 | 2015-09-14T16:00:00 |
View Details | M4132809 | Hydrotest | Not Started | Yes | 0,0 | 2015-09-15T08:00:00 | 2015-09-21T16:00:00 |
View Details | M4132801 | Prefabrication | Not Started | Yes | 0,0 | 2015-04-17T08:00:00 | 2015-06-15T16:00:00 |
View Details | M4132803 | Mechanical / Equipment - Instrument & Plant Air System | Not Started | Yes | 0,0 | 2015-06-10T08:00:00 | 2015-09-08T16:00:00 |
View Details | M4132805 | Instrumentation & Telecomm - Instrument & Plant Air System | Not Started | Yes | 0,0 | 2015-07-26T08:00:00 | 2015-09-21T16:00:00 |
View Details | M4132806 | Paiting & Insulation - Instrument & Plant Air System | Not Started | No | 0,0 | 2015-09-22T08:00:00 | 2015-10-05T16:00:00 |
View Details | M4132804 | Electrical - Instrument & Plant Air System | Not Started | Yes | 0,0 | 2015-07-26T08:00:00 | 2015-09-21T16:00:00 |
View Details | M4132807 | Pre-Commissioning - Instrument & Plant Air System | Not Started | No | 0,0 | 2015-09-22T08:00:00 | 2015-10-15T16:00:00 |
View Details | M413608 | Mechanical Completion - System 220B | Not Started | Yes | 0,0 | 2015-07-13T16:00:00 | 2015-07-13T16:00:00 |
View Details | M413602 | Piping - Gas Separation System | Not Started | Yes | 0,0 | 2015-01-03T08:00:00 | 2015-04-02T16:00:00 |
View Details | M413609 | Hydrotest | Not Started | No | 0,0 | 2015-04-03T08:00:00 | 2015-04-08T16:00:00 |
View Details | M413601 | Prefabrication | Not Started | No | 0,0 | 2014-11-03T08:00:00 | 2015-01-01T16:00:00 |
View Details | M413604 | Electrical - Gas Separation System | Not Started | Yes | 0,0 | 2015-02-18T08:00:00 | 2015-07-13T16:00:00 |
View Details | M413605 | Instrumentation & Telecommunication - Gas Separation System | Not Started | Yes | 0,0 | 2015-02-18T08:00:00 | 2015-07-13T16:00:00 |
View Details | M413603 | Mechanical / Equipment - Gas Separation System | Not Started | Yes | 0,0 | 2015-04-14T08:00:00 | 2015-07-13T16:00:00 |
View Details | M413606 | Paiting & Insulation - Gas Separation System | Not Started | No | 0,0 | 2015-07-14T08:00:00 | 2015-07-27T16:00:00 |
View Details | M413607 | Pre-commissioning - Gas Separation System | Not Started | No | 0,0 | 2015-08-22T08:00:00 | 2015-10-31T16:00:00 |
View Details | M412101 | Right of way (line 1-3) | Not Started | Yes | 0,0 | 2014-11-29T08:00:00 | 2015-03-29T16:00:00 |
View Details | M412102 | Pipe stringing (line 1-3) | Not Started | Yes | 0,0 | 2014-12-06T08:00:00 | 2015-04-05T16:00:00 |
View Details | M412103 | Trenching (line 1-3) | Not Started | Yes | 0,0 | 2014-12-04T08:00:00 | 2015-04-04T16:00:00 |
View Details | M412104 | Laying (line 1-3) | Not Started | Yes | 0,0 | 2014-12-07T08:00:00 | 2015-04-06T16:00:00 |
View Details | M412105 | Lowring-in (line 1-3) | Not Started | No | 0,0 | 2014-12-08T08:00:00 | 2015-04-07T16:00:00 |
View Details | M412116 | Hydrotest | Not Started | Yes | 0,0 | 2015-09-27T08:00:00 | 2015-10-17T16:00:00 |
View Details | M412100 | Mechanical Completion - System 360 | Not Started | No | 0,0 | 2015-10-17T16:00:00 | 2015-10-17T16:00:00 |
View Details | M412106 | Right of way (line 4-6) | Not Started | Yes | 0,0 | 2015-01-27T08:00:00 | 2015-05-27T16:00:00 |
View Details | M412107 | Pipe stringing (line 4-6) | Not Started | Yes | 0,0 | 2015-02-03T08:00:00 | 2015-06-03T16:00:00 |
View Details | M412108 | Trenching (line 4-6) | Not Started | Yes | 0,0 | 2015-02-02T08:00:00 | 2015-06-02T16:00:00 |
View Details | M412109 | Laying (line 4-6) | Not Started | Yes | 0,0 | 2015-02-04T08:00:00 | 2015-06-04T16:00:00 |
View Details | M412110 | Lowring-in (line 4-6) | Not Started | No | 0,0 | 2015-02-05T08:00:00 | 2015-06-06T16:00:00 |
View Details | M412111 | Right of way (line 7-9) | Not Started | Yes | 0,0 | 2015-03-29T08:00:00 | 2015-07-27T16:00:00 |
View Details | M412112 | Pipe stringing (line 7-9) | Not Started | Yes | 0,0 | 2015-04-05T08:00:00 | 2015-08-03T16:00:00 |
View Details | M412113 | Trenching (line 7-9) | Not Started | Yes | 0,0 | 2015-04-04T08:00:00 | 2015-08-02T16:00:00 |
View Details | M412114 | Laying (line 7-9) | Not Started | Yes | 0,0 | 2015-04-06T08:00:00 | 2015-08-04T16:00:00 |
View Details | M412115 | Lowring-in (line 7-9) | Not Started | No | 0,0 | 2015-04-07T08:00:00 | 2015-08-05T16:00:00 |
View Details | M413508 | Mechanical Completion - System 210 | Not Started | Yes | 0,0 | 2015-07-27T16:00:00 | 2015-07-27T16:00:00 |
View Details | M413502 | Piping - Test Separation and Metering System | Not Started | Yes | 0,0 | 2015-01-12T08:00:00 | 2015-04-23T16:00:00 |
View Details | M413509 | Hydrotest | Not Started | No | 0,0 | 2015-04-25T08:00:00 | 2015-04-30T16:00:00 |
View Details | M413500 | Prefabrication 60% | Not Started | Yes | 0,0 | 2014-11-03T08:00:00 | 2015-01-11T16:00:00 |
View Details | M413501 | Prefabrication 100% in MIG Workshop | Not Started | No | 0,0 | 2014-12-25T08:00:00 | 2015-03-04T16:00:00 |
View Details | M413504 | Electrical - Test Separation and Metering System | Not Started | Yes | 0,0 | 2015-06-16T08:00:00 | 2015-07-27T16:00:00 |
View Details | M413505 | Instrumentation & Telecommunication - Test Separation and Metering System | Not Started | Yes | 0,0 | 2015-06-16T08:00:00 | 2015-07-27T16:00:00 |
View Details | M413507 | Pre-commissioning - Test Separation and Metering System | Not Started | No | 0,0 | 2015-07-28T08:00:00 | 2015-08-24T16:00:00 |
View Details | M413503 | Mechanical / Equipment - Test Separation and Metering System | Not Started | Yes | 0,0 | 2015-05-05T08:00:00 | 2015-07-27T16:00:00 |
View Details | M413506 | Paiting & Insulation - Test Separation and Metering System | Not Started | No | 0,0 | 2015-07-28T08:00:00 | 2015-11-09T16:00:00 |
View Details | M4132908 | Mechanical Completion - System 640 | Not Started | Yes | 0,0 | 2015-09-21T16:00:00 | 2015-09-21T16:00:00 |
View Details | M4132902 | Piping - Inert Gas (Nitrogen) System | Not Started | No | 0,0 | 2015-03-02T08:00:00 | 2015-05-31T16:00:00 |
View Details | M4133909 | Hydrotest | Not Started | Yes | 0,0 | 2015-09-15T08:00:00 | 2015-09-21T16:00:00 |
View Details | M4133901 | Prefabrication | Not Started | Yes | 0,0 | 2015-01-01T08:00:00 | 2015-03-01T16:00:00 |
View Details | M4132903 | Mechanical / Equipment - Inert Gas (Nitrogen) System | Not Started | Yes | 0,0 | 2015-06-16T08:00:00 | 2015-09-14T16:00:00 |
View Details | M4132905 | Instrumentation & Telecomm - Inert Gas (Nitrogen) System | Not Started | Yes | 0,0 | 2015-08-01T08:00:00 | 2015-09-21T16:00:00 |
View Details | M4132904 | Electrical - Inert Gas (Nitrogen) System | Not Started | Yes | 0,0 | 2015-08-01T08:00:00 | 2015-09-21T16:00:00 |
View Details | M4132906 | Paiting & Insulation - Inert Gas (Nitrogen) System | Not Started | No | 0,0 | 2015-09-22T08:00:00 | 2015-10-05T16:00:00 |
View Details | M4132907 | Pre-Commissioning - Nitrogen System | Not Started | No | 0,0 | 2015-09-22T08:00:00 | 2015-10-15T16:00:00 |
View Details | M413708 | Mechanical Completion - System 232 | Not Started | Yes | 0,0 | 2015-09-28T16:00:00 | 2015-09-28T16:00:00 |
View Details | M413702 | Piping - Offgas Compression System | Not Started | Yes | 0,0 | 2015-04-25T08:00:00 | 2015-07-23T16:00:00 |
View Details | M413709 | Hydrotest | Not Started | No | 0,0 | 2015-07-24T08:00:00 | 2015-07-29T16:00:00 |
View Details | M413701 | Prefabrication | Not Started | No | 0,0 | 2015-02-23T08:00:00 | 2015-04-23T16:00:00 |
View Details | M413705 | Instrumentation & Telecommunication - Offgas Compression System | Not Started | Yes | 0,0 | 2015-08-11T08:00:00 | 2015-09-28T16:00:00 |
View Details | M413706 | Paiting & Insulation - Offgas Compression System | Not Started | No | 0,0 | 2015-09-29T08:00:00 | 2015-11-02T16:00:00 |
View Details | M413703 | Mechanical / Equipment - Offgas Compression System | Not Started | Yes | 0,0 | 2015-08-11T08:00:00 | 2015-09-28T16:00:00 |
View Details | M413704 | Electrical - Offgas Compression System | Not Started | Yes | 0,0 | 2015-08-11T08:00:00 | 2015-09-28T16:00:00 |
View Details | M413707 | Pre-commissioning - Offgas Compression System | Not Started | No | 0,0 | 2015-09-29T08:00:00 | 2015-10-26T16:00:00 |
View Details | M4132408 | Mechanical Completion - System 530 | Not Started | Yes | 0,0 | 2015-06-01T16:00:00 | 2015-06-01T16:00:00 |
View Details | M4132402 | Piping - Fresh and Demin Water System | Not Started | Yes | 0,0 | 2015-03-25T08:00:00 | 2015-05-26T16:00:00 |
View Details | M4132409 | Hydrotest | Not Started | Yes | 0,0 | 2015-05-27T08:00:00 | 2015-06-01T16:00:00 |
View Details | M4132401 | Prefabrication | Not Started | Yes | 0,0 | 2015-01-24T08:00:00 | 2015-03-24T16:00:00 |
View Details | M4132403 | Mechanical / Equipment - Fresh and Demin Water System | Not Started | Yes | 0,0 | 2015-03-18T08:00:00 | 2015-05-19T16:00:00 |
View Details | M4132404 | Electrical - Fresh and Demin Water System | Not Started | Yes | 0,0 | 2015-04-19T08:00:00 | 2015-06-01T16:00:00 |
View Details | M4132405 | Instrumentation & Telecomm - Fresh and Demin Water System | Not Started | Yes | 0,0 | 2015-04-19T08:00:00 | 2015-06-01T16:00:00 |
View Details | M4132406 | Paiting & Insulation - Fresh and Demin Water System | Not Started | No | 0,0 | 2015-06-02T08:00:00 | 2015-10-19T16:00:00 |
View Details | M4132407 | Pre-Commissioning - Fresh Water System | Not Started | No | 0,0 | 2015-06-02T08:00:00 | 2015-06-22T16:00:00 |
View Details | M4132410 | Pre-Commissioning - Demin Water System | Not Started | No | 0,0 | 2015-06-02T08:00:00 | 2015-06-22T16:00:00 |
View Details | M4132108 | Mechanical Completion - System 470 | Not Started | Yes | 0,0 | 2015-06-29T16:00:00 | 2015-06-29T16:00:00 |
View Details | M4132102 | Piping - Chlorination System | Not Started | Yes | 0,0 | 2015-03-25T08:00:00 | 2015-06-23T16:00:00 |
View Details | M4132109 | Hydrotest | Not Started | Yes | 0,0 | 2015-06-24T08:00:00 | 2015-06-29T16:00:00 |
View Details | M4132101 | Prefabrication | Not Started | Yes | 0,0 | 2015-01-24T08:00:00 | 2015-03-24T16:00:00 |
View Details | M4132103 | Mechanical / Equipment - Chlorination System | Not Started | Yes | 0,0 | 2015-03-18T08:00:00 | 2015-06-16T16:00:00 |
View Details | M4132105 | Instrumentation & Telecomm - Chlorination System | Not Started | No | 0,0 | 2015-05-03T08:00:00 | 2015-06-27T16:00:00 |
View Details | M4132106 | Paiting & Insulation - Chlorination System | Not Started | No | 0,0 | 2015-06-30T08:00:00 | 2015-07-13T16:00:00 |
View Details | M4132104 | Electrical - Chlorination System | Not Started | Yes | 0,0 | 2015-05-03T08:00:00 | 2015-06-29T16:00:00 |
View Details | M4132107 | Pre-Commissioning - Chlorination System | Not Started | No | 0,0 | 2015-06-30T08:00:00 | 2015-07-27T16:00:00 |
View Details | J1850 | Erection - Plant Communication and Visualization System | Not Started | Yes | 0,0 | 2015-04-02T08:00:00 | 2015-06-30T16:00:00 |
View Details | J1860 | Commissioning - Plant Communication and Visualization System | Not Started | No | 0,0 | 2015-06-01T08:00:00 | 2015-08-29T16:00:00 |
View Details | J1570 | Erection - Small Power System (Ende 1. civil - start letzte civil works-4w Dauer anpassen) | Not Started | Yes | 0,0 | 2015-05-12T08:00:00 | 2015-06-18T12:00:00 |
View Details | J1580 | Commissioning - Small Power System | Not Started | No | 0,0 | 2015-06-18T12:00:00 | 2015-07-25T16:00:00 |
View Details | J1660 | Erection - UPS 230V AC | Not Started | Yes | 0,0 | 2015-04-02T08:00:00 | 2015-05-31T16:00:00 |
View Details | J1670 | Pre-Commissioning - UPS 230V AC | Not Started | Yes | 0,0 | 2015-06-01T08:00:00 | 2015-06-30T16:00:00 |
View Details | J1680 | Ready for Energizing - UPS 230V AC | Not Started | No | 0,0 | 2015-07-01T08:00:00 | 2015-07-01T08:00:00 |
View Details | J1760 | Erection - Lighting and Grounding System (Start 1. civil excavation - Ende letzte civil Dauer anpassen) | Not Started | Yes | 0,0 | 2014-12-03T08:00:00 | 2015-01-09T12:00:00 |
View Details | J1770 | Commissioning - Lighting and Grounding System | Not Started | No | 0,0 | 2015-01-09T12:00:00 | 2015-01-16T12:00:00 |
View Details | J1930 | Erection - Cables and Cable Trays (mit 1. Rohrbr�cke Trays; Kabel im electrical substation Geb�ude; Ende letztes Sys) | Not Started | Yes | 0,0 | 2015-02-01T08:00:00 | 2015-03-10T12:00:00 |
View Details | J1940 | Pre-Commissioning - Cables and Cable Trays (gleiche duration wie erection +1M Versatz) | Not Started | No | 0,0 | 2015-03-03T08:00:00 | 2015-04-09T16:00:00 |
View Details | J2020 | Erection - ICSS System | Not Started | Yes | 0,0 | 2015-04-24T12:00:00 | 2015-05-24T12:00:00 |
View Details | J2030 | Pre-Commissioning - ICSS System (�ber pre und hot verteilen) | Not Started | Yes | 0,0 | 2015-05-24T12:00:00 | 2016-01-03T16:00:00 |
View Details | J1170 | Erection - LV System 400V | Not Started | Yes | 0,0 | 2015-05-02T08:00:00 | 2015-07-30T16:00:00 |
View Details | J1180 | Pre-Commissioning - LV System 400V | Not Started | Yes | 0,0 | 2015-07-31T08:00:00 | 2015-08-29T16:00:00 |
View Details | J1190 | Ready for Energizing - LV System 400V | Not Started | No | 0,0 | 2015-08-30T08:00:00 | 2015-08-30T08:00:00 |
View Details | J2210 | Erection - Field Cabling (1M nach Kabeltrassen - ROHRBR�CKENau�en MIG), kabeltrassen innen | Not Started | Yes | 0,0 | 2015-01-24T12:00:00 | 2015-03-02T16:00:00 |
View Details | J2220 | Pre-Commissioning - Field Cabling | Not Started | No | 0,0 | 2015-03-03T08:00:00 | 2015-05-16T16:00:00 |
View Details | J1070 | Erection - MV System 6.6kV | Not Started | Yes | 0,0 | 2015-04-02T08:00:00 | 2015-05-31T16:00:00 |
View Details | J1080 | Pre-Commissioning - MV System 6.6kV | Not Started | Yes | 0,0 | 2015-06-01T08:00:00 | 2015-06-30T16:00:00 |
View Details | J1090 | Ready for Energizing - MV System 6.6kV | Not Started | No | 0,0 | 2015-07-01T08:00:00 | 2015-07-01T08:00:00 |
View Details | J1270 | Erection - LV Trafos | Not Started | Yes | 0,0 | 2015-03-03T08:00:00 | 2015-04-01T16:00:00 |
View Details | J1280 | Pre-Commissioning - LV Trafos | Not Started | Yes | 0,0 | 2015-04-02T08:00:00 | 2015-04-22T16:00:00 |
View Details | J1290 | Ready for Energizing - LV Trafos | Not Started | No | 0,0 | 2015-04-23T08:00:00 | 2015-04-23T08:00:00 |
View Details | J1370 | Erection - Frequency Inverter | Not Started | Yes | 0,0 | 2015-02-01T08:00:00 | 2015-02-14T16:00:00 |
View Details | J1380 | Pre-Commissioning - Frequency Inverter | Not Started | No | 0,0 | 2015-02-15T08:00:00 | 2015-02-28T16:00:00 |
View Details | J1470 | Erection - Battery System 220V DC | Not Started | Yes | 0,0 | 2015-05-02T08:00:00 | 2015-06-30T16:00:00 |
View Details | J1480 | Pre-Commissioning - Battery System 220V DC | Not Started | Yes | 0,0 | 2015-07-01T08:00:00 | 2015-07-30T16:00:00 |
View Details | J1490 | Ready for Energizing - Battery System 220V DC | Not Started | No | 0,0 | 2015-07-31T08:00:00 | 2015-07-31T08:00:00 |
View Details | M4131708 | Mechanical Completion - System 430 | Not Started | Yes | 0,0 | 2015-09-06T16:00:00 | 2015-09-06T16:00:00 |
View Details | M4131702 | Piping - LP/FP Flare system | Not Started | No | 0,0 | 2015-03-02T08:00:00 | 2015-06-07T16:00:00 |
View Details | M4131709 | Hydrotest | Not Started | Yes | 0,0 | 2015-09-01T08:00:00 | 2015-09-06T16:00:00 |
View Details | M4131701 | Prefabrication | Not Started | Yes | 0,0 | 2015-01-01T08:00:00 | 2015-03-01T16:00:00 |
View Details | M4131704 | Electrical - LP/FP Flare system | Not Started | Yes | 0,0 | 2015-07-18T08:00:00 | 2015-09-06T16:00:00 |
View Details | M4131705 | Instrumentation & Telecomm - LP/FP Flare system | Not Started | Yes | 0,0 | 2015-07-18T08:00:00 | 2015-09-06T16:00:00 |
View Details | M4131706 | Paiting & Insulation - LP/FP Flare system | Not Started | No | 0,0 | 2015-09-07T08:00:00 | 2015-10-04T16:00:00 |
View Details | M4131707 | Pre-commissioning - LP/FP Flare system | Not Started | No | 0,0 | 2015-09-07T08:00:00 | 2015-10-04T16:00:00 |
View Details | M4131703 | Mechanical / Equipment - LP/FP Flare system | Not Started | Yes | 0,0 | 2015-06-02T08:00:00 | 2015-08-31T16:00:00 |
View Details | M4131608 | Mechanical Completion - System 420 | Not Started | Yes | 0,0 | 2015-08-16T16:00:00 | 2015-08-16T16:00:00 |
View Details | M4131602 | Piping - Chemical Injection System | Not Started | No | 0,0 | 2015-04-30T08:00:00 | 2015-07-29T16:00:00 |
View Details | M4131609 | Hydrotest | Not Started | Yes | 0,0 | 2015-08-11T08:00:00 | 2015-08-16T16:00:00 |
View Details | M4131601 | Prefabrication | Not Started | Yes | 0,0 | 2015-03-01T08:00:00 | 2015-04-29T16:00:00 |
View Details | M4131604 | Elecrical - Chemical Injection System | Not Started | Yes | 0,0 | 2015-06-27T08:00:00 | 2015-08-06T16:00:00 |
View Details | M4131605 | Instrumentation & Telecomm - Chemical Injection System | Not Started | No | 0,0 | 2015-06-27T08:00:00 | 2015-08-06T16:00:00 |
View Details | M4131606 | Paiting & Insulation - Chemical Injection System | Not Started | No | 0,0 | 2015-08-17T08:00:00 | 2015-08-30T16:00:00 |
View Details | M4131607 | Pre-commissioning - Chemical Injection System | Not Started | No | 0,0 | 2015-08-17T08:00:00 | 2015-09-13T16:00:00 |
View Details | M4131603 | Mechanical / Equipment - Chemical Injection System | Not Started | Yes | 0,0 | 2015-05-12T08:00:00 | 2015-08-10T16:00:00 |
View Details | M4133008 | Mechanical Completion - System 660 | Not Started | Yes | 0,0 | 2015-06-17T16:00:00 | 2015-06-17T16:00:00 |
View Details | M4133004 | Electrical - Sewage Water System | Not Started | Yes | 0,0 | 2015-04-27T08:00:00 | 2015-06-17T16:00:00 |
View Details | M4133005 | Instrumentation & Telecomm - Sewage Water System | Not Started | Yes | 0,0 | 2015-04-27T08:00:00 | 2015-06-17T16:00:00 |
View Details | M4133006 | Paiting & Insulation - Sewage Water System | Not Started | No | 0,0 | 2015-06-18T08:00:00 | 2015-07-01T16:00:00 |
View Details | M4133007 | Pre-commissioning - Sewage Water System | Not Started | No | 0,0 | 2015-06-18T08:00:00 | 2015-07-15T16:00:00 |
View Details | M4133002 | Piping - Sewage Water System | Not Started | No | 0,0 | 2015-02-23T08:00:00 | 2015-05-24T16:00:00 |
View Details | M4133009 | Hydrotest | Not Started | Yes | 0,0 | 2015-06-11T08:00:00 | 2015-06-17T16:00:00 |
View Details | M4133001 | Prefabrication | Not Started | Yes | 0,0 | 2014-12-25T08:00:00 | 2015-02-22T16:00:00 |
View Details | M4133003 | Mechanical / Equipment - Sewage Water System | Not Started | Yes | 0,0 | 2015-03-12T08:00:00 | 2015-06-10T16:00:00 |
View Details | M412201 | General leveling | Not Started | Yes | 0,0 | 2014-09-01T08:00:00 | 2014-10-01T16:00:00 |
View Details | M412202 | Fencing & Road | Not Started | Yes | 0,0 | 2014-10-02T08:00:00 | 2014-11-23T16:00:00 |
View Details | M412203 | Concrete Basement of Equipment | Not Started | No | 0,0 | 2014-11-24T08:00:00 | 2015-01-14T16:00:00 |
View Details | M412204 | Equipment Installation (Skid 1-3) | Not Started | Yes | 0,0 | 2015-06-23T08:00:00 | 2015-08-13T16:00:00 |
View Details | M412208 | Piping Interconnection | Not Started | Yes | 0,0 | 2015-06-23T08:00:00 | 2015-08-13T16:00:00 |
View Details | M412206 | Electrical (Skid 1-3) | Not Started | No | 0,0 | 2015-06-30T08:00:00 | 2015-08-15T16:00:00 |
View Details | M412207 | Instrumentation (Skid 1-3) | Not Started | No | 0,0 | 2015-06-30T08:00:00 | 2015-08-15T16:00:00 |
View Details | M412211 | Painting (Skid 1-3) | Not Started | No | 0,0 | 2015-08-22T08:00:00 | 2015-08-27T16:00:00 |
View Details | M412212 | Pre-commissioning (Skid 1-3) | Not Started | Yes | 0,0 | 2015-08-22T08:00:00 | 2015-09-17T16:00:00 |
View Details | M412214 | Equipment Installation (Skid 4-6) | Not Started | Yes | 0,0 | 2015-07-07T08:00:00 | 2015-08-27T16:00:00 |
View Details | M412216 | Electrical (Skid 4-6) | Not Started | Yes | 0,0 | 2015-07-14T08:00:00 | 2015-08-29T16:00:00 |
View Details | M412217 | Instrumentation (Skid 4-6) | Not Started | Yes | 0,0 | 2015-07-14T08:00:00 | 2015-08-29T16:00:00 |
View Details | M412218 | Painting (Skid 4-6) | Not Started | Yes | 0,0 | 2015-08-30T08:00:00 | 2015-09-05T16:00:00 |
View Details | M412219 | Pre-commissioning (Skid 4-6) | Not Started | Yes | 0,0 | 2015-09-06T08:00:00 | 2015-10-03T16:00:00 |
View Details | M412224 | Equipment Installation (Skid 7-9) | Not Started | Yes | 0,0 | 2015-08-04T08:00:00 | 2015-09-24T16:00:00 |
View Details | M412226 | Electrical (Skid 7-9) | Not Started | Yes | 0,0 | 2015-08-11T08:00:00 | 2015-09-26T16:00:00 |
View Details | M412227 | Instrumentation (Skid 7-9) | Not Started | Yes | 0,0 | 2015-08-11T08:00:00 | 2015-09-26T16:00:00 |
View Details | M412228 | Painting (Skid 7-9) | Not Started | Yes | 0,0 | 2015-09-27T08:00:00 | 2015-10-03T16:00:00 |
View Details | M412229 | Pre-commissioning (Skid 7-9) | Not Started | Yes | 0,0 | 2015-10-04T08:00:00 | 2015-10-31T16:00:00 |
View Details | M412213 | Mechanical Completion - System 110 (Skid 1-3) | Not Started | No | 0,0 | 2015-08-20T16:00:00 | 2015-08-20T16:00:00 |
View Details | M412220 | Mechanical Completion - System 110 (Skid 4-6) | Not Started | No | 0,0 | 2015-08-29T16:00:00 | 2015-08-29T16:00:00 |
View Details | M412230 | Mechanical Completion - System 110 (Skid 7-9) | Not Started | Yes | 0,0 | 2015-09-26T16:00:00 | 2015-09-26T16:00:00 |
View Details | M412209 | Hydrotest | Not Started | Yes | 0,0 | 2015-08-15T08:00:00 | 2015-08-20T16:00:00 |
View Details | M4132508 | Mechanical Completion - System 560 | Not Started | Yes | 0,0 | 2015-04-18T16:00:00 | 2015-04-18T16:00:00 |
View Details | M4132503 | Mechanical / Equipment - Open Drains System | Not Started | Yes | 0,0 | 2015-01-11T08:00:00 | 2015-04-11T16:00:00 |
View Details | M4132504 | Electrical - Open Drains System | Not Started | Yes | 0,0 | 2015-02-25T08:00:00 | 2015-04-18T16:00:00 |
View Details | M4132505 | Instrumentation & Telecomm - Open Drains System | Not Started | Yes | 0,0 | 2015-02-25T08:00:00 | 2015-04-18T16:00:00 |
View Details | M4132506 | Paiting & Insulation - Open Drains System | Not Started | No | 0,0 | 2015-04-19T08:00:00 | 2015-05-02T16:00:00 |
View Details | M4132507 | Pre-commissioning - Open Drains System | Not Started | No | 0,0 | 2015-04-19T08:00:00 | 2015-05-16T16:00:00 |
View Details | M4132502 | Piping - Open Drains System | Not Started | No | 0,0 | 2015-01-03T08:00:00 | 2015-04-02T16:00:00 |
View Details | M4132509 | Hydrotest | Not Started | Yes | 0,0 | 2015-04-12T08:00:00 | 2015-04-18T16:00:00 |
View Details | M4132500 | Prefabrication (60%) | Not Started | No | 0,0 | 2014-11-03T08:00:00 | 2015-01-01T16:00:00 |
View Details | M4132501 | Prefabrication (100%) | Not Started | No | 0,0 | 2014-12-25T08:00:00 | 2015-02-22T16:00:00 |
View Details | M4131108 | Mechanical Completion - System 270 | Not Started | Yes | 0,0 | 2015-09-20T16:00:00 | 2015-09-20T16:00:00 |
View Details | M4131106 | Paiting & Insulation - Gas Export and Metering System | Not Started | No | 0,0 | 2015-09-21T08:00:00 | 2015-10-11T16:00:00 |
View Details | M4131107 | Pre-commissioning - Gas Export and Metering System | Not Started | Yes | 0,0 | 2015-09-21T08:00:00 | 2015-10-18T16:00:00 |
View Details | M4131109 | Hydrotest | Not Started | Yes | 0,0 | 2015-09-15T08:00:00 | 2015-09-20T16:00:00 |
View Details | M4131104 | Electrical - Gas Export and Metering System | Not Started | Yes | 0,0 | 2015-08-10T08:00:00 | 2015-09-20T16:00:00 |
View Details | M4131105 | Instrumentation & Telecomm - Gas Export and Metering System | Not Started | Yes | 0,0 | 2015-08-10T08:00:00 | 2015-09-20T16:00:00 |
View Details | M4131103 | Mechanical / Equipment - Gas Export and Metering System | Not Started | Yes | 0,0 | 2015-06-16T08:00:00 | 2015-09-14T16:00:00 |
View Details | M4132208 | Mechanical Completion - System 480 | Not Started | Yes | 0,0 | 2015-09-13T16:00:00 | 2015-09-13T16:00:00 |
View Details | M4132206 | Paiting & Insulation - Utility Miscellaneous System | Not Started | No | 0,0 | 2015-09-14T08:00:00 | 2015-09-27T16:00:00 |
View Details | M4132207 | Pre-commissioning - Utility Miscellaneous System | Not Started | No | 0,0 | 2015-09-14T08:00:00 | 2015-09-20T16:00:00 |
View Details | M4132202 | Piping - Utility Miscellaneous System | Not Started | No | 0,0 | 2015-04-01T08:00:00 | 2015-06-30T16:00:00 |
View Details | M4132209 | Hydrotest | Not Started | Yes | 0,0 | 2015-09-08T08:00:00 | 2015-09-13T16:00:00 |
View Details | M4132201 | Prefabrication | Not Started | Yes | 0,0 | 2015-01-31T08:00:00 | 2015-03-31T16:00:00 |
View Details | M4132203 | Mechanical / Equipment - Utility Miscellaneous System | Not Started | Yes | 0,0 | 2015-06-30T08:00:00 | 2015-09-07T16:00:00 |
View Details | M4132205 | Instrumentation & Telecom - Utility Miscellaneous System | Not Started | Yes | 0,0 | 2015-08-15T08:00:00 | 2015-09-13T16:00:00 |
View Details | M4132204 | Electrical - Utility Miscellaneous System | Not Started | Yes | 0,0 | 2015-08-15T08:00:00 | 2015-09-13T16:00:00 |
View Details | M4132008 | Mechanical Completion - System 460 | Not Started | Yes | 0,0 | 2015-09-13T16:00:00 | 2015-09-13T16:00:00 |
View Details | M4132007 | Pre-commissioning - Methanol Injection System | Not Started | No | 0,0 | 2015-09-14T08:00:00 | 2015-10-04T16:00:00 |
View Details | M4132002 | Piping - Methanol Injection System | Not Started | No | 0,0 | 2015-02-16T08:00:00 | 2015-05-10T16:00:00 |
View Details | M4132009 | Hydrotest | Not Started | Yes | 0,0 | 2015-09-08T08:00:00 | 2015-09-13T16:00:00 |
View Details | M4132001 | Prefabrication | Not Started | Yes | 0,0 | 2014-12-18T08:00:00 | 2015-02-15T16:00:00 |
View Details | M4132005 | Instrumentation & Telecomm - Methanol Injection System | Not Started | No | 0,0 | 2015-07-25T08:00:00 | 2015-09-07T16:00:00 |
View Details | M4132006 | Paiting & Insulation - Methanol Injection System | Not Started | No | 0,0 | 2015-09-14T08:00:00 | 2015-10-11T16:00:00 |
View Details | M4132004 | Electrical - Methanol Injection System | Not Started | Yes | 0,0 | 2015-07-25T08:00:00 | 2015-09-07T16:00:00 |
View Details | M4132003 | Mechanical / Equipment - Methanol Injection System | Not Started | Yes | 0,0 | 2015-06-09T08:00:00 | 2015-09-07T16:00:00 |
View Details | M4133108 | Mechanical Completion - System 710 | Not Started | Yes | 0,0 | 2015-06-17T16:00:00 | 2015-06-17T16:00:00 |
View Details | M4133106 | Paiting & Insulation - Fire Water System | Not Started | No | 0,0 | 2015-06-18T08:00:00 | 2015-07-01T16:00:00 |
View Details | M4133102 | Piping - Fire Water System | Not Started | No | 0,0 | 2015-02-23T08:00:00 | 2015-05-24T16:00:00 |
View Details | M4133109 | Hydrotest | Not Started | Yes | 0,0 | 2015-06-11T08:00:00 | 2015-06-17T16:00:00 |
View Details | M4133101 | Prefabrication | Not Started | Yes | 0,0 | 2014-12-25T08:00:00 | 2015-02-22T16:00:00 |
View Details | M4133103 | Mechanical / Equipment - Fire Water System | Not Started | Yes | 0,0 | 2015-03-12T08:00:00 | 2015-06-10T16:00:00 |
View Details | M4133104 | Electrical - Fire Water System | Not Started | Yes | 0,0 | 2015-04-27T08:00:00 | 2015-06-17T16:00:00 |
View Details | M4133105 | Instrumentation & Telecomm - Fire Water System | Not Started | Yes | 0,0 | 2015-04-27T08:00:00 | 2015-06-17T16:00:00 |
View Details | M4133107 | Pre-commissioning - Fire Water System | Not Started | No | 0,0 | 2015-06-18T08:00:00 | 2015-07-15T16:00:00 |
View Details | M4132308 | Mechanical Completion - System 500 | Not Started | Yes | 0,0 | 2015-06-21T16:00:00 | 2015-06-21T16:00:00 |
View Details | M4132307 | Pre-Commissioning - Aquifer / Plant Water System | Not Started | Yes | 0,0 | 2015-06-22T08:00:00 | 2015-07-03T16:00:00 |
View Details | M4132310 | System Commissioning - Aquifer / Plant Water System | Not Started | No | 0,0 | 2015-06-22T08:00:00 | 2015-07-29T12:00:00 |
View Details | M4132304 | Electrical - Industrial Water System | Not Started | Yes | 0,0 | 2015-05-09T08:00:00 | 2015-06-21T16:00:00 |
View Details | M4132302 | Piping - Industrial Water System | Not Started | No | 0,0 | 2015-03-25T08:00:00 | 2015-06-09T16:00:00 |
View Details | M4132309 | Hydrotest | Not Started | Yes | 0,0 | 2015-06-16T08:00:00 | 2015-06-21T16:00:00 |
View Details | M4132301 | Prefabrication | Not Started | Yes | 0,0 | 2015-01-24T08:00:00 | 2015-03-24T16:00:00 |
View Details | M4132303 | Mechanical / Equipment - Industrial Water System | Not Started | Yes | 0,0 | 2015-03-31T08:00:00 | 2015-06-15T16:00:00 |
View Details | M4132305 | Instrumentation & Telecom - Industrial Water System | Not Started | Yes | 0,0 | 2015-05-09T08:00:00 | 2015-06-21T16:00:00 |
View Details | M4132306 | Paiting & Insulation - Industrial Water System | Not Started | No | 0,0 | 2015-06-22T08:00:00 | 2015-07-05T16:00:00 |
View Details | M413808 | Mechanical Completion - System 240 | Not Started | Yes | 0,0 | 2015-08-02T16:00:00 | 2015-08-02T16:00:00 |
View Details | M413802 | Piping - Gas Treatment System | Not Started | No | 0,0 | 2015-01-26T08:00:00 | 2015-04-26T16:00:00 |
View Details | M413809 | Hydrotest | Not Started | Yes | 0,0 | 2015-07-28T08:00:00 | 2015-08-02T16:00:00 |
View Details | M413800 | Prefabrication (80%) | Not Started | Yes | 0,0 | 2014-11-27T08:00:00 | 2015-01-25T16:00:00 |
View Details | M413801 | Prefabrication (100%) | Not Started | No | 0,0 | 2014-12-25T08:00:00 | 2015-02-22T16:00:00 |
View Details | M413803 | Mechanical / Equipment - Gas Treatment System | Not Started | Yes | 0,0 | 2015-04-28T08:00:00 | 2015-07-27T16:00:00 |
View Details | M413804 | Electrical - Gas Treatment System | Not Started | Yes | 0,0 | 2015-06-15T08:00:00 | 2015-08-02T16:00:00 |
View Details | M413806 | Paiting & Insulation - Gas Treatment System | Not Started | No | 0,0 | 2015-08-03T08:00:00 | 2015-08-30T16:00:00 |
View Details | M413805 | Instrumentation & Telecomm - Gas Treatment System | Not Started | Yes | 0,0 | 2015-06-15T08:00:00 | 2015-08-02T16:00:00 |
View Details | M413807 | Pre-commissioning - Gas Treatment System | Not Started | No | 0,0 | 2015-08-03T08:00:00 | 2015-09-13T16:00:00 |
View Details | M4131908 | Mechanical Completion - System 450 | Not Started | Yes | 0,0 | 2015-09-01T16:00:00 | 2015-09-01T16:00:00 |
View Details | M4131902 | Piping - Fuel Gas Supply System | Not Started | No | 0,0 | 2015-03-18T08:00:00 | 2015-06-09T16:00:00 |
View Details | M4131909 | Hydrotest | Not Started | Yes | 0,0 | 2015-08-27T08:00:00 | 2015-09-01T16:00:00 |
View Details | M4131901 | Prefabrication | Not Started | Yes | 0,0 | 2015-01-17T08:00:00 | 2015-03-17T16:00:00 |
View Details | M4131904 | Electrical - Fuel Gas Supply System | Not Started | Yes | 0,0 | 2015-07-16T08:00:00 | 2015-08-26T16:00:00 |
View Details | M4131905 | Instrumentation & Telecomm - Fuel Gas Supply System | Not Started | No | 0,0 | 2015-07-16T08:00:00 | 2015-08-26T16:00:00 |
View Details | M4131906 | Paiting & Insulation - Fuel Gas Supply System | Not Started | No | 0,0 | 2015-09-02T08:00:00 | 2015-09-15T16:00:00 |
View Details | M4131907 | Pre-Commissioning - Fuel Gas Supply System | Not Started | No | 0,0 | 2015-09-02T08:00:00 | 2015-09-29T16:00:00 |
View Details | M4131903 | Mechanical / Equipment - Fuel Gas Supply System | Not Started | Yes | 0,0 | 2015-07-16T08:00:00 | 2015-08-26T16:00:00 |
View Details | M413908 | Mechanical Completion - System 250A | Not Started | Yes | 0,0 | 2015-09-22T16:00:00 | 2015-09-22T16:00:00 |
View Details | M413902 | Piping - Gas Conditioning (Dehydration) System | Not Started | No | 0,0 | 2015-05-14T08:00:00 | 2015-08-12T16:00:00 |
View Details | M413909 | Hydrotest | Not Started | Yes | 0,0 | 2015-09-16T08:00:00 | 2015-09-22T16:00:00 |
View Details | M413901 | Prefabrication | Not Started | Yes | 0,0 | 2015-03-15T08:00:00 | 2015-05-13T16:00:00 |
View Details | M413907 | Pre-commissioning - Gas Conditioning (Dehydration) System | Not Started | Yes | 0,0 | 2015-09-23T08:00:00 | 2015-11-03T16:00:00 |
View Details | M413903 | Mechanical / Equipment - Gas Conditioning (Dehydration) System | Not Started | Yes | 0,0 | 2015-07-22T08:00:00 | 2015-09-15T16:00:00 |
View Details | M413904 | Electrical - Gas Conditioning (Dehydration) System | Not Started | Yes | 0,0 | 2015-08-11T08:00:00 | 2015-09-22T16:00:00 |
View Details | M413905 | Instrumentation & Telecomm - Gas Conditioning (Dehydration) System | Not Started | Yes | 0,0 | 2015-08-11T08:00:00 | 2015-09-22T16:00:00 |
View Details | M413906 | Paiting & Insulation - Gas Conditioning (Dehydration) System | Not Started | No | 0,0 | 2015-09-23T08:00:00 | 2015-10-20T16:00:00 |
View Details | M4131008 | Mechanical Completion - System 250B | Not Started | Yes | 0,0 | 2015-09-22T16:00:00 | 2015-09-22T16:00:00 |
View Details | M4131002 | Piping - Gas Conditioning (Dew Pointing) System | Not Started | No | 0,0 | 2015-05-14T08:00:00 | 2015-08-12T16:00:00 |
View Details | M4131009 | Hydrotest | Not Started | Yes | 0,0 | 2015-09-16T08:00:00 | 2015-09-22T16:00:00 |
View Details | M4131001 | Prefabrication | Not Started | Yes | 0,0 | 2015-03-15T08:00:00 | 2015-05-13T16:00:00 |
View Details | M4131004 | Electrical - Gas Conditioning (Dew Pointing) System | Not Started | Yes | 0,0 | 2015-08-11T08:00:00 | 2015-09-22T16:00:00 |
View Details | M4131005 | Instrumentation & Telecomm - Gas Conditioning (Dew Pointing) System | Not Started | Yes | 0,0 | 2015-08-11T08:00:00 | 2015-09-22T16:00:00 |
View Details | M4131006 | Paiting & Insulation - Gas Conditioning (Dew Pointing) System | Not Started | No | 0,0 | 2015-09-23T08:00:00 | 2015-10-20T16:00:00 |
View Details | M4131007 | Pre-commissioning - Gas Conditioning (Dew Pointing) System | Not Started | No | 0,0 | 2015-09-23T08:00:00 | 2015-11-03T16:00:00 |
View Details | M4131003 | Mechanical / Equipment - Gas Conditioning (Dew Pointing) System | Not Started | Yes | 0,0 | 2015-07-22T08:00:00 | 2015-09-15T16:00:00 |
View Details | M4133208 | Mechanical Completion - System 800 | Not Started | Yes | 0,0 | 2015-12-06T16:00:00 | 2015-12-06T16:00:00 |
View Details | M4133202 | Piping - Gas Turbine System | Not Started | No | 0,0 | 2015-02-23T08:00:00 | 2015-05-11T16:00:00 |
View Details | M4133209 | Hydrotest | Not Started | Yes | 0,0 | 2015-11-30T08:00:00 | 2015-12-06T16:00:00 |
View Details | M4133201 | Prefabrication | Not Started | Yes | 0,0 | 2014-12-25T08:00:00 | 2015-02-22T16:00:00 |
View Details | M4133206 | Paiting & Insulation - Gas Turbine System | Not Started | No | 0,0 | 2015-12-07T08:00:00 | 2015-12-20T16:00:00 |
View Details | M4133207 | Pre-commissioning - Gas Turbine System | Not Started | Yes | 0,0 | 2015-12-07T08:00:00 | 2016-01-03T16:00:00 |
View Details | M4133203 | Mechanical / Equipment - Gas Turbine System | Not Started | Yes | 0,0 | 2015-09-19T08:00:00 | 2015-11-29T16:00:00 |
View Details | M4133204 | Electrical - Gas Turbine System | Not Started | Yes | 0,0 | 2015-10-28T08:00:00 | 2015-12-06T16:00:00 |
View Details | M4133205 | Instrumentation & Telecomm - Gas Turbine System | Not Started | Yes | 0,0 | 2015-10-28T08:00:00 | 2015-12-06T16:00:00 |
View Details | M4131208 | Mechanical Completion - System 280 | Not Started | Yes | 0,0 | 2015-09-21T16:00:00 | 2015-09-21T16:00:00 |
View Details | M4131202 | Piping - Gas Sweetening (Amine) System | Not Started | No | 0,0 | 2015-01-03T08:00:00 | 2015-04-23T16:00:00 |
View Details | M4131209 | Hydrotest | Not Started | Yes | 0,0 | 2015-09-15T08:00:00 | 2015-09-21T16:00:00 |
View Details | M4131201 | Prefabrication | Not Started | No | 0,0 | 2014-11-03T08:00:00 | 2015-01-01T16:00:00 |
View Details | M4131204 | Electrical - Gas Sweetening (Amine) System | Not Started | Yes | 0,0 | 2015-07-07T08:00:00 | 2015-09-21T16:00:00 |
View Details | M4131205 | Instrumentation & Telecomm - Gas Sweetening (Amine) System | Not Started | Yes | 0,0 | 2015-07-07T08:00:00 | 2015-09-21T16:00:00 |
View Details | M4131206 | Paiting & Insulation - Gas Sweetening (Amine) System | Not Started | No | 0,0 | 2015-09-22T08:00:00 | 2015-12-14T16:00:00 |
View Details | M4131207 | Pre-commissioning - Gas Sweetening (Amine) System | Not Started | Yes | 0,0 | 2015-09-22T08:00:00 | 2015-11-02T16:00:00 |
View Details | M4131203 | Mechanical / Equipment - Gas Sweetening (Amine) System | Not Started | Yes | 0,0 | 2015-06-16T08:00:00 | 2015-09-14T16:00:00 |
View Details | M4132708 | Mechanical Completion - System 620 | Not Started | Yes | 0,0 | 2015-04-18T16:00:00 | 2015-04-18T16:00:00 |
View Details | M4132704 | Electrical - Diesel Oil System | Not Started | Yes | 0,0 | 2015-02-25T08:00:00 | 2015-04-18T16:00:00 |
View Details | M4132705 | Instrumentation & Telecomm - Diesel Oil System | Not Started | Yes | 0,0 | 2015-02-25T08:00:00 | 2015-04-18T16:00:00 |
View Details | M4132707 | Pre-commissioning - Diesel Oil System | Not Started | No | 0,0 | 2015-04-19T08:00:00 | 2015-05-16T16:00:00 |
View Details | M4132706 | Paiting & Insulation - Diesel Oil System | Not Started | No | 0,0 | 2015-04-19T08:00:00 | 2015-05-02T16:00:00 |
View Details | M4132702 | Piping - Diesel Oil System | Not Started | No | 0,0 | 2015-01-03T08:00:00 | 2015-04-02T16:00:00 |
View Details | M4132709 | Hydrotest | Not Started | Yes | 0,0 | 2015-04-12T08:00:00 | 2015-04-18T16:00:00 |
View Details | M4132700 | Prefabrication (60%) | Not Started | No | 0,0 | 2014-11-03T08:00:00 | 2015-01-01T16:00:00 |
View Details | M4132701 | Prefabrication (100%) | Not Started | No | 0,0 | 2014-12-25T08:00:00 | 2015-02-22T16:00:00 |
View Details | M4132703 | Mechanical / Equipment - Diesel Oil System | Not Started | Yes | 0,0 | 2015-01-11T08:00:00 | 2015-04-11T16:00:00 |
View Details | M4131508 | Mechanical Completion - System 410 | Not Started | Yes | 0,0 | 2015-07-26T16:00:00 | 2015-07-26T16:00:00 |
View Details | M4131502 | Piping - Heating Medium System | Not Started | No | 0,0 | 2015-04-08T08:00:00 | 2015-07-07T16:00:00 |
View Details | M4131509 | Hydrotest | Not Started | Yes | 0,0 | 2015-07-21T08:00:00 | 2015-07-26T16:00:00 |
View Details | M4131501 | Prefabrication | Not Started | Yes | 0,0 | 2015-02-07T08:00:00 | 2015-04-07T16:00:00 |
View Details | M4131504 | Electrical - Heating Medium System | Not Started | Yes | 0,0 | 2015-06-16T08:00:00 | 2015-07-26T16:00:00 |
View Details | M4131505 | Instrumentation & Telecomm - Heating Medium System | Not Started | Yes | 0,0 | 2015-06-16T08:00:00 | 2015-07-26T16:00:00 |
View Details | M4131506 | Paiting & Insulation - Heating Medium System | Not Started | No | 0,0 | 2015-07-27T08:00:00 | 2015-08-09T16:00:00 |
View Details | M4131507 | Pre-commissioning - Heating Medium System | Not Started | No | 0,0 | 2015-07-27T08:00:00 | 2015-08-16T16:00:00 |
View Details | M4131503 | Mechanical / Equipment - Heating Medium System | Not Started | Yes | 0,0 | 2015-05-12T08:00:00 | 2015-07-20T16:00:00 |
View Details | M413207 | Mechanical Completion - System 200B | Not Started | Yes | 0,0 | 2015-07-20T16:00:00 | 2015-07-20T16:00:00 |
View Details | M413202 | Piping - Condensate Stabilisation System | Not Started | Yes | 0,0 | 2014-11-20T08:00:00 | 2015-02-04T16:00:00 |
View Details | M413209 | Hydrotest | Not Started | No | 0,0 | 2015-02-05T08:00:00 | 2015-02-11T16:00:00 |
View Details | M413203 | Mechanical / Equipment - Condensate Stabilisation System | Not Started | Yes | 0,0 | 2015-04-28T08:00:00 | 2015-07-20T16:00:00 |
View Details | M413204 | Electrical & Instrumentation & Telecomm - Condensate Stabilisation System | Not Started | Yes | 0,0 | 2015-04-28T08:00:00 | 2015-07-20T16:00:00 |
View Details | M413206 | Pre-commissioning - Condensate Stabilisation System | Not Started | No | 0,0 | 2015-07-21T08:00:00 | 2015-08-17T16:00:00 |
View Details | M413205 | Paiting & Insulation - Condensate Stabilisation System | Not Started | No | 0,0 | 2015-07-21T08:00:00 | 2015-08-03T16:00:00 |
View Details | M413307 | Mechanical Completion - System 200A | Not Started | Yes | 0,0 | 2015-07-20T16:00:00 | 2015-07-20T16:00:00 |
View Details | M413303 | Mechanical / Equipment - Water / Condensate Separator System | Not Started | Yes | 0,0 | 2015-04-28T08:00:00 | 2015-07-20T16:00:00 |
View Details | M413302 | Piping - Water / Condensate Separator System | Not Started | Yes | 0,0 | 2015-03-05T08:00:00 | 2015-05-20T16:00:00 |
View Details | M413312 | Hydrotest | Not Started | No | 0,0 | 2015-05-21T08:00:00 | 2015-05-27T16:00:00 |
View Details | M413301 | Pre-Fabrication 100% in MIG Workshop System 200 | Not Started | Yes | 0,0 | 2014-12-25T08:00:00 | 2015-03-04T16:00:00 |
View Details | M413304 | Electrical & Instrumentation & Telecomm - Water / Condensate Separator System | Not Started | Yes | 0,0 | 2015-04-28T08:00:00 | 2015-07-20T16:00:00 |
View Details | M413306 | Pre-commissioning - Water / Condensate Separator System | Not Started | No | 0,0 | 2015-07-21T08:00:00 | 2015-08-17T16:00:00 |
View Details | M413305 | Paiting & Insulation - Water / Condensate Separator System | Not Started | No | 0,0 | 2015-07-21T08:00:00 | 2015-08-03T16:00:00 |
View Details | M413101 | General Levelling | Not Started | Yes | 0,0 | 2014-06-01T08:00:00 | 2014-07-05T16:00:00 |
View Details | M413102 | Fencing & Roads | Not Started | No | 0,0 | 2014-07-06T08:00:00 | 2015-03-18T16:00:00 |
View Details | M413100 | Fundaments of all CPF system | Not Started | Yes | 0,0 | 2014-07-06T08:00:00 | 2015-01-10T16:00:00 |
View Details | M413103 | Concrete Basement (410, 480, 570) | Not Started | No | 0,0 | 2014-07-06T08:00:00 | 2015-05-30T16:00:00 |
View Details | M413104 | Civil works for Pipe Rack and Pipe rack | Not Started | No | 0,0 | 2014-07-06T08:00:00 | 2015-01-01T16:00:00 |
View Details | F5600 | Purchasing - Flare System | Not Started | Yes | 0,0 | 2014-05-24T08:00:00 | 2014-07-04T16:00:00 |
View Details | F5610 | PO placed - Flare System | Not Started | Yes | 0,0 | 2014-07-04T16:00:00 | 2014-07-04T16:00:00 |
View Details | F5630 | Ready for Shipment - Flare System | Not Started | Yes | 0,0 | 2015-04-10T16:00:00 | 2015-04-10T16:00:00 |
View Details | F5620 | Delievery Time - Flare System | Not Started | Yes | 0,0 | 2014-07-05T08:00:00 | 2015-04-10T16:00:00 |
View Details | M6160 | Shipment - Flare System | Not Started | Yes | 0,0 | 2015-04-18T08:00:00 | 2015-06-01T16:00:00 |
View Details | M6170 | At site - Flare System | Not Started | Yes | 0,0 | 2015-06-01T16:00:00 | 2015-06-01T16:00:00 |
View Details | F5635 | Transport to Port of Export - Flare System | Not Started | Yes | 0,0 | 2015-04-11T08:00:00 | 2015-04-17T16:00:00 |
View Details | J2925 | Engineering - Flare interconnecting piping | Not Started | Yes | 0,0 | 2014-04-14T08:00:00 | 2014-08-06T16:00:00 |
View Details | J2930 | Purchasing - Flare interconnecting piping | Not Started | Yes | 0,0 | 2014-05-29T08:00:00 | 2014-08-06T16:00:00 |
View Details | J2940 | First PO placed - Flare interconnecting piping | Not Started | Yes | 0,0 | 2014-06-13T08:00:00 | 2014-06-13T08:00:00 |
View Details | J2950 | Delivery Time - Flare interconnecting piping | Not Started | Yes | 0,0 | 2014-06-13T08:00:00 | 2014-11-09T16:00:00 |
View Details | J2970 | Ready for Shipment - Flare interconnecting piping | Not Started | Yes | 0,0 | 2014-11-10T08:00:00 | 2014-11-10T08:00:00 |
View Details | M6040 | Shipment - Flare interconnecting piping | Not Started | Yes | 0,0 | 2014-11-17T08:00:00 | 2014-12-31T16:00:00 |
View Details | M6050 | At site - Flare interconnecting piping | Not Started | Yes | 0,0 | 2014-12-31T16:00:00 | 2014-12-31T16:00:00 |
View Details | J2975 | Transport to Port of Export - Flare interconnecting piping | Not Started | Yes | 0,0 | 2014-11-10T08:00:00 | 2014-11-16T16:00:00 |
View Details | F4950 | Purchasing - Produced Water Treatment System | Not Started | Yes | 0,0 | 2014-05-03T08:00:00 | 2014-06-13T16:00:00 |
View Details | F4960 | PO placed - Produced Water Treatment System | Not Started | Yes | 0,0 | 2014-06-13T16:00:00 | 2014-06-13T16:00:00 |
View Details | F4980 | Ready for Shipment - Produced Water Treatment System | Not Started | Yes | 0,0 | 2015-06-13T16:00:00 | 2015-06-13T16:00:00 |
View Details | F4970 | Delievery Time - Produced Water Treatment System | Not Started | Yes | 0,0 | 2014-06-14T08:00:00 | 2015-06-13T16:00:00 |
View Details | M4990 | Shipment - Produced Water Treatment System | Not Started | Yes | 0,0 | 2015-06-21T08:00:00 | 2015-08-04T16:00:00 |
View Details | M5000 | At site - Produced Water Treatment System | Not Started | Yes | 0,0 | 2015-08-04T16:00:00 | 2015-08-04T16:00:00 |
View Details | F4985 | Transport to Port of Export - Produced Water Treatment System | Not Started | Yes | 0,0 | 2015-06-14T08:00:00 | 2015-06-20T16:00:00 |
View Details | J5170 | Purchasing - Produced water treatment system piping | Not Started | Yes | 0,0 | 2014-05-22T08:00:00 | 2014-07-30T16:00:00 |
View Details | J5180 | First PO placed - Produced water treatment system piping | Not Started | Yes | 0,0 | 2014-06-06T08:00:00 | 2014-06-06T08:00:00 |
View Details | J5190 | Delivery Time - Produced water treatment system piping | Not Started | Yes | 0,0 | 2014-06-06T08:00:00 | 2015-01-01T16:00:00 |
View Details | J5210 | Ready for Shipment - Produced water treatment system piping | Not Started | Yes | 0,0 | 2015-01-02T08:00:00 | 2015-01-02T08:00:00 |
View Details | M5225 | Shipment - Produced water piping | Not Started | Yes | 0,0 | 2015-01-09T08:00:00 | 2015-02-22T16:00:00 |
View Details | M5235 | At site - Produced water piping | Not Started | No | 0,0 | 2015-02-22T16:00:00 | 2015-02-22T16:00:00 |
View Details | J5215 | Transport to Port of Export - Produced water treatment system piping | Not Started | Yes | 0,0 | 2015-01-02T08:00:00 | 2015-01-08T16:00:00 |
View Details | M3401 | Purchasing - Evaporation Pond | Not Started | Yes | 0,0 | 2014-05-17T08:00:00 | 2014-06-15T16:00:00 |
View Details | M3402 | PO placed - Evaporation Pond | Not Started | Yes | 0,0 | 2014-06-15T16:00:00 | 2014-06-15T16:00:00 |
View Details | M3404 | Ready for Shipment - Evaporation Pond | Not Started | Yes | 0,0 | 2014-10-16T16:00:00 | 2014-10-16T16:00:00 |
View Details | M3403 | Delievery Time - Evaporation Pond | Not Started | Yes | 0,0 | 2014-06-16T08:00:00 | 2014-10-16T16:00:00 |
View Details | M3405 | Shipment - Evaporation Pond | Not Started | Yes | 0,0 | 2014-10-18T08:00:00 | 2014-11-13T16:00:00 |
View Details | M3406 | At site - Evaporation Pond | Not Started | No | 0,0 | 2014-11-13T16:00:00 | 2014-11-13T16:00:00 |
View Details | J3030 | Purchasing - Produced water interconnecting piping | Not Started | Yes | 0,0 | 2014-06-21T08:00:00 | 2014-08-29T16:00:00 |
View Details | J3040 | First PO placed - Produced water interconnecting piping | Not Started | Yes | 0,0 | 2014-07-06T08:00:00 | 2014-07-06T08:00:00 |
View Details | J3050 | Delivery Time - Produced water interconnecting piping | Not Started | Yes | 0,0 | 2014-07-06T08:00:00 | 2014-12-02T16:00:00 |
View Details | J3070 | Ready for Shipment - Produced water interconnecting piping | Not Started | Yes | 0,0 | 2014-12-03T08:00:00 | 2014-12-03T08:00:00 |
View Details | M6060 | Shipment - Produced water interconnecting piping | Not Started | Yes | 0,0 | 2014-12-10T08:00:00 | 2015-01-23T16:00:00 |
View Details | M6070 | At site - Produced water interconnecting piping | Not Started | Yes | 0,0 | 2015-01-23T16:00:00 | 2015-01-23T16:00:00 |
View Details | J3075 | Transport to Port of Export - Produced water interconnecting piping | Not Started | Yes | 0,0 | 2014-12-03T08:00:00 | 2014-12-09T16:00:00 |
View Details | J2830 | Purchasing - Chemical injection interconnecting piping | Not Started | Yes | 0,0 | 2014-07-19T08:00:00 | 2014-09-26T16:00:00 |
View Details | J2840 | First PO placed - Chemical injection interconnecting piping | Not Started | Yes | 0,0 | 2014-08-03T08:00:00 | 2014-08-03T08:00:00 |
View Details | J2850 | Delivery Time - Chemical injection interconnecting piping | Not Started | Yes | 0,0 | 2014-08-03T08:00:00 | 2014-12-30T16:00:00 |
View Details | J2870 | Ready for Shipment - Chemical injection interconnecting piping | Not Started | Yes | 0,0 | 2014-12-31T08:00:00 | 2014-12-31T08:00:00 |
View Details | M6020 | Shipment - Chemical injection interconnecting piping | Not Started | Yes | 0,0 | 2015-01-07T08:00:00 | 2015-02-28T16:00:00 |
View Details | M6030 | At site - Chemical injection interconnecting piping | Not Started | Yes | 0,0 | 2015-02-28T16:00:00 | 2015-02-28T16:00:00 |
View Details | J2875 | Transport to Port of Export - Chemical injection interconnecting piping | Not Started | Yes | 0,0 | 2014-12-31T08:00:00 | 2015-01-06T16:00:00 |
View Details | F2800 | Purchasing - Chemical Injection System | Not Started | Yes | 0,0 | 2014-05-17T08:00:00 | 2014-06-27T16:00:00 |
View Details | F2810 | PO placed - Chemical Injection System | Not Started | Yes | 0,0 | 2014-06-27T16:00:00 | 2014-06-27T16:00:00 |
View Details | F2830 | Ready for Shipment - Chemical Injection System | Not Started | Yes | 0,0 | 2015-03-20T16:00:00 | 2015-03-20T16:00:00 |
View Details | F2820 | Delievery Time - Chemical Injection System | Not Started | Yes | 0,0 | 2014-06-28T08:00:00 | 2015-03-20T16:00:00 |
View Details | M2840 | Shipment - Chemical Injection System | Not Started | Yes | 0,0 | 2015-03-28T08:00:00 | 2015-05-11T16:00:00 |
View Details | M2850 | At site - Chemical Injection System | Not Started | Yes | 0,0 | 2015-05-11T16:00:00 | 2015-05-11T16:00:00 |
View Details | F2835 | Transport to Port of Export - Chemical Injection System | Not Started | Yes | 0,0 | 2015-03-21T08:00:00 | 2015-03-27T16:00:00 |
View Details | F1240 | Purchasing - Condensate Stabilisation System | Not Started | Yes | 0,0 | 2014-04-12T08:00:00 | 2014-05-23T16:00:00 |
View Details | F1250 | PO placed - Condensate Stabilisation System | Not Started | Yes | 0,0 | 2014-05-23T16:00:00 | 2014-05-23T16:00:00 |
View Details | F1270 | Ready for Shipment - Condensate Stabilisation System | Not Started | Yes | 0,0 | 2015-03-06T16:00:00 | 2015-03-06T16:00:00 |
View Details | F1260 | Delievery Time - Condensate Stabilisation System | Not Started | Yes | 0,0 | 2014-05-24T08:00:00 | 2015-03-06T16:00:00 |
View Details | M1280 | Shipment - Condensate Stabilisation System | Not Started | Yes | 0,0 | 2015-03-14T08:00:00 | 2015-04-27T16:00:00 |
View Details | M1290 | At site - Condensate Stabilisation System | Not Started | Yes | 0,0 | 2015-04-27T16:00:00 | 2015-04-27T16:00:00 |
View Details | F1275 | Transport to Port of Export - Condensate Stabilisation System | Not Started | Yes | 0,0 | 2015-03-07T08:00:00 | 2015-03-13T16:00:00 |
View Details | J3840 | Purchasing - Condensate Piping | Not Started | Yes | 0,0 | 2014-05-22T08:00:00 | 2014-07-30T16:00:00 |
View Details | J3850 | First PO placed - Condensate Piping | Not Started | Yes | 0,0 | 2014-06-06T08:00:00 | 2014-06-06T08:00:00 |
View Details | J3860 | Delivery Time - Condensate Piping | Not Started | Yes | 0,0 | 2014-06-06T08:00:00 | 2014-11-02T16:00:00 |
View Details | J3880 | Ready for Shipment (Ex Works) - Condensate Piping | Not Started | Yes | 0,0 | 2014-11-03T08:00:00 | 2014-11-03T08:00:00 |
View Details | M5580 | Shipment - Condensate Piping | Not Started | Yes | 0,0 | 2014-11-10T08:00:00 | 2014-12-24T16:00:00 |
View Details | M5590 | At workshop - Condensate Piping | Not Started | Yes | 0,0 | 2014-12-24T16:00:00 | 2014-12-24T16:00:00 |
View Details | J3885 | Transport to Port of Export - Condensate Piping | Not Started | Yes | 0,0 | 2014-11-03T08:00:00 | 2014-11-09T16:00:00 |
View Details | F1360 | Purchasing - Test Separation and Metering System | Not Started | Yes | 0,0 | 2014-05-03T08:00:00 | 2014-06-13T16:00:00 |
View Details | F1370 | PO placed - Test Separation and Metering System | Not Started | Yes | 0,0 | 2014-06-13T16:00:00 | 2014-06-13T16:00:00 |
View Details | F1390 | Ready for Shipment - Test Separation and Metering System | Not Started | Yes | 0,0 | 2015-03-13T16:00:00 | 2015-03-13T16:00:00 |
View Details | F1380 | Delievery Time - Test Separation and Metering System | Not Started | Yes | 0,0 | 2014-06-14T08:00:00 | 2015-03-13T16:00:00 |
View Details | M1400 | Shipment - Test Separation and Metering System | Not Started | Yes | 0,0 | 2015-03-21T08:00:00 | 2015-05-04T16:00:00 |
View Details | M1410 | At site - Test Separation and Metering System | Not Started | Yes | 0,0 | 2015-05-04T16:00:00 | 2015-05-04T16:00:00 |
View Details | F1395 | Transport to Port of Export - Test Separation and Metering System | Not Started | Yes | 0,0 | 2015-03-14T08:00:00 | 2015-03-20T16:00:00 |
View Details | F1480 | Purchasing - Gas Reception System | Not Started | Yes | 0,0 | 2014-04-12T08:00:00 | 2014-05-23T16:00:00 |
View Details | F1490 | PO placed - Gas Reception System | Not Started | Yes | 0,0 | 2014-05-23T16:00:00 | 2014-05-23T16:00:00 |
View Details | F1510 | Ready for Shipment - Gas Reception System | Not Started | Yes | 0,0 | 2015-02-20T16:00:00 | 2015-02-20T16:00:00 |
View Details | F1500 | Delievery Time - Gas Reception System | Not Started | Yes | 0,0 | 2014-05-24T08:00:00 | 2015-02-20T16:00:00 |
View Details | M1520 | Shipment - Gas Reception System | Not Started | Yes | 0,0 | 2015-02-28T08:00:00 | 2015-04-13T16:00:00 |
View Details | M1530 | At site - Gas Reception System | Not Started | Yes | 0,0 | 2015-04-13T16:00:00 | 2015-04-13T16:00:00 |
View Details | M31201 | Inlet Manifold - HP, MP, LP (in MIG Workshop) | Not Started | No | 0,0 | 2014-09-01T08:00:00 | 2014-12-29T16:00:00 |
View Details | F1515 | Transport to Port of Export - Gas Reception System | Not Started | Yes | 0,0 | 2015-02-21T08:00:00 | 2015-02-27T16:00:00 |
View Details | F1600 | Purchasing - Gas Separation System | Not Started | Yes | 0,0 | 2014-04-12T08:00:00 | 2014-05-23T16:00:00 |
View Details | F1610 | PO placed - Gas Separation System | Not Started | Yes | 0,0 | 2014-05-23T16:00:00 | 2014-05-23T16:00:00 |
View Details | F1630 | Ready for Shipment - Gas Separation System | Not Started | Yes | 0,0 | 2015-02-20T16:00:00 | 2015-02-20T16:00:00 |
View Details | F1620 | Delievery Time - Gas Separation System | Not Started | Yes | 0,0 | 2014-05-24T08:00:00 | 2015-02-20T16:00:00 |
View Details | M1640 | Shipment - Gas Separation System | Not Started | Yes | 0,0 | 2015-02-28T08:00:00 | 2015-04-13T16:00:00 |
View Details | M1650 | At site - Gas Separation System | Not Started | Yes | 0,0 | 2015-04-13T16:00:00 | 2015-04-13T16:00:00 |
View Details | F1635 | Transport to Port of Export - Gas Separation System | Not Started | Yes | 0,0 | 2015-02-21T08:00:00 | 2015-02-27T16:00:00 |
View Details | F1840 | Purchasing - Gas Treatment System | Not Started | Yes | 0,0 | 2014-04-19T08:00:00 | 2014-05-30T16:00:00 |
View Details | F1850 | PO placed - Gas Treatment System | Not Started | Yes | 0,0 | 2014-05-30T16:00:00 | 2014-05-30T16:00:00 |
View Details | F1870 | Ready for Shipment - Gas Treatment System | Not Started | Yes | 0,0 | 2015-03-06T16:00:00 | 2015-03-06T16:00:00 |
View Details | F1860 | Delievery Time - Gas Treatment System | Not Started | Yes | 0,0 | 2014-05-31T08:00:00 | 2015-03-06T16:00:00 |
View Details | M1880 | Shipment - Gas Treatment System | Not Started | Yes | 0,0 | 2015-03-14T08:00:00 | 2015-04-27T16:00:00 |
View Details | M1890 | At site - Gas Treatment System | Not Started | Yes | 0,0 | 2015-04-27T16:00:00 | 2015-04-27T16:00:00 |
View Details | F1875 | Transport to Port of Export - Gas Treatment System | Not Started | Yes | 0,0 | 2015-03-07T08:00:00 | 2015-03-13T16:00:00 |
View Details | F2200 | Purchasing - Gas Export and Metering System | Not Started | Yes | 0,0 | 2014-04-26T08:00:00 | 2014-06-06T16:00:00 |
View Details | F2210 | PO placed - Gas Export and Metering System | Not Started | Yes | 0,0 | 2014-06-06T16:00:00 | 2014-06-06T16:00:00 |
View Details | F2230 | Ready for Shipment - Gas Export and Metering System | Not Started | Yes | 0,0 | 2015-04-24T16:00:00 | 2015-04-24T16:00:00 |
View Details | F2220 | Delievery Time - Gas Export and Metering System | Not Started | Yes | 0,0 | 2014-06-07T08:00:00 | 2015-04-24T16:00:00 |
View Details | M2240 | Shipment - Gas Export and Metering System | Not Started | Yes | 0,0 | 2015-05-02T08:00:00 | 2015-06-15T16:00:00 |
View Details | M2250 | At site - Gas Export and Metering System | Not Started | Yes | 0,0 | 2015-06-15T16:00:00 | 2015-06-15T16:00:00 |
View Details | F2235 | Transport to Port of Export - Gas Export and Metering System | Not Started | Yes | 0,0 | 2015-04-25T08:00:00 | 2015-05-01T16:00:00 |
View Details | F2440 | Purchasing - Condensate Metering System and Pumps | Not Started | Yes | 0,0 | 2014-05-24T08:00:00 | 2014-07-04T16:00:00 |
View Details | F2450 | PO placed - Condensate Metering System and Pumps | Not Started | Yes | 0,0 | 2014-07-04T16:00:00 | 2014-07-04T16:00:00 |
View Details | F2470 | Ready for Shipment - Condensate Metering System and Pumps | Not Started | Yes | 0,0 | 2015-05-22T16:00:00 | 2015-05-22T16:00:00 |
View Details | F2460 | Delievery Time - Condensate Metering System and Pumps | Not Started | Yes | 0,0 | 2014-07-05T08:00:00 | 2015-05-22T16:00:00 |
View Details | M2480 | Shipment - Condensate Metering System and Pumps | Not Started | Yes | 0,0 | 2015-05-30T08:00:00 | 2015-07-13T16:00:00 |
View Details | M2490 | At site - Condensate Metering System and Pumps | Not Started | Yes | 0,0 | 2015-07-13T16:00:00 | 2015-07-13T16:00:00 |
View Details | F2475 | Transport to Port of Export - Condensate Metering System and Pumps | Not Started | Yes | 0,0 | 2015-05-23T08:00:00 | 2015-05-29T16:00:00 |
View Details | J5345 | data sheet and techn. requirements for purchasing available | Not Started | Yes | 0,0 | 2014-05-24T08:00:00 | 2014-05-24T08:00:00 |
View Details | J2230 | Purchasing - Condensate System Piping | Not Started | Yes | 0,0 | 2014-06-08T08:00:00 | 2014-08-16T16:00:00 |
View Details | J2240 | First PO placed - Condensate System Piping | Not Started | Yes | 0,0 | 2014-06-23T08:00:00 | 2014-06-23T08:00:00 |
View Details | J2250 | Delivery Time - Condensate System Piping | Not Started | Yes | 0,0 | 2014-06-23T08:00:00 | 2014-11-19T16:00:00 |
View Details | J2270 | Ready for Shipment - Condensate System Piping | Not Started | Yes | 0,0 | 2014-11-20T08:00:00 | 2014-11-20T08:00:00 |
View Details | M5620 | Shipment - Condensate System Piping | Not Started | Yes | 0,0 | 2014-11-27T08:00:00 | 2015-01-10T16:00:00 |
View Details | M5630 | At site - Condensate System Piping | Not Started | Yes | 0,0 | 2015-01-10T16:00:00 | 2015-01-10T16:00:00 |
View Details | J2275 | Transport to Port of Export - Condensate System Piping | Not Started | Yes | 0,0 | 2014-11-20T08:00:00 | 2014-11-26T16:00:00 |
View Details | J5405 | Ready for Shipment - (70%) Condensate System Piping | Not Started | Yes | 0,0 | 2014-10-29T08:00:00 | 2014-10-29T08:00:00 |
View Details | M5415 | Shipment - (70%) Condensate System Piping | Not Started | Yes | 0,0 | 2014-11-05T08:00:00 | 2014-12-19T16:00:00 |
View Details | M5425 | At site - (70%) Condensate System Piping | Not Started | Yes | 0,0 | 2014-12-19T16:00:00 | 2014-12-19T16:00:00 |
View Details | J5415 | Transport to Port of Export - (70%) Condensate System Piping | Not Started | Yes | 0,0 | 2014-10-29T08:00:00 | 2014-11-04T16:00:00 |
View Details | M7010 | Purchasing - Condensate Storage System | Not Started | Yes | 0,0 | 2014-07-05T08:00:00 | 2014-08-29T16:00:00 |
View Details | M7020 | PO placed - Condensate Storage System | Not Started | Yes | 0,0 | 2014-08-29T16:00:00 | 2014-08-29T16:00:00 |
View Details | M7045 | Ready for Shipment - Condensate Storage System | Not Started | Yes | 0,0 | 2015-03-27T16:00:00 | 2015-03-27T16:00:00 |
View Details | M7040 | Delievery Time - Condensate Storage System | Not Started | Yes | 0,0 | 2014-08-30T08:00:00 | 2015-03-27T16:00:00 |
View Details | M7055 | Shipment - Condensate Storage System | Not Started | Yes | 0,0 | 2015-03-28T08:00:00 | 2015-04-20T16:00:00 |
View Details | M7065 | At site - Condensate Storage System | Not Started | Yes | 0,0 | 2015-04-20T16:00:00 | 2015-04-20T16:00:00 |
View Details | F2560 | Purchasing - Cooling Medium (Propane) System | Not Started | Yes | 0,0 | 2014-04-26T08:00:00 | 2014-06-06T16:00:00 |
View Details | F2570 | PO placed - Cooling Medium (Propane) System | Not Started | Yes | 0,0 | 2014-06-06T16:00:00 | 2014-06-06T16:00:00 |
View Details | F2590 | Ready for Shipment - Cooling Medium (Propane) System | Not Started | Yes | 0,0 | 2015-06-19T16:00:00 | 2015-06-19T16:00:00 |
View Details | F2580 | Delievery Time - Cooling Medium (Propane) System | Not Started | Yes | 0,0 | 2014-06-07T08:00:00 | 2015-06-19T16:00:00 |
View Details | M2600 | Shipment - Cooling Medium (Propane) System | Not Started | Yes | 0,0 | 2015-06-27T08:00:00 | 2015-08-10T16:00:00 |
View Details | M2610 | At site - Cooling Medium (Propane) System | Not Started | Yes | 0,0 | 2015-08-10T16:00:00 | 2015-08-10T16:00:00 |
View Details | F2595 | Transport to Port of Export - Cooling Medium (Propane) System | Not Started | Yes | 0,0 | 2015-06-20T08:00:00 | 2015-06-26T16:00:00 |
View Details | F2680 | Purchasing - Heating Medium System | Not Started | Yes | 0,0 | 2014-05-17T08:00:00 | 2014-06-27T16:00:00 |
View Details | F2690 | PO placed - Heating Medium System | Not Started | Yes | 0,0 | 2014-06-27T16:00:00 | 2014-06-27T16:00:00 |
View Details | F2710 | Ready for Shipment - Heating Medium System | Not Started | Yes | 0,0 | 2015-03-20T16:00:00 | 2015-03-20T16:00:00 |
View Details | F2700 | Delievery Time - Heating Medium System | Not Started | Yes | 0,0 | 2014-06-28T08:00:00 | 2015-03-20T16:00:00 |
View Details | M2720 | Shipment - Heating Medium System | Not Started | Yes | 0,0 | 2015-03-28T08:00:00 | 2015-05-11T16:00:00 |
View Details | M2730 | At site - Heating Medium System | Not Started | Yes | 0,0 | 2015-05-11T16:00:00 | 2015-05-11T16:00:00 |
View Details | F2715 | Transport to Port of Export - Heating Medium System | Not Started | Yes | 0,0 | 2015-03-21T08:00:00 | 2015-03-27T16:00:00 |
View Details | J2730 | Purchasing - Heat medium interconnecting piping | Not Started | Yes | 0,0 | 2014-07-05T08:00:00 | 2014-09-12T16:00:00 |
View Details | J2740 | First PO placed - Heat medium interconnecting piping | Not Started | Yes | 0,0 | 2014-07-20T08:00:00 | 2014-07-20T08:00:00 |
View Details | J2750 | Delivery Time - Heat medium interconnecting piping | Not Started | Yes | 0,0 | 2014-07-20T08:00:00 | 2014-12-16T16:00:00 |
View Details | J2770 | Ready for Shipment - Heat medium interconnecting piping | Not Started | Yes | 0,0 | 2014-12-17T08:00:00 | 2014-12-17T08:00:00 |
View Details | M6000 | Shipment - Heat medium interconnecting piping | Not Started | Yes | 0,0 | 2014-12-24T08:00:00 | 2015-02-06T16:00:00 |
View Details | M6010 | At site - Heat medium interconnecting piping | Not Started | Yes | 0,0 | 2015-02-06T16:00:00 | 2015-02-06T16:00:00 |
View Details | J2775 | Transport to Port of Export - Heat medium interconnecting piping | Not Started | Yes | 0,0 | 2014-12-17T08:00:00 | 2014-12-23T16:00:00 |
View Details | J3450 | Purchasing - Fuel Gas Supply System Piping | Not Started | Yes | 0,0 | 2014-06-14T08:00:00 | 2014-08-22T16:00:00 |
View Details | J3460 | First PO placed - Fuel Gas Supply System Piping | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2014-06-29T08:00:00 |
View Details | J3470 | Delivery Time - Fuel Gas Supply System Piping | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2014-11-25T16:00:00 |
View Details | J3490 | Ready for Shipment - Fuel Gas Supply System Piping | Not Started | Yes | 0,0 | 2014-11-26T08:00:00 | 2014-11-26T08:00:00 |
View Details | M5720 | Shipment - Fuel Gas Supply System Piping | Not Started | Yes | 0,0 | 2014-12-03T08:00:00 | 2015-01-16T16:00:00 |
View Details | M5730 | At site - Fuel Gas Supply System Piping | Not Started | Yes | 0,0 | 2015-01-16T16:00:00 | 2015-01-16T16:00:00 |
View Details | J3495 | Transport to Port of Export - Fuel Gas Supply System Piping | Not Started | Yes | 0,0 | 2014-11-26T08:00:00 | 2014-12-02T16:00:00 |
View Details | J3340 | Purchasing - Fuel Gas Supply System | Not Started | Yes | 0,0 | 2014-05-30T08:00:00 | 2014-06-28T16:00:00 |
View Details | J3350 | PO placed - Fuel Gas Supply System | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2014-06-29T08:00:00 |
View Details | J3360 | Delivery Time (incl. Detail Engineering) - Fuel Gas Supply System | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2015-05-24T16:00:00 |
View Details | J3370 | FAT - Fuel Gas Supply System | Not Started | No | 0,0 | 2015-05-11T08:00:00 | 2015-05-17T16:00:00 |
View Details | J3380 | Ready for Shipment - Fuel Gas Supply System | Not Started | Yes | 0,0 | 2015-05-25T08:00:00 | 2015-05-25T08:00:00 |
View Details | M3390 | Shipment (Placeholder / MIG Scope) - Fuel Gas Supply System | Not Started | Yes | 0,0 | 2015-06-01T08:00:00 | 2015-07-15T16:00:00 |
View Details | M3400 | At site - Fuel Gas Supply System | Not Started | Yes | 0,0 | 2015-07-15T16:00:00 | 2015-07-15T16:00:00 |
View Details | J3385 | Transport to Port of Export - Fuel Gas Supply System | Not Started | Yes | 0,0 | 2015-05-25T08:00:00 | 2015-05-31T16:00:00 |
View Details | J3390 | data sheet | Not Started | Yes | 0,0 | 2014-05-30T08:00:00 | 2014-05-30T08:00:00 |
View Details | F2920 | Purchasing - Methanol Injection System | Not Started | Yes | 0,0 | 2014-05-17T08:00:00 | 2014-06-27T16:00:00 |
View Details | F2930 | PO placed - Methanol Injection System | Not Started | Yes | 0,0 | 2014-06-27T16:00:00 | 2014-06-27T16:00:00 |
View Details | F2950 | Ready for Shipment - Methanol Injection System | Not Started | Yes | 0,0 | 2015-04-17T16:00:00 | 2015-04-17T16:00:00 |
View Details | F2940 | Delievery Time - Methanol Injection System | Not Started | Yes | 0,0 | 2014-06-28T08:00:00 | 2015-04-17T16:00:00 |
View Details | M2960 | Shipment - Methanol Injection System | Not Started | Yes | 0,0 | 2015-04-25T08:00:00 | 2015-06-08T16:00:00 |
View Details | M2970 | At site - Methanol Injection System | Not Started | Yes | 0,0 | 2015-06-08T16:00:00 | 2015-06-08T16:00:00 |
View Details | F2955 | Transport to Port of Export - Methanol Injection System | Not Started | Yes | 0,0 | 2015-04-18T08:00:00 | 2015-04-24T16:00:00 |
View Details | F2960 | data sheet | Not Started | Yes | 0,0 | 2014-05-17T08:00:00 | 2014-05-17T08:00:00 |
View Details | J4190 | Purchasing - Methanol injection interconnecting piping | Not Started | Yes | 0,0 | 2014-05-15T08:00:00 | 2014-07-23T16:00:00 |
View Details | J4200 | First PO placed - Methanol injection interconnecting piping | Not Started | Yes | 0,0 | 2014-05-30T08:00:00 | 2014-05-30T08:00:00 |
View Details | J4210 | Delivery Time - Methanol injection interconnecting piping | Not Started | Yes | 0,0 | 2014-05-30T08:00:00 | 2014-10-26T16:00:00 |
View Details | J4230 | Ready for Shipment - Methanol injection interconnecting piping | Not Started | Yes | 0,0 | 2014-10-27T08:00:00 | 2014-10-27T08:00:00 |
View Details | M6080 | Shipment - Methanol injection interconnecting piping | Not Started | Yes | 0,0 | 2014-11-03T08:00:00 | 2014-12-17T16:00:00 |
View Details | M6090 | At site - Methanol injection interconnecting piping | Not Started | Yes | 0,0 | 2014-12-17T16:00:00 | 2014-12-17T16:00:00 |
View Details | J4235 | Transport to Port of Export - Methanol injection interconnecting piping | Not Started | Yes | 0,0 | 2014-10-27T08:00:00 | 2014-11-02T16:00:00 |
View Details | M7050 | Purchasing - Methanol Storage System | Not Started | Yes | 0,0 | 2014-05-17T08:00:00 | 2014-07-28T16:00:00 |
View Details | M7060 | PO placed - Methanol Storage System | Not Started | Yes | 0,0 | 2014-07-28T16:00:00 | 2014-07-28T16:00:00 |
View Details | M7080 | Ready for Shipment - Methanol Storage System | Not Started | Yes | 0,0 | 2014-12-31T16:00:00 | 2014-12-31T16:00:00 |
View Details | M7070 | Delievery Time - Methanol Storage System | Not Started | Yes | 0,0 | 2014-07-29T08:00:00 | 2014-12-31T16:00:00 |
View Details | M7085 | Shipment - Methanol Storage System | Not Started | Yes | 0,0 | 2015-01-01T08:00:00 | 2015-02-22T16:00:00 |
View Details | M7095 | At site - Methanol Storage System | Not Started | No | 0,0 | 2015-02-22T16:00:00 | 2015-02-22T16:00:00 |
View Details | F3040 | Purchasing - Utility Miscellaneous System | Not Started | Yes | 0,0 | 2014-05-10T08:00:00 | 2014-06-20T16:00:00 |
View Details | F3050 | PO placed - Utility Miscellaneous System | Not Started | Yes | 0,0 | 2014-06-20T16:00:00 | 2014-06-20T16:00:00 |
View Details | F3070 | Ready for Shipment - Utility Miscellaneous System | Not Started | Yes | 0,0 | 2015-05-08T16:00:00 | 2015-05-08T16:00:00 |
View Details | F3060 | Delievery Time - Utility Miscellaneous System | Not Started | Yes | 0,0 | 2014-06-21T08:00:00 | 2015-05-08T16:00:00 |
View Details | M3080 | Shipment - Utility Miscellaneous System | Not Started | Yes | 0,0 | 2015-05-16T08:00:00 | 2015-06-29T16:00:00 |
View Details | M3090 | At site - Utility Miscellaneous System | Not Started | Yes | 0,0 | 2015-06-29T16:00:00 | 2015-06-29T16:00:00 |
View Details | F3075 | Transport to Port of Export - Utility Miscellaneous System | Not Started | Yes | 0,0 | 2015-05-09T08:00:00 | 2015-05-15T16:00:00 |
View Details | J4250 | Purchasing - Amine Piping | Not Started | Yes | 0,0 | 2014-06-28T08:00:00 | 2014-09-05T16:00:00 |
View Details | J4260 | First PO placed - Amine Piping | Not Started | Yes | 0,0 | 2014-07-13T08:00:00 | 2014-07-13T08:00:00 |
View Details | J4270 | Delivery Time - Amine Piping | Not Started | Yes | 0,0 | 2014-07-13T08:00:00 | 2014-12-09T16:00:00 |
View Details | J4290 | Ready for Shipment - Amine Piping | Not Started | Yes | 0,0 | 2014-12-10T08:00:00 | 2014-12-10T08:00:00 |
View Details | M5800 | Shipment - Amine Piping | Not Started | Yes | 0,0 | 2014-12-17T08:00:00 | 2015-01-30T16:00:00 |
View Details | M5810 | At site - Amine Piping | Not Started | Yes | 0,0 | 2015-01-30T16:00:00 | 2015-01-30T16:00:00 |
View Details | J4295 | Transport to Port of Export - Amine Piping | Not Started | Yes | 0,0 | 2014-12-10T08:00:00 | 2014-12-16T16:00:00 |
View Details | J4310 | Purchasing - Glycol Piping | Not Started | Yes | 0,0 | 2014-06-28T08:00:00 | 2014-09-05T16:00:00 |
View Details | J4320 | First PO placed - Glycol Piping | Not Started | Yes | 0,0 | 2014-07-13T08:00:00 | 2014-07-13T08:00:00 |
View Details | J4330 | Delivery Time - Glycol Piping | Not Started | Yes | 0,0 | 2014-07-13T08:00:00 | 2014-12-09T16:00:00 |
View Details | J4350 | Ready for Shipment - Glycol Piping | Not Started | Yes | 0,0 | 2014-12-10T08:00:00 | 2014-12-10T08:00:00 |
View Details | M5820 | Shipment - Glycol Piping | Not Started | Yes | 0,0 | 2014-12-17T08:00:00 | 2015-01-30T16:00:00 |
View Details | M5830 | At site - Glycol Piping | Not Started | Yes | 0,0 | 2015-01-30T16:00:00 | 2015-01-30T16:00:00 |
View Details | J4355 | Transport to Port of Export - Glycol Piping | Not Started | Yes | 0,0 | 2014-12-10T08:00:00 | 2014-12-16T16:00:00 |
View Details | J4020 | Purchasing - Interconnecting Piping | Not Started | Yes | 0,0 | 2014-05-22T08:00:00 | 2014-07-30T16:00:00 |
View Details | J4030 | First PO placed - Interconnecting Piping | Not Started | Yes | 0,0 | 2014-06-06T08:00:00 | 2014-06-06T08:00:00 |
View Details | J4040 | Delivery Time - Interconnecting Piping | Not Started | Yes | 0,0 | 2014-06-06T08:00:00 | 2014-11-02T16:00:00 |
View Details | J4060 | Ready for Shipment - Interconnecting Piping | Not Started | Yes | 0,0 | 2014-11-03T08:00:00 | 2014-11-03T08:00:00 |
View Details | M5940 | Shipment - Interconnecting Piping | Not Started | Yes | 0,0 | 2014-11-10T08:00:00 | 2014-12-24T16:00:00 |
View Details | M5950 | At site - Interconnecting Piping | Not Started | Yes | 0,0 | 2014-12-24T16:00:00 | 2014-12-24T16:00:00 |
View Details | J4065 | Transport to Port of Export - Interconnecting Piping | Not Started | Yes | 0,0 | 2014-11-03T08:00:00 | 2014-11-09T16:00:00 |
View Details | J5365 | Ready for Shipment - Interconnecting Piping 60% | Not Started | Yes | 0,0 | 2014-09-12T08:00:00 | 2014-09-12T08:00:00 |
View Details | M5385 | Shipment - Interconnecting Piping 60% | Not Started | Yes | 0,0 | 2014-09-19T08:00:00 | 2014-11-02T16:00:00 |
View Details | M5395 | At site - Interconnecting Piping 60% | Not Started | Yes | 0,0 | 2014-11-02T16:00:00 | 2014-11-02T16:00:00 |
View Details | J5375 | Transport to Port of Export - Interconnecting Piping 60% | Not Started | Yes | 0,0 | 2014-09-12T08:00:00 | 2014-09-18T16:00:00 |
View Details | J5385 | Ready for Shipment - Interconnecting Piping 80% | Not Started | Yes | 0,0 | 2014-10-06T08:00:00 | 2014-10-06T08:00:00 |
View Details | M5405 | Shipment - Interconnecting Piping 80% | Not Started | Yes | 0,0 | 2014-10-13T08:00:00 | 2014-11-26T16:00:00 |
View Details | M5435 | At site - Interconnecting Piping 80% | Not Started | Yes | 0,0 | 2014-11-26T16:00:00 | 2014-11-26T16:00:00 |
View Details | J5395 | Transport to Port of Export - Interconnecting Piping 80% | Not Started | Yes | 0,0 | 2014-10-06T08:00:00 | 2014-10-12T16:00:00 |
View Details | F4830 | Purchasing - Gas Wells System | Not Started | Yes | 0,0 | 2014-05-03T08:00:00 | 2014-06-13T16:00:00 |
View Details | F4840 | PO placed - Gas Wells System | Not Started | Yes | 0,0 | 2014-06-13T16:00:00 | 2014-06-13T16:00:00 |
View Details | F4860 | Ready for Shipment - Gas Wells System (Skid 1-3) | Not Started | Yes | 0,0 | 2015-05-01T16:00:00 | 2015-05-01T16:00:00 |
View Details | F4850 | Delievery Time - Gas Wells System (Skid 1-3) | Not Started | Yes | 0,0 | 2014-06-14T08:00:00 | 2015-05-01T16:00:00 |
View Details | M4870 | Shipment - Gas Wells System (Skid 1-3) | Not Started | Yes | 0,0 | 2015-05-09T08:00:00 | 2015-06-22T16:00:00 |
View Details | M4880 | At site - Gas Wells System (Skid 1-3) | Not Started | Yes | 0,0 | 2015-06-22T16:00:00 | 2015-06-22T16:00:00 |
View Details | F5570 | Ready for Shipment - Gas Wells System (Skid 4-6) | Not Started | Yes | 0,0 | 2015-05-15T16:00:00 | 2015-05-15T16:00:00 |
View Details | F5560 | Delievery Time - Gas Wells System (Skid 4-6) | Not Started | Yes | 0,0 | 2014-06-14T08:00:00 | 2015-05-15T16:00:00 |
View Details | M6120 | Shipment - Gas Wells System (Skid 4-6) | Not Started | Yes | 0,0 | 2015-05-23T08:00:00 | 2015-07-06T16:00:00 |
View Details | M6130 | At site - Gas Wells System (Skid 4-6) | Not Started | Yes | 0,0 | 2015-07-06T16:00:00 | 2015-07-06T16:00:00 |
View Details | F5590 | Ready for Shipment - Gas Wells System (Skid 7-9) | Not Started | Yes | 0,0 | 2015-06-12T16:00:00 | 2015-06-12T16:00:00 |
View Details | F5580 | Delievery Time - Gas Wells System (Skid 7-9) | Not Started | Yes | 0,0 | 2014-06-14T08:00:00 | 2015-06-12T16:00:00 |
View Details | M6140 | Shipment - Gas Wells System (Skid 7-9) | Not Started | Yes | 0,0 | 2015-06-20T08:00:00 | 2015-08-03T16:00:00 |
View Details | M6150 | At site - Gas Wells System (Skid 7-9) | Not Started | Yes | 0,0 | 2015-08-03T16:00:00 | 2015-08-03T16:00:00 |
View Details | F4865 | Transport to Port of Export - Gas Wells System (Skid 1-3) | Not Started | Yes | 0,0 | 2015-05-02T08:00:00 | 2015-05-08T16:00:00 |
View Details | F5575 | Transport to Port of Export - Gas Wells System (Skid 4-6) | Not Started | Yes | 0,0 | 2015-05-16T08:00:00 | 2015-05-22T16:00:00 |
View Details | F5595 | Transport to Port of Export - Gas Wells System (Skid 7-9) | Not Started | Yes | 0,0 | 2015-06-13T08:00:00 | 2015-06-19T16:00:00 |
View Details | F1120 | Purchasing - Water / Condensate Separator System | Not Started | Yes | 0,0 | 2014-04-12T08:00:00 | 2014-05-23T16:00:00 |
View Details | F1130 | PO placed - Water / Condensate Separator System | Not Started | Yes | 0,0 | 2014-05-23T16:00:00 | 2014-05-23T16:00:00 |
View Details | F1150 | Ready for Shipment - Water / Condensate Separator System | Not Started | Yes | 0,0 | 2015-03-06T16:00:00 | 2015-03-06T16:00:00 |
View Details | F1140 | Delievery Time - Water / Condensate Separator System | Not Started | Yes | 0,0 | 2014-05-24T08:00:00 | 2015-03-06T16:00:00 |
View Details | M1160 | Shipment - Water / Condensate Separator System | Not Started | Yes | 0,0 | 2015-03-14T08:00:00 | 2015-04-27T16:00:00 |
View Details | M1170 | At site - Water / Condensate Separator System | Not Started | Yes | 0,0 | 2015-04-27T16:00:00 | 2015-04-27T16:00:00 |
View Details | F1155 | Transport to Port of Export - Water / Condensate Separator System | Not Started | Yes | 0,0 | 2015-03-07T08:00:00 | 2015-03-13T16:00:00 |
View Details | F1720 | Purchasing - Offgas Compression System | Not Started | Yes | 0,0 | 2014-04-12T08:00:00 | 2014-05-23T16:00:00 |
View Details | F1730 | PO placed - Offgas Compression System | Not Started | Yes | 0,0 | 2014-05-23T16:00:00 | 2014-05-23T16:00:00 |
View Details | F1750 | Ready for Shipment - Offgas Compression System | Not Started | Yes | 0,0 | 2015-06-19T16:00:00 | 2015-06-19T16:00:00 |
View Details | F1740 | Delievery Time - Offgas Compression System | Not Started | Yes | 0,0 | 2014-05-24T08:00:00 | 2015-06-19T16:00:00 |
View Details | M1760 | Shipment - Offgas Compression System | Not Started | Yes | 0,0 | 2015-06-27T08:00:00 | 2015-08-10T16:00:00 |
View Details | M1770 | At site - Offgas Compression System | Not Started | Yes | 0,0 | 2015-08-10T16:00:00 | 2015-08-10T16:00:00 |
View Details | F1755 | Transport to Port of Export - Offgas Compression System | Not Started | Yes | 0,0 | 2015-06-20T08:00:00 | 2015-06-26T16:00:00 |
View Details | J3900 | Purchasing - Off gas interconnecting piping | Not Started | Yes | 0,0 | 2014-05-22T08:00:00 | 2014-07-30T16:00:00 |
View Details | J3910 | First PO placed - Off gas interconnecting piping | Not Started | Yes | 0,0 | 2014-06-06T08:00:00 | 2014-06-06T08:00:00 |
View Details | J3920 | Delivery Time - Off gas interconnecting piping | Not Started | Yes | 0,0 | 2014-06-06T08:00:00 | 2015-01-01T16:00:00 |
View Details | J3940 | Ready for Shipment (Ex Works) - Off gas interconnecting piping | Not Started | Yes | 0,0 | 2015-01-02T08:00:00 | 2015-01-02T08:00:00 |
View Details | M5600 | Shipment - Off gas interconnecting piping | Not Started | Yes | 0,0 | 2015-01-09T08:00:00 | 2015-02-22T16:00:00 |
View Details | M5610 | At site - Off gas interconnecting piping | Not Started | Yes | 0,0 | 2015-02-22T16:00:00 | 2015-02-22T16:00:00 |
View Details | J3945 | Transport to Port of Export - Off gas interconnecting piping | Not Started | Yes | 0,0 | 2015-01-02T08:00:00 | 2015-01-08T16:00:00 |
View Details | J5050 | Purchasing - Plant Air Piping | Not Started | Yes | 0,0 | 2014-05-15T08:00:00 | 2014-07-23T16:00:00 |
View Details | J5060 | First PO placed - Plant Air Piping | Not Started | Yes | 0,0 | 2014-05-30T08:00:00 | 2014-05-30T08:00:00 |
View Details | J5070 | Delivery Time - Plant Air Piping | Not Started | Yes | 0,0 | 2014-05-30T08:00:00 | 2014-10-26T16:00:00 |
View Details | J5090 | Ready for Shipment - Plant Air Piping | Not Started | Yes | 0,0 | 2014-10-27T08:00:00 | 2014-10-27T08:00:00 |
View Details | M5900 | Shipment - Plant Air Piping | Not Started | Yes | 0,0 | 2014-11-03T08:00:00 | 2014-12-17T16:00:00 |
View Details | M5910 | At site - Plant Air Piping | Not Started | No | 0,0 | 2014-12-17T16:00:00 | 2014-12-17T16:00:00 |
View Details | J5095 | Transport to Port of Export - Plant Air Piping | Not Started | Yes | 0,0 | 2014-10-27T08:00:00 | 2014-11-02T16:00:00 |
View Details | J4940 | Purchasing - Instrument & Plant Air System | Not Started | Yes | 0,0 | 2014-05-30T08:00:00 | 2014-06-28T16:00:00 |
View Details | J4950 | PO placed - Instrument & Plant Air System | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2014-06-29T08:00:00 |
View Details | J4960 | Delivery Time (incl. Detail Engineering) - Instrument & Plant Air System | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2014-12-25T16:00:00 |
View Details | J4970 | FAT - Instrument & Plant Air System | Not Started | No | 0,0 | 2014-12-12T08:00:00 | 2014-12-18T16:00:00 |
View Details | J4980 | Ready for Shipment - Instrument & Plant Air System | Not Started | Yes | 0,0 | 2014-12-26T08:00:00 | 2014-12-26T08:00:00 |
View Details | M3120 | Shipment (Placeholder / MIG Scope) - Instrument & Plant Air System | Not Started | Yes | 0,0 | 2015-01-02T08:00:00 | 2015-02-15T16:00:00 |
View Details | M3130 | At site - Instrument & Plant Air System | Not Started | No | 0,0 | 2015-02-15T16:00:00 | 2015-02-15T16:00:00 |
View Details | J4985 | Transport to Port of Export - Instrument & Plant Air System | Not Started | Yes | 0,0 | 2014-12-26T08:00:00 | 2015-01-01T16:00:00 |
View Details | J5110 | Purchasing - Instrument Air Piping | Not Started | Yes | 0,0 | 2014-05-15T08:00:00 | 2014-07-23T16:00:00 |
View Details | J5120 | First PO placed - Instrument Air Piping | Not Started | No | 0,0 | 2014-05-30T08:00:00 | 2014-05-30T08:00:00 |
View Details | J5130 | Delivery Time - Instrument Air Piping | Not Started | Yes | 0,0 | 2014-10-27T08:00:00 | 2015-03-25T16:00:00 |
View Details | J5150 | Ready for Shipment - Instrument Air Piping | Not Started | Yes | 0,0 | 2015-03-26T08:00:00 | 2015-03-26T08:00:00 |
View Details | M5920 | Shipment - Instrument Air Piping | Not Started | Yes | 0,0 | 2015-04-02T08:00:00 | 2015-05-16T16:00:00 |
View Details | M5930 | At site - Instrument Air Piping | Not Started | Yes | 0,0 | 2015-05-16T16:00:00 | 2015-05-16T16:00:00 |
View Details | J5155 | Transport to Port of Export - Instrument Air Piping | Not Started | Yes | 0,0 | 2015-03-26T08:00:00 | 2015-04-01T16:00:00 |
View Details | M3501 | Purchasing - Open Drains System | Not Started | Yes | 0,0 | 2014-07-20T08:00:00 | 2014-08-19T16:00:00 |
View Details | M3502 | PO placed - Open Drains System | Not Started | Yes | 0,0 | 2014-08-19T16:00:00 | 2014-08-19T16:00:00 |
View Details | M3504 | Ready for Shipment - Open Drains System | Not Started | Yes | 0,0 | 2014-11-17T16:00:00 | 2014-11-17T16:00:00 |
View Details | M3503 | Delievery Time - Open Drains System | Not Started | Yes | 0,0 | 2014-08-20T08:00:00 | 2014-11-17T16:00:00 |
View Details | M3505 | Shipment - Open Drains System | Not Started | Yes | 0,0 | 2014-11-18T08:00:00 | 2014-12-18T16:00:00 |
View Details | M3506 | At site - Open Drains System | Not Started | No | 0,0 | 2014-12-18T16:00:00 | 2014-12-18T16:00:00 |
View Details | M31001 | Camp | Not Started | No | 0,0 | 2014-06-01T08:00:00 | 2014-09-29T16:00:00 |
View Details | J1590 | Purchasing - UPS 230V AC | Not Started | Yes | 0,0 | 2014-05-30T08:00:00 | 2014-06-28T16:00:00 |
View Details | J1600 | PO placed - UPS 230V AC | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2014-06-29T08:00:00 |
View Details | J1610 | Delivery Time (incl. Detail Engineering) - UPS 230V AC | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2015-01-24T16:00:00 |
View Details | J1620 | FAT - UPS 230V AC | Not Started | No | 0,0 | 2015-01-11T08:00:00 | 2015-01-17T16:00:00 |
View Details | J1630 | Ready for Shipment - UPS 230V AC | Not Started | Yes | 0,0 | 2015-01-25T08:00:00 | 2015-01-25T08:00:00 |
View Details | M1570 | Shipment (Placeholder / MIG Scope) - UPS 230V AC | Not Started | Yes | 0,0 | 2015-02-01T08:00:00 | 2015-04-01T16:00:00 |
View Details | M1580 | At site - UPS 230V AC | Not Started | Yes | 0,0 | 2015-04-01T16:00:00 | 2015-04-01T16:00:00 |
View Details | J1635 | Transport to Port of Export - UPS 230V AC | Not Started | Yes | 0,0 | 2015-01-25T08:00:00 | 2015-01-31T16:00:00 |
View Details | J1100 | Purchasing - LV System 400V | Not Started | Yes | 0,0 | 2014-05-30T08:00:00 | 2014-06-28T16:00:00 |
View Details | J1110 | PO placed - LV System 400V | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2014-06-29T08:00:00 |
View Details | J1120 | Delivery Time (incl. Detail Engineering) - LV System 400V | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2015-02-23T16:00:00 |
View Details | J1130 | FAT - LV System 400V | Not Started | No | 0,0 | 2015-02-10T08:00:00 | 2015-02-16T16:00:00 |
View Details | J1140 | Ready for Shipment - LV System 400V | Not Started | Yes | 0,0 | 2015-02-24T08:00:00 | 2015-02-24T08:00:00 |
View Details | M1180 | Shipment (Placeholder / MIG Scope) - LV System 400V | Not Started | Yes | 0,0 | 2015-03-03T08:00:00 | 2015-05-01T16:00:00 |
View Details | M1190 | At site - LV System 400V | Not Started | Yes | 0,0 | 2015-05-01T16:00:00 | 2015-05-01T16:00:00 |
View Details | J1145 | Transport to Port of Export - LV System 400V | Not Started | Yes | 0,0 | 2015-02-24T08:00:00 | 2015-03-02T16:00:00 |
View Details | J1780 | Purchasing - Plant Communication and Visualization System | Not Started | Yes | 0,0 | 2014-05-30T08:00:00 | 2014-06-28T16:00:00 |
View Details | J1790 | PO placed - Plant Communication and Visualization System | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2014-06-29T08:00:00 |
View Details | J1800 | Delivery Time (incl. Detail Engineering) - Plant Communication and Visualization System | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2015-01-24T16:00:00 |
View Details | J1810 | FAT - Plant Communication and Visualization System | Not Started | No | 0,0 | 2015-01-11T08:00:00 | 2015-01-17T16:00:00 |
View Details | J1820 | Ready for Shipment - Plant Communication and Visualization System | Not Started | Yes | 0,0 | 2015-01-25T08:00:00 | 2015-01-25T08:00:00 |
View Details | M1830 | Shipment (Placeholder / MIG Scope) - Plant Communication and Visualization System | Not Started | Yes | 0,0 | 2015-02-01T08:00:00 | 2015-04-01T16:00:00 |
View Details | M1840 | At site - Plant Communication and Visualization System | Not Started | Yes | 0,0 | 2015-04-01T16:00:00 | 2015-04-01T16:00:00 |
View Details | J1825 | Transport to Port of Export - Plant Communication and Visualization System | Not Started | Yes | 0,0 | 2015-01-25T08:00:00 | 2015-01-31T16:00:00 |
View Details | J1400 | Purchasing - Battery System 220V DC | Not Started | Yes | 0,0 | 2014-05-30T08:00:00 | 2014-06-28T16:00:00 |
View Details | J1410 | PO placed - Battery System 220V DC | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2014-06-29T08:00:00 |
View Details | J1420 | Delivery Time (incl. Detail Engineering) - Battery System 220V DC | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2015-02-23T16:00:00 |
View Details | J1430 | FAT - Battery System 220V DC | Not Started | No | 0,0 | 2015-02-10T08:00:00 | 2015-02-16T16:00:00 |
View Details | J1440 | Ready for Shipment - Battery System 220V DC | Not Started | Yes | 0,0 | 2015-02-24T08:00:00 | 2015-02-24T08:00:00 |
View Details | M1450 | Shipment (Placeholder / MIG Scope) - Battery System 220V DC | Not Started | Yes | 0,0 | 2015-03-03T08:00:00 | 2015-05-01T16:00:00 |
View Details | M1460 | At site - Battery System 220V DC | Not Started | Yes | 0,0 | 2015-05-01T16:00:00 | 2015-05-01T16:00:00 |
View Details | J1445 | Transport to Port of Export - Battery System 220V DC | Not Started | Yes | 0,0 | 2015-02-24T08:00:00 | 2015-03-02T16:00:00 |
View Details | J1690 | Purchasing - Lighting and Grounding System | Not Started | Yes | 0,0 | 2014-05-30T08:00:00 | 2014-06-28T16:00:00 |
View Details | J1700 | PO placed - Lighting and Grounding System | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2014-06-29T08:00:00 |
View Details | J1710 | Delivery Time (incl. Detail Engineering) - Lighting and Grounding System | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2014-09-26T16:00:00 |
View Details | J1720 | FAT - Lighting and Grounding System | Not Started | No | 0,0 | 2014-09-13T08:00:00 | 2014-09-19T16:00:00 |
View Details | J1730 | Ready for Shipment - Lighting and Grounding System | Not Started | Yes | 0,0 | 2014-09-27T08:00:00 | 2014-09-27T08:00:00 |
View Details | M1740 | Shipment (Placeholder / MIG Scope) - Lighting and Grounding System | Not Started | Yes | 0,0 | 2014-10-04T08:00:00 | 2014-12-02T16:00:00 |
View Details | M1750 | At site - Lighting and Grounding System | Not Started | Yes | 0,0 | 2014-12-02T16:00:00 | 2014-12-02T16:00:00 |
View Details | J1735 | Transport to Port of Export - Lighting and Grounding System | Not Started | Yes | 0,0 | 2014-09-27T08:00:00 | 2014-10-03T16:00:00 |
View Details | J2050 | Purchasing - Field Instruments | Not Started | Yes | 0,0 | 2014-06-10T10:00:00 | 2014-07-10T10:00:00 |
View Details | J2060 | PO placed - Field Instruments | Not Started | Yes | 0,0 | 2014-07-10T10:00:00 | 2014-07-10T10:00:00 |
View Details | J2070 | Delivery Time (incl. Detail Engineering) - Field Instruments | Not Started | Yes | 0,0 | 2014-07-10T10:00:00 | 2014-10-08T10:00:00 |
View Details | J2080 | FAT - Field Instruments | Not Started | No | 0,0 | 2014-09-24T10:00:00 | 2014-10-01T10:00:00 |
View Details | J2090 | Ready for Shipment - Field Instruments | Not Started | Yes | 0,0 | 2014-10-08T10:00:00 | 2014-10-08T10:00:00 |
View Details | M2100 | Shipment (Placeholder / MIG Scope) - Field Instruments | Not Started | Yes | 0,0 | 2014-10-15T10:00:00 | 2014-12-14T10:00:00 |
View Details | M2115 | At site - Field Instruments | Not Started | No | 0,0 | 2014-12-14T10:00:00 | 2014-12-14T10:00:00 |
View Details | J2095 | Transport to Port of Export - Field Instruments | Not Started | Yes | 0,0 | 2014-10-08T10:00:00 | 2014-10-15T10:00:00 |
View Details | J2150 | Purchasing - Field Cabling | Not Started | Yes | 0,0 | 2014-05-22T12:00:00 | 2014-06-21T12:00:00 |
View Details | J2160 | PO placed - Field Cabling | Not Started | Yes | 0,0 | 2014-06-21T12:00:00 | 2014-06-21T12:00:00 |
View Details | J2170 | Delivery Time (incl. Detail Engineering) - Field Cabling | Not Started | Yes | 0,0 | 2014-06-21T12:00:00 | 2014-11-18T12:00:00 |
View Details | J2180 | Ready for Shipment - Field Cabling | Not Started | Yes | 0,0 | 2014-11-18T12:00:00 | 2014-11-18T12:00:00 |
View Details | M2190 | Shipment (Placeholder / MIG Scope) - Field Cabling | Not Started | Yes | 0,0 | 2014-11-25T12:00:00 | 2015-01-24T12:00:00 |
View Details | M2200 | At site - Field Cabling | Not Started | Yes | 0,0 | 2015-01-24T12:00:00 | 2015-01-24T12:00:00 |
View Details | J2185 | Transport to Port of Export - Field Cabling | Not Started | Yes | 0,0 | 2014-11-18T12:00:00 | 2014-11-25T12:00:00 |
View Details | J1000 | Purchasing - MV System 6.6kV | Not Started | Yes | 0,0 | 2014-05-30T08:00:00 | 2014-06-28T16:00:00 |
View Details | J1010 | PO placed - MV System 6.6kV | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2014-06-29T08:00:00 |
View Details | J1020 | Delivery Time (incl. Detail Engineering) - MV System 6.6kV | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2015-01-24T16:00:00 |
View Details | J1030 | FAT - MV System 6.6kV | Not Started | No | 0,0 | 2015-01-11T08:00:00 | 2015-01-17T16:00:00 |
View Details | J1040 | Ready for Shipment - MV System 6.6kV | Not Started | Yes | 0,0 | 2015-01-25T08:00:00 | 2015-01-25T08:00:00 |
View Details | M1050 | Shipment (Placeholder / MIG Scope) - MV System 6.6kV | Not Started | Yes | 0,0 | 2015-02-01T08:00:00 | 2015-04-01T16:00:00 |
View Details | M1060 | At site - MV System 6.6kV | Not Started | Yes | 0,0 | 2015-04-01T16:00:00 | 2015-04-01T16:00:00 |
View Details | J1045 | Transport to Port of Export - MV System 6.6kV | Not Started | Yes | 0,0 | 2015-01-25T08:00:00 | 2015-01-31T16:00:00 |
View Details | J1300 | Purchasing - Frequency Inverter | Not Started | Yes | 0,0 | 2014-04-30T08:00:00 | 2014-05-29T16:00:00 |
View Details | J1310 | PO placed - Frequency Inverter | Not Started | Yes | 0,0 | 2014-05-30T08:00:00 | 2014-05-30T08:00:00 |
View Details | J1320 | Delivery Time (incl. Detail Engineering) - Frequency Inverter | Not Started | Yes | 0,0 | 2014-05-30T08:00:00 | 2014-08-27T16:00:00 |
View Details | J1330 | FAT - Frequency Inverter | Not Started | No | 0,0 | 2014-08-14T08:00:00 | 2014-08-20T16:00:00 |
View Details | J1340 | Ready for Shipment - Frequency Inverter | Not Started | Yes | 0,0 | 2014-08-28T08:00:00 | 2014-08-28T08:00:00 |
View Details | M1350 | Shipment (Placeholder / MIG Scope) - Frequency Inverter | Not Started | Yes | 0,0 | 2014-09-04T08:00:00 | 2014-11-02T16:00:00 |
View Details | M1360 | At site - Frequency Inverter | Not Started | Yes | 0,0 | 2014-11-02T16:00:00 | 2014-11-02T16:00:00 |
View Details | J1345 | Transport to Port of Export - Frequency Inverter | Not Started | Yes | 0,0 | 2014-08-28T08:00:00 | 2014-09-03T16:00:00 |
View Details | J1200 | Purchasing - LV Trafos | Not Started | Yes | 0,0 | 2014-04-30T08:00:00 | 2014-05-29T16:00:00 |
View Details | J1210 | PO placed - LV Trafos | Not Started | Yes | 0,0 | 2014-05-30T08:00:00 | 2014-05-30T08:00:00 |
View Details | J1220 | Delivery Time (incl. Detail Engineering) - LV Trafos | Not Started | Yes | 0,0 | 2014-05-30T08:00:00 | 2014-12-25T16:00:00 |
View Details | J1230 | FAT - LV Trafos | Not Started | No | 0,0 | 2014-12-12T08:00:00 | 2014-12-18T16:00:00 |
View Details | J1240 | Ready for Shipment - LV Trafos | Not Started | Yes | 0,0 | 2014-12-26T08:00:00 | 2014-12-26T08:00:00 |
View Details | M1250 | Shipment (Placeholder / MIG Scope) - LV Trafos | Not Started | Yes | 0,0 | 2015-01-02T08:00:00 | 2015-03-02T16:00:00 |
View Details | M1260 | At site - LV Trafos | Not Started | Yes | 0,0 | 2015-03-02T16:00:00 | 2015-03-02T16:00:00 |
View Details | J1245 | Transport to Port of Export - LV Trafos | Not Started | Yes | 0,0 | 2014-12-26T08:00:00 | 2015-01-01T16:00:00 |
View Details | J1950 | Purchasing - ICSS System | Not Started | Yes | 0,0 | 2014-06-21T12:00:00 | 2014-07-21T12:00:00 |
View Details | J1960 | PO placed - ICSS System | Not Started | Yes | 0,0 | 2014-07-21T12:00:00 | 2014-07-21T12:00:00 |
View Details | J1970 | Delivery Time (incl. Detail Engineering) - ICSS System | Not Started | Yes | 0,0 | 2014-07-21T12:00:00 | 2015-02-16T12:00:00 |
View Details | J1980 | FAT - ICSS System | Not Started | No | 0,0 | 2015-02-02T12:00:00 | 2015-02-09T12:00:00 |
View Details | J1990 | Ready for Shipment - ICSS System | Not Started | Yes | 0,0 | 2015-02-16T12:00:00 | 2015-02-16T12:00:00 |
View Details | M1930 | Shipment (Placeholder / MIG Scope) - ICSS System | Not Started | Yes | 0,0 | 2015-02-23T12:00:00 | 2015-04-24T12:00:00 |
View Details | M1940 | At site - ICSS System | Not Started | Yes | 0,0 | 2015-04-24T12:00:00 | 2015-04-24T12:00:00 |
View Details | J1995 | Transport to Port of Export - ICSS System | Not Started | Yes | 0,0 | 2015-02-16T12:00:00 | 2015-02-23T12:00:00 |
View Details | J1870 | Purchasing - Cables and Cable Trays | Not Started | Yes | 0,0 | 2014-05-30T08:00:00 | 2014-06-28T16:00:00 |
View Details | J1880 | PO placed - Cables and Cable Trays | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2014-06-29T08:00:00 |
View Details | J1890 | Delivery Time (incl. Detail Engineering) - Cables and Cable Trays | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2014-11-25T16:00:00 |
View Details | J1900 | Ready for Shipment - Cables and Cable Trays | Not Started | Yes | 0,0 | 2014-11-26T08:00:00 | 2014-11-26T08:00:00 |
View Details | M1910 | Shipment (Placeholder / MIG Scope) - Cables and Cable Trays | Not Started | Yes | 0,0 | 2014-12-03T08:00:00 | 2015-01-31T16:00:00 |
View Details | M1920 | At site - Cables and Cable Trays | Not Started | Yes | 0,0 | 2015-01-31T16:00:00 | 2015-01-31T16:00:00 |
View Details | J1905 | Transport to Port of Export - Cables and Cable Trays | Not Started | Yes | 0,0 | 2014-11-26T08:00:00 | 2014-12-02T16:00:00 |
View Details | J1500 | Purchasing - Small Power System | Not Started | Yes | 0,0 | 2014-06-09T08:00:00 | 2014-07-08T16:00:00 |
View Details | J1510 | PO placed - Small Power System | Not Started | Yes | 0,0 | 2014-07-09T08:00:00 | 2014-07-09T08:00:00 |
View Details | J1520 | Delivery Time (incl. Detail Engineering) - Small Power System | Not Started | Yes | 0,0 | 2014-07-09T08:00:00 | 2015-03-05T16:00:00 |
View Details | J1530 | FAT - Small Power System | Not Started | No | 0,0 | 2015-02-20T08:00:00 | 2015-02-26T16:00:00 |
View Details | J1540 | Ready for Shipment - Small Power System | Not Started | Yes | 0,0 | 2015-03-06T08:00:00 | 2015-03-06T08:00:00 |
View Details | M1550 | Shipment (Placeholder / MIG Scope) - Small Power System | Not Started | Yes | 0,0 | 2015-03-13T08:00:00 | 2015-05-11T16:00:00 |
View Details | M1560 | At site - Small Power System | Not Started | Yes | 0,0 | 2015-05-11T16:00:00 | 2015-05-11T16:00:00 |
View Details | J1545 | Transport to Port of Export - Small Power System | Not Started | Yes | 0,0 | 2015-03-06T08:00:00 | 2015-03-12T16:00:00 |
View Details | J3230 | Purchasing - Inertgas interconnecting Piping | Not Started | Yes | 0,0 | 2014-05-15T08:00:00 | 2014-07-23T16:00:00 |
View Details | J3240 | First PO placed - Inertgas interconnecting Piping | Not Started | Yes | 0,0 | 2014-05-30T08:00:00 | 2014-05-30T08:00:00 |
View Details | J3250 | Delivery Time - Inertgas interconnecting Piping | Not Started | Yes | 0,0 | 2014-05-30T08:00:00 | 2014-10-26T16:00:00 |
View Details | J3270 | Ready for Shipment - Inertgas interconnecting Piping | Not Started | Yes | 0,0 | 2014-10-27T08:00:00 | 2014-10-27T08:00:00 |
View Details | M6100 | Shipment - Inertgas interconnecting Piping | Not Started | Yes | 0,0 | 2014-11-03T08:00:00 | 2014-12-17T16:00:00 |
View Details | M6110 | At site - Inertgas interconnecting Piping | Not Started | Yes | 0,0 | 2014-12-17T16:00:00 | 2014-12-17T16:00:00 |
View Details | J3275 | Transport to Port of Export - Inertgas interconnecting Piping | Not Started | Yes | 0,0 | 2014-10-27T08:00:00 | 2014-11-02T16:00:00 |
View Details | J2430 | Purchasing - Nitrogen System | Not Started | Yes | 0,0 | 2014-05-30T08:00:00 | 2014-06-28T16:00:00 |
View Details | J2440 | PO placed - Nitrogen System | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2014-06-29T08:00:00 |
View Details | J2450 | Delivery Time (incl. Detail Engineering) - Nitrogen System | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2015-04-24T16:00:00 |
View Details | J2460 | FAT - Nitrogen System | Not Started | No | 0,0 | 2015-04-11T08:00:00 | 2015-04-17T16:00:00 |
View Details | J2470 | Ready for Shipment - Nitrogen System | Not Started | Yes | 0,0 | 2015-04-25T08:00:00 | 2015-04-25T08:00:00 |
View Details | M3100 | Shipment (Placeholder / MIG Scope) - Nitrogen System | Not Started | Yes | 0,0 | 2015-05-02T08:00:00 | 2015-06-15T16:00:00 |
View Details | M3110 | At site - Nitrogen System | Not Started | Yes | 0,0 | 2015-06-15T16:00:00 | 2015-06-15T16:00:00 |
View Details | J2475 | Transport to Port of Export - Nitrogen System | Not Started | Yes | 0,0 | 2015-04-25T08:00:00 | 2015-05-01T16:00:00 |
View Details | J4370 | Purchasing - Aquifer / Plant Water System | Not Started | Yes | 0,0 | 2014-06-12T08:00:00 | 2014-07-11T16:00:00 |
View Details | J4380 | PO placed - Aquifer / Plant Water System | Not Started | Yes | 0,0 | 2014-07-12T08:00:00 | 2014-07-12T08:00:00 |
View Details | J4390 | Delivery Time (incl. Detail Engineering) - Aquifer / Plant Water System | Not Started | Yes | 0,0 | 2014-07-12T08:00:00 | 2015-02-06T16:00:00 |
View Details | J4400 | FAT - Aquifer / Plant Water System | Not Started | No | 0,0 | 2015-01-24T08:00:00 | 2015-01-30T16:00:00 |
View Details | J4410 | Ready for Shipment - Aquifer / Plant Water System | Not Started | Yes | 0,0 | 2015-02-07T08:00:00 | 2015-02-07T08:00:00 |
View Details | M4420 | Shipment (Placeholder / MIG Scope) - Aquifer / Plant Water System | Not Started | Yes | 0,0 | 2015-02-14T08:00:00 | 2015-03-30T16:00:00 |
View Details | M4430 | At site - Aquifer / Plant Water System | Not Started | Yes | 0,0 | 2015-03-30T16:00:00 | 2015-03-30T16:00:00 |
View Details | J4415 | Transport to Port of Export - Aquifer / Plant Water System | Not Started | Yes | 0,0 | 2015-02-07T08:00:00 | 2015-02-13T16:00:00 |
View Details | J4480 | Purchasing - Plant Water Piping | Not Started | Yes | 0,0 | 2014-06-21T08:00:00 | 2014-08-29T16:00:00 |
View Details | J4490 | First PO placed - Plant Water Piping | Not Started | Yes | 0,0 | 2014-07-06T08:00:00 | 2014-07-06T08:00:00 |
View Details | J4500 | Delivery Time - Plant Water Piping | Not Started | Yes | 0,0 | 2014-07-06T08:00:00 | 2014-12-02T16:00:00 |
View Details | J4520 | Ready for Shipment - Plant Water Piping | Not Started | Yes | 0,0 | 2014-12-03T08:00:00 | 2014-12-03T08:00:00 |
View Details | M5840 | Shipment - Plant Water Piping | Not Started | Yes | 0,0 | 2014-12-10T08:00:00 | 2015-01-23T16:00:00 |
View Details | M5850 | At site - Plant Water Piping | Not Started | Yes | 0,0 | 2015-01-23T16:00:00 | 2015-01-23T16:00:00 |
View Details | J4525 | Transport to Port of Export - Plant Water Piping | Not Started | Yes | 0,0 | 2014-12-03T08:00:00 | 2014-12-09T16:00:00 |
View Details | J3530 | Purchasing - Chlorination System | Not Started | Yes | 0,0 | 2014-05-30T08:00:00 | 2014-06-28T16:00:00 |
View Details | J3540 | PO placed - Chlorination System | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2014-06-29T08:00:00 |
View Details | J3550 | Delivery Time - Chlorination System | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2015-01-24T16:00:00 |
View Details | J3560 | FAT - Chlorination System | Not Started | No | 0,0 | 2015-01-11T08:00:00 | 2015-01-17T16:00:00 |
View Details | J3570 | Ready for Shipment - Chlorination System | Not Started | Yes | 0,0 | 2015-01-25T08:00:00 | 2015-01-25T08:00:00 |
View Details | M3580 | Shipment (Placeholder / MIG Scope) - Chlorination System | Not Started | Yes | 0,0 | 2015-02-01T08:00:00 | 2015-03-17T16:00:00 |
View Details | M3590 | At site - Chlorination System | Not Started | Yes | 0,0 | 2015-03-17T16:00:00 | 2015-03-17T16:00:00 |
View Details | J3575 | Transport to Port of Export - Chlorination System | Not Started | Yes | 0,0 | 2015-01-25T08:00:00 | 2015-01-31T16:00:00 |
View Details | J3640 | Purchasing - Chlorination System Piping | Not Started | Yes | 0,0 | 2014-06-21T08:00:00 | 2014-08-29T16:00:00 |
View Details | J3650 | First PO placed - Chlorination System Piping | Not Started | Yes | 0,0 | 2014-07-06T08:00:00 | 2014-07-06T08:00:00 |
View Details | J3660 | Delivery Time - Chlorination System Piping | Not Started | Yes | 0,0 | 2014-07-06T08:00:00 | 2014-12-02T16:00:00 |
View Details | J3680 | Ready for Shipment - Chlorination System Piping | Not Started | Yes | 0,0 | 2014-12-03T08:00:00 | 2014-12-03T08:00:00 |
View Details | M5780 | Shipment - Chlorination System Piping | Not Started | Yes | 0,0 | 2014-12-10T08:00:00 | 2015-01-23T16:00:00 |
View Details | M5790 | At site - Chlorination System Piping | Not Started | Yes | 0,0 | 2015-01-23T16:00:00 | 2015-01-23T16:00:00 |
View Details | J3685 | Transport to Port of Export - Chlorination System Piping | Not Started | Yes | 0,0 | 2014-12-03T08:00:00 | 2014-12-09T16:00:00 |
View Details | J4820 | Purchasing - Demin Water System Piping | Not Started | Yes | 0,0 | 2014-06-21T08:00:00 | 2014-08-29T16:00:00 |
View Details | J4830 | First PO placed - Demin Water System Piping | Not Started | Yes | 0,0 | 2014-07-06T08:00:00 | 2014-07-06T08:00:00 |
View Details | J4840 | Delivery Time - Demin Water System Piping | Not Started | Yes | 0,0 | 2014-07-06T08:00:00 | 2014-12-02T16:00:00 |
View Details | J4860 | Ready for Shipment - Demin Water System Piping | Not Started | Yes | 0,0 | 2014-12-03T08:00:00 | 2014-12-03T08:00:00 |
View Details | M5880 | Shipment - Demin Water System Piping | Not Started | Yes | 0,0 | 2014-12-10T08:00:00 | 2015-01-23T16:00:00 |
View Details | M5890 | At site - Demin Water System Piping | Not Started | Yes | 0,0 | 2015-01-23T16:00:00 | 2015-01-23T16:00:00 |
View Details | J4865 | Transport to Port of Export - Demin Water System Piping | Not Started | Yes | 0,0 | 2014-12-03T08:00:00 | 2014-12-09T16:00:00 |
View Details | J4650 | Purchasing - Demin Water System | Not Started | Yes | 0,0 | 2014-05-30T08:00:00 | 2014-06-28T16:00:00 |
View Details | J4660 | PO placed - Demin Water System | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2014-06-29T08:00:00 |
View Details | J4670 | Delivery Time (incl. Detail Engineering) - Demin Water System | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2015-01-24T16:00:00 |
View Details | J4680 | FAT - Demin Water System | Not Started | No | 0,0 | 2015-01-11T08:00:00 | 2015-01-17T16:00:00 |
View Details | J4690 | Ready for Shipment - Demin Water System | Not Started | Yes | 0,0 | 2015-01-25T08:00:00 | 2015-01-25T08:00:00 |
View Details | M4700 | Shipment (Placeholder / MIG Scope) - Demin Water System | Not Started | Yes | 0,0 | 2015-02-01T08:00:00 | 2015-03-17T16:00:00 |
View Details | M4710 | At site - Demin Water System | Not Started | Yes | 0,0 | 2015-03-17T16:00:00 | 2015-03-17T16:00:00 |
View Details | J4695 | Transport to Port of Export - Demin Water System | Not Started | Yes | 0,0 | 2015-01-25T08:00:00 | 2015-01-31T16:00:00 |
View Details | J4540 | Purchasing - Fresh Water System | Not Started | Yes | 0,0 | 2014-05-30T08:00:00 | 2014-06-28T16:00:00 |
View Details | J4550 | PO placed - Fresh Water System | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2014-06-29T08:00:00 |
View Details | J4560 | Delivery Time (incl. Detail Engineering) - Fresh Water System | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2015-01-24T16:00:00 |
View Details | J4570 | FAT - Fresh Water System | Not Started | No | 0,0 | 2015-01-11T08:00:00 | 2015-01-17T16:00:00 |
View Details | J4580 | Ready for Shipment - Fresh Water System | Not Started | Yes | 0,0 | 2015-01-25T08:00:00 | 2015-01-25T08:00:00 |
View Details | M4590 | Shipment (Placeholder / MIG Scope) - Fresh Water System | Not Started | Yes | 0,0 | 2015-02-01T08:00:00 | 2015-03-17T16:00:00 |
View Details | M4600 | At site - Fresh Water System | Not Started | Yes | 0,0 | 2015-03-17T16:00:00 | 2015-03-17T16:00:00 |
View Details | J4585 | Transport to Port of Export - Fresh Water System | Not Started | Yes | 0,0 | 2015-01-25T08:00:00 | 2015-01-31T16:00:00 |
View Details | J4760 | Purchasing - Fresh Water System Piping | Not Started | Yes | 0,0 | 2014-06-21T08:00:00 | 2014-08-29T16:00:00 |
View Details | J4770 | First PO placed - Fresh Water System Piping | Not Started | Yes | 0,0 | 2014-07-06T08:00:00 | 2014-07-06T08:00:00 |
View Details | J4780 | Delivery Time - Fresh Water System Piping | Not Started | Yes | 0,0 | 2014-07-06T08:00:00 | 2014-12-02T16:00:00 |
View Details | J4800 | Ready for Shipment - Fresh Water System Piping | Not Started | Yes | 0,0 | 2014-12-03T08:00:00 | 2014-12-03T08:00:00 |
View Details | M5860 | Shipment - Fresh Water System Piping | Not Started | Yes | 0,0 | 2014-12-10T08:00:00 | 2015-01-23T16:00:00 |
View Details | M5870 | At site - Fresh Water System Piping | Not Started | Yes | 0,0 | 2015-01-23T16:00:00 | 2015-01-23T16:00:00 |
View Details | J4805 | Transport to Port of Export - Fresh Water System Piping | Not Started | Yes | 0,0 | 2014-12-03T08:00:00 | 2014-12-09T16:00:00 |
View Details | M3601 | Purchasing - Closed Drains System | Not Started | Yes | 0,0 | 2014-07-20T08:00:00 | 2014-08-19T16:00:00 |
View Details | M3602 | PO placed - Closed Drains System | Not Started | Yes | 0,0 | 2014-08-19T16:00:00 | 2014-08-19T16:00:00 |
View Details | M3604 | Ready for Shipment - Closed Drains System | Not Started | Yes | 0,0 | 2014-11-19T16:00:00 | 2014-11-19T16:00:00 |
View Details | M3603 | Delievery Time - Closed Drains System | Not Started | Yes | 0,0 | 2014-08-20T08:00:00 | 2014-11-19T16:00:00 |
View Details | M3605 | Shipment - Closed Drains System | Not Started | Yes | 0,0 | 2014-11-20T08:00:00 | 2014-12-22T16:00:00 |
View Details | M3606 | At site - Closed Drains System | Not Started | No | 0,0 | 2014-12-22T16:00:00 | 2014-12-22T16:00:00 |
View Details | M3901 | Purchasing - Fire Water System | Not Started | Yes | 0,0 | 2014-07-20T08:00:00 | 2014-08-19T16:00:00 |
View Details | M3902 | PO placed - Fire Water System | Not Started | Yes | 0,0 | 2014-08-19T16:00:00 | 2014-08-19T16:00:00 |
View Details | M3904 | Ready for Shipment - Fire Water System | Not Started | Yes | 0,0 | 2014-11-18T16:00:00 | 2014-11-18T16:00:00 |
View Details | M3903 | Delievery Time - Fire Water System | Not Started | Yes | 0,0 | 2014-08-20T08:00:00 | 2014-11-18T16:00:00 |
View Details | M3905 | Shipment - Fire Water System | Not Started | Yes | 0,0 | 2014-11-19T08:00:00 | 2014-12-20T16:00:00 |
View Details | M3906 | At site - Fire Water System | Not Started | No | 0,0 | 2014-12-20T16:00:00 | 2014-12-20T16:00:00 |
View Details | M3801 | Purchasing - Sewage Treatment System | Not Started | Yes | 0,0 | 2014-07-20T08:00:00 | 2014-08-19T16:00:00 |
View Details | M3802 | PO placed - Sewage Treatment System | Not Started | Yes | 0,0 | 2014-08-19T16:00:00 | 2014-08-19T16:00:00 |
View Details | M3804 | Ready for Shipment - Sewage Treatment System | Not Started | Yes | 0,0 | 2014-12-02T16:00:00 | 2014-12-02T16:00:00 |
View Details | M3803 | Delievery Time - Sewage Treatment System | Not Started | Yes | 0,0 | 2014-08-20T08:00:00 | 2014-12-02T16:00:00 |
View Details | M3805 | Shipment - Sewage Treatment System | Not Started | Yes | 0,0 | 2014-12-03T08:00:00 | 2015-01-03T16:00:00 |
View Details | M3806 | At site - Sewage Treatment System | Not Started | No | 0,0 | 2015-01-03T16:00:00 | 2015-01-03T16:00:00 |
View Details | F5460 | Purchasing - Vessels off-package | Not Started | Yes | 0,0 | 2014-05-04T08:00:00 | 2014-07-19T16:00:00 |
View Details | F5470 | PO placed - Vessels off-package | Not Started | Yes | 0,0 | 2014-07-19T16:00:00 | 2014-07-19T16:00:00 |
View Details | F5490 | Ready for Shipment - Vessels off-package | Not Started | Yes | 0,0 | 2015-05-23T16:00:00 | 2015-05-23T16:00:00 |
View Details | F5480 | Delievery Time - Vessels off-package | Not Started | Yes | 0,0 | 2014-07-20T08:00:00 | 2015-05-23T16:00:00 |
View Details | M5500 | Shipment - Vessels off-package | Not Started | Yes | 0,0 | 2015-05-31T08:00:00 | 2015-07-29T16:00:00 |
View Details | M5510 | At site - Vessels off-package | Not Started | No | 0,0 | 2015-07-29T16:00:00 | 2015-07-29T16:00:00 |
View Details | F5495 | Transport to Port of Export - Vessels off-package | Not Started | Yes | 0,0 | 2015-05-24T08:00:00 | 2015-05-30T16:00:00 |
View Details | J5230 | Purchasing - Emergency Power Generator | Not Started | Yes | 0,0 | 2014-05-30T08:00:00 | 2014-06-28T16:00:00 |
View Details | J5240 | PO placed - Emergency Power Generator | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2014-06-29T08:00:00 |
View Details | J5250 | Delivery Time (incl. Detail Engineering) - Emergency Power Generator | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2014-12-25T16:00:00 |
View Details | J5260 | FAT - Emergency Power Generator | Not Started | No | 0,0 | 2014-12-12T08:00:00 | 2014-12-18T16:00:00 |
View Details | J5270 | Ready for Shipment - Emergency Power Generator | Not Started | Yes | 0,0 | 2014-12-26T08:00:00 | 2014-12-26T08:00:00 |
View Details | M5285 | Shipment (Placeholder / MIG Scope) - Emergency Power Generator | Not Started | Yes | 0,0 | 2015-01-02T08:00:00 | 2015-02-15T16:00:00 |
View Details | M5295 | At site - Emergency Power Generator | Not Started | Yes | 0,0 | 2015-02-15T16:00:00 | 2015-02-15T16:00:00 |
View Details | J5275 | Transport to Port of Export - Emergency Power Generator | Not Started | Yes | 0,0 | 2014-12-26T08:00:00 | 2015-01-01T16:00:00 |
View Details | J3130 | Purchasing - Gas Turbine System | Not Started | Yes | 0,0 | 2014-05-30T08:00:00 | 2014-07-28T16:00:00 |
View Details | J3140 | PO placed - Gas Turbine System | Not Started | Yes | 0,0 | 2014-07-29T08:00:00 | 2014-07-29T08:00:00 |
View Details | J3150 | Delivery Time (incl. Detail Engineering) - Gas Turbine System | Not Started | Yes | 0,0 | 2014-07-29T08:00:00 | 2015-07-28T16:00:00 |
View Details | J3160 | FAT - Gas Turbine System | Not Started | No | 0,0 | 2015-07-15T08:00:00 | 2015-07-21T16:00:00 |
View Details | J3170 | Ready for Shipment - Gas Turbine System | Not Started | Yes | 0,0 | 2015-07-29T08:00:00 | 2015-07-29T08:00:00 |
View Details | M3180 | Shipment (Placeholder / MIG Scope) - Gas Turbine System | Not Started | Yes | 0,0 | 2015-08-05T08:00:00 | 2015-09-18T16:00:00 |
View Details | M3190 | At site - Gas Turbine System | Not Started | Yes | 0,0 | 2015-09-18T16:00:00 | 2015-09-18T16:00:00 |
View Details | J3175 | Transport to Port of Export - Gas Turbine System | Not Started | Yes | 0,0 | 2015-07-29T08:00:00 | 2015-08-04T16:00:00 |
View Details | F2320 | Purchasing - Gas Sweetening (Amine) System | Not Started | Yes | 0,0 | 2014-04-26T08:00:00 | 2014-06-06T16:00:00 |
View Details | F2330 | PO placed - Gas Sweetening (Amine) System | Not Started | Yes | 0,0 | 2014-06-06T16:00:00 | 2014-06-06T16:00:00 |
View Details | F2350 | Ready for Shipment - Gas Sweetening (Amine) System | Not Started | Yes | 0,0 | 2015-04-24T16:00:00 | 2015-04-24T16:00:00 |
View Details | F2340 | Delievery Time - Gas Sweetening (Amine) System | Not Started | Yes | 0,0 | 2014-06-07T08:00:00 | 2015-04-24T16:00:00 |
View Details | M2360 | Shipment - Gas Sweetening (Amine) System | Not Started | Yes | 0,0 | 2015-05-02T08:00:00 | 2015-06-15T16:00:00 |
View Details | M2370 | At site - Gas Sweetening (Amine) System | Not Started | Yes | 0,0 | 2015-06-15T16:00:00 | 2015-06-15T16:00:00 |
View Details | F2355 | Transport to Port of Export - Gas Sweetening (Amine) System | Not Started | Yes | 0,0 | 2015-04-25T08:00:00 | 2015-05-01T16:00:00 |
View Details | F2080 | Purchasing - Gas Conditioning (Dew Pointing) System | Not Started | Yes | 0,0 | 2014-04-19T08:00:00 | 2014-05-30T16:00:00 |
View Details | F2090 | PO placed - Gas Conditioning (Dew Pointing) System | Not Started | Yes | 0,0 | 2014-05-30T16:00:00 | 2014-05-30T16:00:00 |
View Details | F2110 | Ready for Shipment - Gas Conditioning (Dew Pointing) System | Not Started | Yes | 0,0 | 2015-05-30T16:00:00 | 2015-05-30T16:00:00 |
View Details | F2100 | Delievery Time - Gas Conditioning (Dew Pointing) System | Not Started | Yes | 0,0 | 2014-05-31T08:00:00 | 2015-05-30T16:00:00 |
View Details | M2120 | Shipment - Gas Conditioning (Dew Pointing) System | Not Started | Yes | 0,0 | 2015-06-07T08:00:00 | 2015-07-21T16:00:00 |
View Details | M2130 | At site - Gas Conditioning (Dew Pointing) System | Not Started | Yes | 0,0 | 2015-07-21T16:00:00 | 2015-07-21T16:00:00 |
View Details | F2115 | Transport to Port of Export - Gas Conditioning (Dew Pointing) System | Not Started | Yes | 0,0 | 2015-05-31T08:00:00 | 2015-06-06T16:00:00 |
View Details | M3701 | Purchasing - Diesel Oil System | Not Started | Yes | 0,0 | 2014-05-24T08:00:00 | 2014-06-23T16:00:00 |
View Details | M3702 | PO placed - Diesel Oil System | Not Started | Yes | 0,0 | 2014-06-23T16:00:00 | 2014-06-23T16:00:00 |
View Details | M3704 | Ready for Shipment - Diesel Oil System | Not Started | Yes | 0,0 | 2014-08-14T16:00:00 | 2014-08-14T16:00:00 |
View Details | M3703 | Delievery Time - Diesel Oil System | Not Started | Yes | 0,0 | 2014-06-24T08:00:00 | 2014-08-14T16:00:00 |
View Details | M3705 | Shipment - Diesel Oil System | Not Started | No | 0,0 | 2014-08-16T08:00:00 | 2014-09-15T16:00:00 |
View Details | M3706 | At site - Diesel Oil System | Not Started | No | 0,0 | 2014-09-30T08:00:00 | 2014-09-30T08:00:00 |
View Details | F5400 | Purchasing - Equipment off-package | Not Started | Yes | 0,0 | 2014-05-04T08:00:00 | 2014-07-19T16:00:00 |
View Details | F5410 | PO placed - Equipment off-package | Not Started | Yes | 0,0 | 2014-07-19T16:00:00 | 2014-07-19T16:00:00 |
View Details | F5430 | Ready for Shipment - Equipment off-package | Not Started | Yes | 0,0 | 2015-05-23T16:00:00 | 2015-05-23T16:00:00 |
View Details | F5420 | Delievery Time - Equipment off-package | Not Started | Yes | 0,0 | 2014-07-20T08:00:00 | 2015-05-23T16:00:00 |
View Details | M5440 | Shipment - Equipment off-package | Not Started | Yes | 0,0 | 2015-05-31T08:00:00 | 2015-07-29T16:00:00 |
View Details | M5450 | At site - Equipment off-package | Not Started | No | 0,0 | 2015-07-29T16:00:00 | 2015-07-29T16:00:00 |
View Details | F5435 | Transport to Port of Export - Equipment off-package | Not Started | Yes | 0,0 | 2015-05-24T08:00:00 | 2015-05-30T16:00:00 |
View Details | F1960 | Purchasing - Gas Conditioning (Dehydration) System | Not Started | Yes | 0,0 | 2014-04-19T08:00:00 | 2014-05-30T16:00:00 |
View Details | F1970 | PO placed - Gas Conditioning (Dehydration) System | Not Started | Yes | 0,0 | 2014-05-30T16:00:00 | 2014-05-30T16:00:00 |
View Details | F1990 | Ready for Shipment - Gas Conditioning (Dehydration) System | Not Started | Yes | 0,0 | 2015-05-30T16:00:00 | 2015-05-30T16:00:00 |
View Details | F1980 | Delievery Time - Gas Conditioning (Dehydration) System | Not Started | Yes | 0,0 | 2014-05-31T08:00:00 | 2015-05-30T16:00:00 |
View Details | M2000 | Shipment - Gas Conditioning (Dehydration) System | Not Started | Yes | 0,0 | 2015-06-07T08:00:00 | 2015-07-21T16:00:00 |
View Details | M2010 | At site - Gas Conditioning (Dehydration) System | Not Started | Yes | 0,0 | 2015-07-21T16:00:00 | 2015-07-21T16:00:00 |
View Details | F1995 | Transport to Port of Export - Gas Conditioning (Dehydration) System | Not Started | Yes | 0,0 | 2015-05-31T08:00:00 | 2015-06-06T16:00:00 |
View Details | J3720 | Purchasing - Well Flowlines | Not Started | Yes | 0,0 | 2014-06-09T08:00:00 | 2014-08-07T16:00:00 |
View Details | J3730 | PO placed - Well Flowlines | Not Started | Yes | 0,0 | 2014-08-08T08:00:00 | 2014-08-08T08:00:00 |
View Details | J3740 | Delivery Time - Well Flowlines | Not Started | Yes | 0,0 | 2014-08-08T08:00:00 | 2015-02-03T16:00:00 |
View Details | J3760 | Ready for Shipment - (100%) Well Flowlines | Not Started | Yes | 0,0 | 2015-02-04T08:00:00 | 2015-02-04T08:00:00 |
View Details | M3105 | Shipment - (100%) Well Flowlines | Not Started | Yes | 0,0 | 2015-02-11T08:00:00 | 2015-04-04T16:00:00 |
View Details | M3106 | At site - (100%) Well Flowlines | Not Started | Yes | 0,0 | 2015-04-04T16:00:00 | 2015-04-04T16:00:00 |
View Details | J3765 | Transport to Port of Export - (100%) Well Flowlines | Not Started | Yes | 0,0 | 2015-02-04T08:00:00 | 2015-02-10T16:00:00 |
View Details | J5425 | Ready for Shipment - (30%) Well Flowlines | Not Started | Yes | 0,0 | 2014-10-07T08:00:00 | 2014-10-07T08:00:00 |
View Details | M5445 | Shipment - (30%) Well Flowlines | Not Started | Yes | 0,0 | 2014-10-14T08:00:00 | 2014-12-04T16:00:00 |
View Details | M5455 | At site - (30%) Well Flowlines | Not Started | Yes | 0,0 | 2014-12-04T16:00:00 | 2014-12-04T16:00:00 |
View Details | J5435 | Transport to Port of Export - (30%) Well Flowlines | Not Started | Yes | 0,0 | 2014-10-07T08:00:00 | 2014-10-13T16:00:00 |
View Details | J5445 | Ready for Shipment - (60%) Well Flowlines | Not Started | Yes | 0,0 | 2014-12-06T08:00:00 | 2014-12-06T08:00:00 |
View Details | M5465 | Shipment - (60%) Well Flowlines | Not Started | Yes | 0,0 | 2014-12-13T08:00:00 | 2015-02-02T16:00:00 |
View Details | M5475 | At site - (60%) Well Flowlines | Not Started | Yes | 0,0 | 2015-02-02T16:00:00 | 2015-02-02T16:00:00 |
View Details | J5455 | Transport to Port of Export - (60%) Well Flowlines | Not Started | Yes | 0,0 | 2014-12-06T08:00:00 | 2014-12-12T16:00:00 |
View Details | J3780 | Purchasing - Methanol lines | Not Started | Yes | 0,0 | 2014-06-09T08:00:00 | 2014-08-07T16:00:00 |
View Details | J3790 | PO placed - Methanol lines | Not Started | Yes | 0,0 | 2014-08-08T08:00:00 | 2014-08-08T08:00:00 |
View Details | J3800 | Delivery Time - Methanol lines | Not Started | Yes | 0,0 | 2014-08-08T08:00:00 | 2015-02-03T16:00:00 |
View Details | J3820 | Ready for Shipment - (100%) Methanol lines | Not Started | Yes | 0,0 | 2015-02-04T08:00:00 | 2015-02-04T08:00:00 |
View Details | M5660 | Shipment - (100%) Methanol lines | Not Started | Yes | 0,0 | 2015-02-11T08:00:00 | 2015-04-04T16:00:00 |
View Details | M5670 | At site - (100%) Methanol lines | Not Started | Yes | 0,0 | 2015-04-04T16:00:00 | 2015-04-04T16:00:00 |
View Details | J3825 | Transport to Port of Export - (100%) Methanol lines | Not Started | Yes | 0,0 | 2015-02-04T08:00:00 | 2015-02-10T16:00:00 |
View Details | J5465 | Ready for Shipment - (30%) Methanol lines | Not Started | Yes | 0,0 | 2014-10-07T08:00:00 | 2014-10-07T08:00:00 |
View Details | M5485 | Shipment - (30%) Methanol lines | Not Started | Yes | 0,0 | 2014-10-14T08:00:00 | 2014-12-04T16:00:00 |
View Details | M5495 | At site - (30%) Methanol lines | Not Started | No | 0,0 | 2014-12-04T16:00:00 | 2014-12-04T16:00:00 |
View Details | J5475 | Transport to Port of Export - (30%) Methanol lines | Not Started | Yes | 0,0 | 2014-10-07T08:00:00 | 2014-10-13T16:00:00 |
View Details | J5485 | Ready for Shipment - (60%) Methanol lines | Not Started | Yes | 0,0 | 2014-12-06T08:00:00 | 2014-12-06T08:00:00 |
View Details | M5505 | Shipment - (60%) Methanol lines | Not Started | Yes | 0,0 | 2014-12-13T08:00:00 | 2015-02-02T16:00:00 |
View Details | M5515 | At site - (60%) Methanol lines | Not Started | Yes | 0,0 | 2015-02-02T16:00:00 | 2015-02-02T16:00:00 |
View Details | J5495 | Transport to Port of Export - (60%) Methanol lines | Not Started | Yes | 0,0 | 2014-12-06T08:00:00 | 2014-12-12T16:00:00 |
View Details | F4890 | Purchasing - Well Flowlines System | Not Started | Yes | 0,0 | 2014-05-03T08:00:00 | 2014-06-13T16:00:00 |
View Details | F4900 | PO placed - Well Flowlines System | Not Started | Yes | 0,0 | 2014-06-13T16:00:00 | 2014-06-13T16:00:00 |
View Details | F4920 | Ready for Shipment - Well Flowlines System | Not Started | Yes | 0,0 | 2015-04-03T16:00:00 | 2015-04-03T16:00:00 |
View Details | F4910 | Delievery Time - Well Flowlines System | Not Started | Yes | 0,0 | 2014-06-14T08:00:00 | 2015-04-03T16:00:00 |
View Details | M4930 | Shipment - Well Flowlines System | Not Started | Yes | 0,0 | 2015-04-11T08:00:00 | 2015-05-25T16:00:00 |
View Details | M4940 | At site - Well Flowlines System | Not Started | No | 0,0 | 2015-05-25T16:00:00 | 2015-05-25T16:00:00 |
View Details | F4925 | Transport to Port of Export - Well Flowlines System | Not Started | Yes | 0,0 | 2015-04-04T08:00:00 | 2015-04-10T16:00:00 |
View Details | M310101 | Purchasing - Structural Steel & Steel Plate | Not Started | Yes | 0,0 | 2014-06-01T08:00:00 | 2014-06-30T16:00:00 |
View Details | M310102 | PO placed - Structural Steel & Steel Plate | Not Started | Yes | 0,0 | 2014-07-01T08:00:00 | 2014-07-01T08:00:00 |
View Details | M310103 | Delivery Time ( 60%) - Structural Steel & Steel Plate | Not Started | Yes | 0,0 | 2014-07-01T08:00:00 | 2014-08-31T16:00:00 |
View Details | M310104 | Delivery Time ( 35%) - Structural Steel & Steel Plate | Not Started | Yes | 0,0 | 2014-09-01T08:00:00 | 2014-10-02T16:00:00 |
View Details | M310105 | Delivery Time ( 5%) - Structural Steel & Steel Plate | Not Started | No | 0,0 | 2014-10-04T08:00:00 | 2014-10-14T16:00:00 |
View Details | M312001 | Pressure Vessels | Not Started | No | 0,0 | 2014-09-01T08:00:00 | 2014-11-20T16:00:00 |
View Details | M312002 | Tanks | Not Started | No | 0,0 | 2014-09-01T08:00:00 | 2014-10-16T16:00:00 |
View Details | M312003 | Piping | Not Started | No | 0,0 | 2014-09-01T08:00:00 | 2014-12-25T16:00:00 |
View Details | F0790 | Commissioning - System 270 | Not Started | Yes | 0,0 | 2015-10-19T08:00:00 | 2015-11-01T16:00:00 |
View Details | F0820 | Commissioning - System 330 | Not Started | Yes | 0,0 | 2015-10-25T08:00:00 | 2015-11-07T16:00:00 |
View Details | F0860 | Commissioning - System 420 | Not Started | Yes | 0,0 | 2015-09-19T08:00:00 | 2015-10-15T16:00:00 |
View Details | F0920 | Commissioning - System 470 | Not Started | Yes | 0,0 | 2015-09-19T08:00:00 | 2015-10-15T16:00:00 |
View Details | F0940 | Commissioning - System 500 | Not Started | Yes | 0,0 | 2015-09-19T08:00:00 | 2015-10-15T16:00:00 |
View Details | F0950 | Commissioning - System 530 | Not Started | Yes | 0,0 | 2015-09-19T08:00:00 | 2015-10-15T16:00:00 |
View Details | F0960 | Commissioning - System 560 | Not Started | Yes | 0,0 | 2015-09-19T08:00:00 | 2015-10-15T16:00:00 |
View Details | F0970 | Commissioning - System 570 | Not Started | Yes | 0,0 | 2015-09-19T08:00:00 | 2015-10-15T16:00:00 |
View Details | F0980 | Commissioning - System 620 | Not Started | Yes | 0,0 | 2015-09-19T08:00:00 | 2015-10-15T16:00:00 |
View Details | F0990 | Commissioning - System 630 | Not Started | Yes | 0,0 | 2015-10-17T08:00:00 | 2015-10-29T16:00:00 |
View Details | F1000 | Commissioning - System 640 | Not Started | Yes | 0,0 | 2015-10-17T08:00:00 | 2015-10-29T16:00:00 |
View Details | F1010 | Commissioning - System 660 | Not Started | Yes | 0,0 | 2015-09-19T08:00:00 | 2015-10-15T16:00:00 |
View Details | F1020 | Commissioning - System 710 | Not Started | Yes | 0,0 | 2015-09-19T08:00:00 | 2015-10-15T16:00:00 |
View Details | F1040 | Commissioning - System 830 | Not Started | Yes | 0,0 | 2015-09-19T08:00:00 | 2015-10-15T16:00:00 |
View Details | F0815 | Commissioning - System 410 | Not Started | Yes | 0,0 | 2015-09-19T08:00:00 | 2015-10-15T16:00:00 |
View Details | F0720 | Commissioning - System 200 | Not Started | Yes | 0,0 | 2015-11-01T08:00:00 | 2015-11-28T16:00:00 |
View Details | F0730 | Commissioning - System 210 | Not Started | Yes | 0,0 | 2015-11-01T08:00:00 | 2015-11-28T16:00:00 |
View Details | F0740 | Commissioning - System 220 | Not Started | Yes | 0,0 | 2015-11-01T08:00:00 | 2015-11-28T16:00:00 |
View Details | F0750 | Commissioning - System 232 | Not Started | Yes | 0,0 | 2015-11-01T08:00:00 | 2015-11-28T16:00:00 |
View Details | F0760 | Commissioning - System 240 | Not Started | Yes | 0,0 | 2015-11-01T08:00:00 | 2015-12-12T16:00:00 |
View Details | F0770 | Commissioning - System 250A | Not Started | Yes | 0,0 | 2015-11-04T08:00:00 | 2015-12-15T16:00:00 |
View Details | F0800 | Commissioning - System 280 | Not Started | Yes | 0,0 | 2015-11-03T08:00:00 | 2015-12-14T16:00:00 |
View Details | F0830 | Commissioning - System 400 | Not Started | Yes | 0,0 | 2015-12-16T08:00:00 | 2015-12-29T16:00:00 |
View Details | F0780 | Commissioning - System 250B | Not Started | Yes | 0,0 | 2015-12-16T08:00:00 | 2015-12-29T16:00:00 |
View Details | F0930 | Commissioning - System 480 | Not Started | Yes | 0,0 | 2015-12-16T08:00:00 | 2015-12-22T16:00:00 |
View Details | F0840 | Commissioning - System 410 | Not Started | Yes | 0,0 | 2015-12-16T08:00:00 | 2016-01-05T16:00:00 |
View Details | F0870 | Commissioning - System 430 | Not Started | Yes | 0,0 | 2015-12-16T08:00:00 | 2016-01-05T16:00:00 |
View Details | F0880 | Commissioning - System 440 | Not Started | Yes | 0,0 | 2015-12-16T08:00:00 | 2016-01-05T16:00:00 |
View Details | F0910 | Commissioning - System 460 | Not Started | Yes | 0,0 | 2015-12-16T08:00:00 | 2016-01-05T16:00:00 |
View Details | F6090 | First Fire | Not Started | Yes | 0,0 | 2016-01-20T08:00:00 | 2016-01-20T08:00:00 |
View Details | F6100 | First Synchronization | Not Started | No | 0,0 | 2016-01-27T08:00:00 | 2016-01-27T08:00:00 |
View Details | F6110 | Energizing | Not Started | Yes | 0,0 | 2015-11-04T08:00:00 | 2016-01-05T16:00:00 |
View Details | F0890 | Commissioning - System 450 | Not Started | Yes | 0,0 | 2015-12-16T08:00:00 | 2016-01-05T16:00:00 |
View Details | F1030 | Commissioning - System 800 | Not Started | Yes | 0,0 | 2016-01-06T08:00:00 | 2016-03-01T16:00:00 |
View Details | F0710 | Commissioning - System 110 (1-3) | Not Started | No | 0,0 | 2015-09-19T08:00:00 | 2015-09-29T16:00:00 |
View Details | F0714 | Commissioning - System 110 (4-6) | Not Started | No | 0,0 | 2015-10-04T08:00:00 | 2015-10-14T16:00:00 |
View Details | F0718 | Commissioning - System 110 (7-9) | Not Started | Yes | 0,0 | 2015-11-01T08:00:00 | 2015-11-11T16:00:00 |
View Details | F5660 | Start Commissioning | Not Started | Yes | 0,0 | 2015-09-19T08:00:00 | 2015-09-19T08:00:00 |
View Details | J1390 | Commissioning - Frequency Inverter | Not Started | Yes | 0,0 | 2015-10-19T08:00:00 | 2015-11-03T16:00:00 |
View Details | F5640 | Prepartion of Performance Test | Not Started | Yes | 0,0 | 2016-03-02T08:00:00 | 2016-03-03T16:00:00 |
View Details | F5645 | Overall Performance Test (Minimum Capacity) | Not Started | Yes | 0,0 | 2016-03-04T08:00:00 | 2016-03-05T16:00:00 |
View Details | F5650 | Overall Performance Test (Full Capacity) | Not Started | Yes | 0,0 | 2016-03-06T08:00:00 | 2016-03-08T16:00:00 |
Project ID | : | 1260014 | |||
Project Flag | : | Y | Project Web Site URL | : | None |
Default Cost Account | : | Rate Type | : | COST_PER_QTY | |
Link Percent Complete With Actual | : | Y | Drive Activity Dates Default | : | Y |
Link actual to date and actual this period units and costs | : | Y | Default Activity Type | : | TT_Task |
Add Actual To Remain | : | N | Project Forecast Start | : | None |
Added By | : | admin | Financial Period Calendar ID | : | None |
Date Added | : | 2013-11-25 14:41 | Fiscal Year Begins | : | 1 |
Can resources mark activities completed | : | Y | Global Unique ID | : | /LxNHTJISdyNEPK19oTeCg |
Allow Negative Actual Units | : | N | History Interval | : | |
Last Apply Actuals Date | : | None | History Level | : | |
Baseline Type | : | None | Integrated Project | : | |
Enable Summarization | : | Y | Last Update Date | : | None |
Date Checked Out | : | Last Checksum | : | None | |
Project Check-out Status | : | N | Financial Period | : | None |
Checked Out By | : | Last Leveled Date | : | ||
Resources Edit Percent Complete | : | Last Recalc Date | : | 2014-02-01 00:00 | |
Default Calendar | : | 1183 | Last Scheduled Date | : | |
Status Update Control | : | Last Summarized Date | : | None | |
Cost Qty Recalc Flag | : | N | Project Location | : | None |
Content Repository External UUID | : | None | MS Project Managed Flag | : | |
Critical activities have float less than or equal to | : | 24 | Code Separator | : | . |
critical_path_type | : | CT_DrivPath | Original Project | : | None |
Default Percent Complete Type | : | CP_Drtn | Must Finish By | : | 2016-01-01 16:00 |
Default Price / Unit | : | None | Planned Start | : | 2014-02-01 00:00 |
Default Duration Type | : | DT_FixedDUR2 | Project Leveling Priority | : | 10 |
Default Price Time Units | : | QT_Hour | Unique ID | : | 22726 |
Change Chart Timescale
Code | Name | Status | Critical | Percent Complete | Start | Finish |
---|---|---|---|---|---|---|
307477 | Nawara - CPF, Wellpads, Flowlines - Rev. 0 (25.11.2013) | |||||
307478 | PROJECT MILESTONES AND GENERAL ITEMS | |||||
C1050 | Effective Contract Date (ECD) | Not Started | Yes | 0,0 | 2014-03-01T08:00:00 | 2014-03-01T08:00:00 |
C2500 | Engineering complete | Not Started | No | 0,0 | 2015-02-23T16:00:00 | 2015-02-23T16:00:00 |
C4500 | Pre-Commissioning completed | Not Started | No | 0,0 | 2016-01-03T16:00:00 | 2016-01-03T16:00:00 |
C7550 | Completion Date (CD) - Hand Over Certificate issued | Not Started | Yes | 0,0 | 2016-03-08T16:00:00 | 2016-03-08T16:00:00 |
C6000 | All Final Documentation issued | Not Started | No | 0,0 | 2016-03-01T16:00:00 | 2016-03-01T16:00:00 |
C3500 | Mechanical Completion | Not Started | Yes | 0,0 | 2015-12-06T16:00:00 | 2015-12-06T16:00:00 |
C2000 | Start Engineering | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-01T08:00:00 |
C3000 | Construction Work Commence | Not Started | No | 0,0 | 2014-05-01T08:00:00 | 2014-05-01T08:00:00 |
C7500 | PAC achieved | Not Started | Yes | 0,0 | 2016-03-08T16:00:00 | 2016-03-08T16:00:00 |
C5500 | Commissioning completed | Not Started | Yes | 0,0 | 2016-03-01T16:00:00 | 2016-03-01T16:00:00 |
C7050 | Performance Test completed | Not Started | Yes | 0,0 | 2016-03-08T16:00:00 | 2016-03-08T16:00:00 |
C1000 | Contract Award | Not Started | Yes | 0,0 | 2014-02-01T08:00:00 | 2014-02-01T08:00:00 |
307479 | ENGINEERING | |||||
307480 | EXHIBIT C - KEY DATES | |||||
F3220 | Project Execution Plan (Exhibit A, 4.2) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-30T16:00:00 |
F3230 | Procurement Plan (Exhibit A, 6.3.2) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-30T16:00:00 |
F3240 | Subcontracting Plan (Exhibit A, 4) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-30T16:00:00 |
F3250 | Quality Management Plan (Exhibit A, 6.14.1) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-30T16:00:00 |
F3260 | Alignment Workshops Schedule (Exhibit A, 4.11) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-30T16:00:00 |
F3270 | Organization Chart (Exhibit P, 1.3.2) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-30T16:00:00 |
F3280 | Job Roles and Responsibilities (Exhibit A, 4.2) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-30T16:00:00 |
F3290 | Integrity Management (Exhibit A, 8.8) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-30T16:00:00 |
F3300 | Reporting Plan (Exhibit P, 1.6.2) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-30T16:00:00 |
F3310 | Weekly Progress Report (Exhibit P, 1.6.4) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-30T16:00:00 |
F3320 | Monthly Progress Report (Exhibit P, 1.6.4) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-04-29T16:00:00 |
F3330 | Kick-Off Meeting Engineering and Procurement (Exhibit P, 1.6.4) | Not Started | No | 0,0 | 2014-03-15T08:00:00 | 2014-03-15T08:00:00 |
F3340 | Kick-Off Meeting HSSE (Exhibit P, 1.6.4) | Not Started | No | 0,0 | 2014-03-22T08:00:00 | 2014-03-22T08:00:00 |
M9040 | Kick-Off Meeting Construction (Exhibit P, 1.6.4) | Not Started | No | 0,0 | 2014-06-02T08:00:00 | 2014-06-02T08:00:00 |
F3360 | Construction Weekly Progress Meeting (Exhibit P, 1.6.4) | Not Started | No | 0,0 | 2014-06-19T08:00:00 | 2014-06-19T08:00:00 |
F3370 | Close Out Report (Exhibit P, 1.6.4) | Not Started | No | 0,0 | 2015-12-07T08:00:00 | 2016-02-14T16:00:00 |
F3400 | Work Breakdown Structures (Exhibit P, 2.3.2) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-30T16:00:00 |
F3410 | Schedule development and Control Plan (Exhibit P, 2.3.2) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-30T16:00:00 |
F3420 | 90 Days Look Ahead (Exhibit P, 2.3.2) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-30T16:00:00 |
F3430 | Basis of the Schedule (Exhibit P, 2.3.5) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-30T16:00:00 |
F3460 | Overall Project Execution Schedule (Exhibit P, 2.3.5) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-05-29T16:00:00 |
F3470 | Progress Measurement Plan for Engineering and Procurement Activities (Exhibit P, 2.3.6) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-04-14T16:00:00 |
F3480 | Progress Measurement Plan for Construction, Pre-Commissioning and Commissioning (Exhibit P, 2.3.7) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-06-28T16:00:00 |
F3490 | Cost Control and Accounting Plan (Exhibit P, 2.4.2) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-30T16:00:00 |
F3500 | Baseline for Cost Control and Reporting (Exhibit P, 2.4.5) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-30T16:00:00 |
F3510 | Mobilisation Plan | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-30T16:00:00 |
F3520 | Invoicing and Payment Procedure (Exhibit P, 2.4.7) | Not Started | No | 0,0 | 2014-02-01T08:00:00 | 2014-02-14T16:00:00 |
F3530 | Variation Change Control Plan (Exhibit P, 2.4.4) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-30T16:00:00 |
F3540 | Risk Management System (Plan, Procedure, Schedule, Matrix and Register) (Exhibit P, 2.5.2) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-30T16:00:00 |
F3550 | Mech. Completion, Pre-Comm., Comm., Start Up, Handover and Provisional Acceptance Plan (Exhibit K, 3.1) | Not Started | Yes | 0,0 | 2014-11-22T08:00:00 | 2014-12-19T16:00:00 |
F3560 | Performance Test Procedure (Exhibit D, 3.1) | Not Started | Yes | 0,0 | 2015-11-05T08:00:00 | 2015-12-02T16:00:00 |
F3570 | Information Management Plan (incl. Corresp. Plan and Procedures, Doc Distrib. Matrix, Master Doc Reg.) (Ex. P, 2.6.3) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-30T16:00:00 |
F3580 | Knowledge Management (KM) Plan (Exhibit P, 2.7.2) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-30T16:00:00 |
F3590 | Management of Change Procedure (Exhibit P, 2.8.1) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-05-29T16:00:00 |
F3600 | Equipment Testing and Matertial Inspection Program | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-04-09T16:00:00 |
F3610 | FEED Design Endorsement Certificate (Exhibit A, 5.4) | Not Started | Yes | 0,0 | 2014-03-30T16:00:00 | 2014-03-30T16:00:00 |
F3620 | Technical Documents Register (Exhibit A, 12.1) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-04-14T16:00:00 |
F3630 | Constructability Plan (Exhibit A, 5.13) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-30T16:00:00 |
F3640 | Interface Management Plan (Exhibit P, 2.10) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-30T16:00:00 |
F3650 | Interface Management Procedure (Exhibit P, 2.10) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-04-14T16:00:00 |
F3660 | Interface Data Submission Schedule (Exhibit P, 2.10.1) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-04-29T16:00:00 |
F3670 | Interface Data Requirements Schedule (Exhibit P, 2.10.1) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-04-29T16:00:00 |
F3680 | Interface Register (Exhibit P, 2.10.1) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-05-29T16:00:00 |
F3690 | Interface Definition Report (Exhibit P, 2.10.1) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-06-28T16:00:00 |
F3700 | HSSE Bridging Document (Exhibit J, 4.2) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-20T16:00:00 |
F3710 | Final Security Plan (Exhibit J, 4.9) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-06-28T16:00:00 |
F3720 | Final Community Relation Plan (Exhibit J, 4.14) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-06-28T16:00:00 |
F3730 | Final Environemental Management and Monitoring Plan (Exhibit J, Att. 3) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-06-28T16:00:00 |
F3740 | Final Emergency Response Plan (Exhibit J, 4.13) | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-06-28T16:00:00 |
307481 | ENGINEERING BY DISCIPLINES | |||||
307482 | Fire and Safety | |||||
M2801 | Fire & Safety Design | Not Started | Yes | 0,0 | 2014-03-03T08:00:00 | 2014-04-09T16:00:00 |
M2802 | Fire Protection Layout/Dwgs | Not Started | Yes | 0,0 | 2014-03-03T08:00:00 | 2014-03-31T16:00:00 |
M2803 | Fire Escape Route & Safety sign Layouts | Not Started | Yes | 0,0 | 2014-03-03T08:00:00 | 2014-03-31T16:00:00 |
M2804 | Fire Water sys. P&IDs | Not Started | No | 0,0 | 2014-03-12T08:00:00 | 2014-04-09T16:00:00 |
M2806 | F&G Detection Layouts | Not Started | Yes | 0,0 | 2014-04-01T08:00:00 | 2014-04-18T16:00:00 |
M2807 | F&G Control & alarm system | Not Started | Yes | 0,0 | 2014-04-10T08:00:00 | 2014-04-29T16:00:00 |
M2808 | Equipment Data sheets | Not Started | No | 0,0 | 2014-04-30T08:00:00 | 2014-05-19T16:00:00 |
M2805 | Deluge system - Req | Not Started | No | 0,0 | 2014-04-10T08:00:00 | 2014-04-26T16:00:00 |
307483 | CIVIL | |||||
F5060 | Engineering - Civil | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2014-09-26T16:00:00 |
F5061 | First Submittal of first Civil Document acc. to DDS | Not Started | Yes | 0,0 | 2014-04-29T16:00:00 | 2014-04-29T16:00:00 |
F5062 | First Submittal of last Civil Document acc. to DDS | Not Started | No | 0,0 | 2014-06-28T16:00:00 | 2014-06-28T16:00:00 |
F5065 | Approval of Civil Documents by Client and Independent third Party | Not Started | Yes | 0,0 | 2014-04-30T08:00:00 | 2014-07-12T16:00:00 |
307484 | Civil, Structural and Buildings | |||||
M2201 | BID Review for Civil Eng. Design Basis | Not Started | Yes | 0,0 | 2014-03-03T08:00:00 | 2014-05-02T16:00:00 |
M2202 | Civil & Str. Specs Review & update | Not Started | No | 0,0 | 2014-03-10T08:00:00 | 2014-04-07T16:00:00 |
M2203 | Site Investigation & Survey Reports | Not Started | Yes | 0,0 | 2014-04-10T08:00:00 | 2014-06-11T16:00:00 |
M2204 | Plot Plans - Prelim. | Not Started | Yes | 0,0 | 2014-03-03T08:00:00 | 2014-03-31T16:00:00 |
M2207 | Pilling Layout Dwgs | Not Started | No | 0,0 | 2014-06-12T08:00:00 | 2014-07-10T16:00:00 |
M2209 | Bldgs. | Not Started | Yes | 0,0 | 2014-04-01T08:00:00 | 2014-04-18T16:00:00 |
M2210 | Substation Bldgs. | Not Started | No | 0,0 | 2014-04-21T08:00:00 | 2014-05-08T16:00:00 |
M2212 | Equipment Structure Design | Not Started | Yes | 0,0 | 2014-03-03T08:00:00 | 2014-04-18T16:00:00 |
M2213 | Pipe Rack Design | Not Started | Yes | 0,0 | 2014-03-03T08:00:00 | 2014-04-18T16:00:00 |
M2215 | Steel Structure MTO/Req. | Not Started | No | 0,0 | 2014-03-21T08:00:00 | 2014-04-18T16:00:00 |
M2205 | Plot Plans | Not Started | Yes | 0,0 | 2014-04-22T08:00:00 | 2014-05-20T16:00:00 |
M2206 | Roads & Paving Plan | Not Started | No | 0,0 | 2014-05-13T08:00:00 | 2014-06-10T16:00:00 |
M2211 | Shelters | Not Started | No | 0,0 | 2014-05-13T08:00:00 | 2014-05-30T16:00:00 |
M2208 | Equipment Foundation Design | Not Started | No | 0,0 | 2014-06-12T08:00:00 | 2014-08-08T16:00:00 |
M2214 | Steel Structure 1st MTO/Req.(65%) | Not Started | No | 0,0 | 2014-03-03T08:00:00 | 2014-03-20T16:00:00 |
307485 | ROTATING/STATIC EQUIPMENT, HVAC | |||||
F5030 | Engineering - Rotating/Static Equipment, HVAC | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2015-02-23T16:00:00 |
F5031 | First Submittal of first Rotating/Static Equipment, HVAC Document acc. to DDS | Not Started | Yes | 0,0 | 2014-04-29T16:00:00 | 2014-04-29T16:00:00 |
F5032 | First Submittal of last Rotating/Static Equipment, HVAC Document acc. to DDS | Not Started | No | 0,0 | 2014-06-28T16:00:00 | 2014-06-28T16:00:00 |
F5035 | Approval of Rotating/Static Equipment, HVAC Documents by Client and Independent third Party | Not Started | Yes | 0,0 | 2014-04-30T08:00:00 | 2014-07-12T16:00:00 |
J2425 | Engineering - Nitrogen System | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2014-06-28T16:00:00 |
J3125 | Engineering - Gas Turbine System | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2014-07-28T16:00:00 |
J3330 | Engineering - Fuel Gas Supply System | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2014-06-28T16:00:00 |
J3520 | Engineering - Chlorination System | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2014-06-28T16:00:00 |
J4360 | Engineering - Aquifer / Plant Water System | Not Started | No | 0,0 | 2014-03-31T08:00:00 | 2014-06-28T16:00:00 |
J4530 | Engineering - Fresh Water System | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2014-06-28T16:00:00 |
J4640 | Engineering - Demin Water System | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2014-06-28T16:00:00 |
J4930 | Engineering - Instrument & Plant Air System | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2014-06-28T16:00:00 |
J5220 | Engineering - Emergency Power Generator | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2014-06-28T16:00:00 |
307486 | HVAC Engineering | |||||
M2701 | Design Criteria for HVAC Design | Not Started | Yes | 0,0 | 2014-04-01T08:00:00 | 2014-04-29T16:00:00 |
M2702 | Design Load calculations | Not Started | Yes | 0,0 | 2014-04-30T08:00:00 | 2014-05-28T16:00:00 |
M2703 | Optimisation & Selection of system | Not Started | Yes | 0,0 | 2014-04-30T08:00:00 | 2014-05-28T16:00:00 |
M2704 | Equipment Sizing | Not Started | Yes | 0,0 | 2014-04-30T08:00:00 | 2014-05-28T16:00:00 |
M2705 | Specifications & Data sheets | Not Started | Yes | 0,0 | 2014-04-30T08:00:00 | 2014-05-28T16:00:00 |
M2706 | HVAC system drawings | Not Started | Yes | 0,0 | 2014-04-30T08:00:00 | 2014-05-28T16:00:00 |
M2707 | HVAC- MTO/Req. | Not Started | No | 0,0 | 2014-05-29T08:00:00 | 2014-06-17T16:00:00 |
307487 | General | |||||
M1100 | ENGINEERING | Not Started | Yes | 0,0 | 2014-03-01T08:00:00 | 2014-10-02T16:00:00 |
M2101 | Home Office Moilization Eng. Team | Not Started | Yes | 0,0 | 2014-03-03T08:00:00 | 2014-03-20T16:00:00 |
M2103 | Project management Procedure | Not Started | No | 0,0 | 2014-03-10T08:00:00 | 2014-04-07T16:00:00 |
M2110 | Early S/C Award for Geotech Survey | Not Started | Yes | 0,0 | 2014-03-21T08:00:00 | 2014-04-09T16:00:00 |
M2106 | Quality Plan | Not Started | No | 0,0 | 2014-03-10T08:00:00 | 2014-03-27T16:00:00 |
M2107 | HSE Plan | Not Started | No | 0,0 | 2014-03-12T08:00:00 | 2014-03-31T16:00:00 |
M2104 | Project Execution Plan | Not Started | No | 0,0 | 2014-03-10T08:00:00 | 2014-04-07T16:00:00 |
M2109 | Work Schedule Level -3 - 4 - 5 | Not Started | No | 0,0 | 2014-03-12T08:00:00 | 2014-04-09T16:00:00 |
M2102 | Contract Management Manual | Not Started | No | 0,0 | 2014-03-10T08:00:00 | 2014-04-07T16:00:00 |
M2108 | Materials Mgt./Procurement Plan | Not Started | No | 0,0 | 2014-03-12T08:00:00 | 2014-03-31T16:00:00 |
M2105 | Sub-Contracting Procedure | Not Started | No | 0,0 | 2014-03-12T08:00:00 | 2014-03-31T16:00:00 |
M2111 | Early S/C Award for Topographic Survey | Not Started | No | 0,0 | 2014-03-22T08:00:00 | 2014-04-06T16:00:00 |
307488 | STATIC EQUIPMENT | |||||
F5020 | Engineering - Static Equipment | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2014-11-25T16:00:00 |
F5021 | First Submittal of first Static Equipment Document acc. to DDS | Not Started | Yes | 0,0 | 2014-04-29T16:00:00 | 2014-04-29T16:00:00 |
F5022 | First Submittal of last Static Equipment Document acc. to DDS | Not Started | No | 0,0 | 2014-06-28T16:00:00 | 2014-06-28T16:00:00 |
F5025 | Approval of Static Equipment Documents by Client and Independent Third Party | Not Started | Yes | 0,0 | 2014-04-30T08:00:00 | 2014-07-12T16:00:00 |
307489 | Mechanical and Equipment | |||||
M2301 | Equipment Data Sheets | Not Started | Yes | 0,0 | 2014-03-03T08:00:00 | 2014-03-31T16:00:00 |
M2303 | Equipment Erection Procedure | Not Started | No | 0,0 | 2014-04-01T08:00:00 | 2014-04-18T16:00:00 |
M2302 | Vessels/Drums- Req. | Not Started | No | 0,0 | 2014-05-16T08:00:00 | 2014-06-13T16:00:00 |
307490 | Tanks | |||||
M2402 | Vessel & Tanks Plates- Req. | Not Started | No | 0,0 | 2014-04-01T08:00:00 | 2014-04-29T16:00:00 |
M2401 | Tanks & Vessel Engg. Drawings | Not Started | Yes | 0,0 | 2014-03-03T08:00:00 | 2014-03-31T16:00:00 |
M2403 | Other Tanks Plates- Req. | Not Started | No | 0,0 | 2014-03-15T08:00:00 | 2014-03-30T16:00:00 |
M2404 | Other Plates- Req. | Not Started | No | 0,0 | 2014-04-01T08:00:00 | 2014-04-16T16:00:00 |
307491 | STEEL STRUCTURE | |||||
F5070 | Engineering - Steel Structures | Not Started | Yes | 0,0 | 2014-05-30T08:00:00 | 2015-01-24T16:00:00 |
F5071 | First Submittal of first Steel Structure Document acc. to DDS | Not Started | Yes | 0,0 | 2014-06-28T16:00:00 | 2014-06-28T16:00:00 |
F5072 | First Submittal of last Steel Structure Document acc. to DDS | Not Started | No | 0,0 | 2014-08-27T16:00:00 | 2014-08-27T16:00:00 |
F5075 | Approval of Steel Structure Documents by Client and Independent third Party | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2014-09-10T16:00:00 |
307492 | HSE | |||||
F5100 | Engineering - HSE | Not Started | Yes | 0,0 | 2014-08-28T08:00:00 | 2014-12-25T16:00:00 |
F5110 | First Submittal of first HSE Document acc. to DDS | Not Started | Yes | 0,0 | 2014-09-26T16:00:00 | 2014-09-26T16:00:00 |
F5120 | First Submittal of last HSE Document acc. to DDS | Not Started | No | 0,0 | 2014-11-25T16:00:00 | 2014-11-25T16:00:00 |
F5130 | Approval of HSE Documents by Client and Independent Third Party | Not Started | Yes | 0,0 | 2014-09-27T08:00:00 | 2014-12-09T16:00:00 |
307493 | ELECTRICAL | |||||
F5040 | Engineering - Electrical | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2015-02-23T16:00:00 |
F5041 | First Submittal of first Electrical Engineering Document acc. to DDS | Not Started | Yes | 0,0 | 2014-04-29T16:00:00 | 2014-04-29T16:00:00 |
F5042 | First Submittal of last Electrical Engineering Document acc. to DDS | Not Started | No | 0,0 | 2014-06-28T16:00:00 | 2014-06-28T16:00:00 |
F5045 | Approval of Electrical Engineering Documents by Client and Independent third Party | Not Started | Yes | 0,0 | 2014-04-30T08:00:00 | 2014-07-12T16:00:00 |
J0995 | Engineering - MV System 6.6kV | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2014-06-28T16:00:00 |
J1095 | Engineering - LV System 400V | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2014-06-28T16:00:00 |
J1195 | Engineering - LV Trafos | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2014-05-29T16:00:00 |
J1295 | Engineering - Frequency Inverter | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2014-05-29T16:00:00 |
J1395 | Engineering - Battery System 220V DC | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2014-06-28T16:00:00 |
J1495 | Engineering - Small Power System | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2014-07-08T16:00:00 |
J1585 | Engineering - UPS 230V AC | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2014-06-28T16:00:00 |
J1685 | Engineering - Lighting and Grounding System | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2014-06-28T16:00:00 |
J1775 | Engineering - Plant Communication and Visualization System | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2014-06-28T16:00:00 |
J1865 | Engineering - Cables and Cable Trays | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2014-06-28T16:00:00 |
J2145 | Engineering - Field Cabling | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2014-06-28T16:00:00 |
307494 | PROCESS | |||||
F5010 | Engineering - Process | Not Started | Yes | 0,0 | 2014-03-01T08:00:00 | 2014-11-25T16:00:00 |
F5011 | First Submittal of first Process Engineering Document acc. to DDS | Not Started | Yes | 0,0 | 2014-03-30T16:00:00 | 2014-03-30T16:00:00 |
F5012 | First Submittal of last Process Engineering Document acc. to DDS | Not Started | No | 0,0 | 2014-05-29T16:00:00 | 2014-05-29T16:00:00 |
F5015 | Approval of Process Engineering Documents by Client and Independent Third Party | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2014-06-12T16:00:00 |
307495 | Corrosion Control and Mettalurgy | |||||
M2501 | Review CMS & Control Philosphy | Not Started | Yes | 0,0 | 2014-03-03T08:00:00 | 2014-03-20T16:00:00 |
M2502 | Corrosion control & Monitoring Sys. Specs | Not Started | Yes | 0,0 | 2014-03-21T08:00:00 | 2014-04-09T16:00:00 |
M2503 | Cath. Protn Design/Specs/D.sheets/Dwgs | Not Started | Yes | 0,0 | 2014-04-01T08:00:00 | 2014-04-29T16:00:00 |
M2504 | Protective coating /Lining Specs/Data sheets | Not Started | Yes | 0,0 | 2014-04-30T08:00:00 | 2014-05-28T16:00:00 |
M2505 | Cathodic Protn. - Req | Not Started | No | 0,0 | 2014-04-30T08:00:00 | 2014-05-17T16:00:00 |
M2506 | Coating/Lining - Req. | Not Started | Yes | 0,0 | 2014-05-29T08:00:00 | 2014-06-22T16:00:00 |
307496 | AUXILIARY EQUIPMENT | |||||
F5140 | Engineering - Auxiliary Equipment | Not Started | Yes | 0,0 | 2014-05-30T08:00:00 | 2014-11-25T16:00:00 |
F5150 | First Submittal of first Auxiliary Equipment Document acc. to DDS | Not Started | Yes | 0,0 | 2014-06-28T16:00:00 | 2014-06-28T16:00:00 |
F5160 | First Submittal of last Auxiliary Equipment Document acc. to DDS | Not Started | No | 0,0 | 2014-08-27T16:00:00 | 2014-08-27T16:00:00 |
F5170 | Approval of Auxiliary Equipment Documents by Client and Independent Third Party | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2014-09-10T16:00:00 |
307497 | AUTOMATION, INSTRUMENTATION, CONTROL | |||||
F5050 | Engineering - Automation, Instrumentation and Control | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2015-02-23T16:00:00 |
F5051 | First Submittal of first Automation, I&C Engineering Document acc. to DDS | Not Started | Yes | 0,0 | 2014-04-29T16:00:00 | 2014-04-29T16:00:00 |
F5052 | First Submittal of last Automation, I&C Engineering Document acc. to DDS | Not Started | No | 0,0 | 2014-06-28T16:00:00 | 2014-06-28T16:00:00 |
F5055 | Approval of Automation, I&C Engineering Documents by Client and Independent third Party | Not Started | Yes | 0,0 | 2014-04-30T08:00:00 | 2014-07-12T16:00:00 |
J1945 | Engineering - ICSS System | Not Started | Yes | 0,0 | 2014-04-30T08:00:00 | 2014-07-28T16:00:00 |
J2045 | Engineering - Field Instruments | Not Started | Yes | 0,0 | 2014-04-30T08:00:00 | 2014-06-28T16:00:00 |
307498 | PIPING | |||||
F5180 | Engineering - Piping | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2014-10-26T16:00:00 |
F5190 | First Submittal of first Piping Document acc. to DDS | Not Started | Yes | 0,0 | 2014-04-29T16:00:00 | 2014-04-29T16:00:00 |
F5200 | First Submittal of last Piping Document acc. to DDS | Not Started | No | 0,0 | 2014-06-28T16:00:00 | 2014-06-28T16:00:00 |
F5210 | Approval of Piping Documents by Client and Independent third Party | Not Started | Yes | 0,0 | 2014-04-30T08:00:00 | 2014-07-12T16:00:00 |
J2225 | Engineering - Condensate System Piping | Not Started | Yes | 0,0 | 2014-04-24T08:00:00 | 2014-08-16T16:00:00 |
J2325 | Engineering - Methanol injection Piping | Not Started | No | 0,0 | 2014-04-17T08:00:00 | 2014-08-09T16:00:00 |
J2525 | Engineering - Nitrogen Nitrogen System Piping | Not Started | No | 0,0 | 2014-03-31T08:00:00 | 2014-07-23T16:00:00 |
J3145 | Engineering - Fuel Gas Supply System Piping | Not Started | Yes | 0,0 | 2014-04-30T08:00:00 | 2014-08-22T16:00:00 |
J3635 | Engineering - Chlorination System Piping | Not Started | Yes | 0,0 | 2014-05-07T08:00:00 | 2014-08-29T16:00:00 |
J3715 | Engineering Ready for Procurement - Well head flow lines | Not Started | Yes | 0,0 | 2014-06-09T08:00:00 | 2014-06-09T08:00:00 |
J3770 | Engineering Ready for Procurement - Methanol lines | Not Started | Yes | 0,0 | 2014-06-09T08:00:00 | 2014-06-09T08:00:00 |
J3830 | Engineering - Condensate Piping | Not Started | Yes | 0,0 | 2014-04-07T08:00:00 | 2014-07-30T16:00:00 |
J3890 | Engineering - Off gas connection piping | Not Started | Yes | 0,0 | 2014-04-07T08:00:00 | 2014-07-30T16:00:00 |
J2725 | Engineering - Heat medium piping | Not Started | Yes | 0,0 | 2014-05-21T08:00:00 | 2014-09-12T16:00:00 |
J4010 | Engineering - Gas / Condensate Piping | Not Started | No | 0,0 | 2014-05-28T08:00:00 | 2014-09-19T16:00:00 |
J4070 | Engineering - Gas Piping | Not Started | Yes | 0,0 | 2014-05-28T08:00:00 | 2014-09-19T16:00:00 |
J4130 | Engineering - Condensate Piping | Not Started | No | 0,0 | 2014-04-07T08:00:00 | 2014-07-30T16:00:00 |
J2825 | Engineering - Chemical injection piping | Not Started | Yes | 0,0 | 2014-06-04T08:00:00 | 2014-09-26T16:00:00 |
J3025 | Engineering - Produced water piping | Not Started | Yes | 0,0 | 2014-05-07T08:00:00 | 2014-08-29T16:00:00 |
J3225 | Engineering - Inertgas Piping | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2014-07-23T16:00:00 |
J4185 | Engineering - Methanol injection interconnecting piping | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2014-07-23T16:00:00 |
J4240 | Engineering - Amine Piping | Not Started | Yes | 0,0 | 2014-05-14T08:00:00 | 2014-09-05T16:00:00 |
J4300 | Engineering - Glycol Piping | Not Started | Yes | 0,0 | 2014-05-14T08:00:00 | 2014-09-05T16:00:00 |
J4470 | Engineering - Plant Water Piping | Not Started | Yes | 0,0 | 2014-05-07T08:00:00 | 2014-08-29T16:00:00 |
J4750 | Engineering - Fresh Water System Piping | Not Started | Yes | 0,0 | 2014-05-07T08:00:00 | 2014-08-29T16:00:00 |
J4810 | Engineering - Demin Water System Piping | Not Started | Yes | 0,0 | 2014-05-07T08:00:00 | 2014-08-29T16:00:00 |
J5040 | Engineering - Plant Air Piping | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2014-07-23T16:00:00 |
J5100 | Engineering - Instrument Air Piping | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2014-07-23T16:00:00 |
J5160 | Engineering - Produced water treatment system piping | Not Started | Yes | 0,0 | 2014-04-07T08:00:00 | 2014-07-30T16:00:00 |
J3870 | data sheet and techn. requirements for purchasing available | Not Started | No | 0,0 | 2014-04-12T08:00:00 | 2014-04-12T08:00:00 |
J5355 | Engineering - interconecting piping (general) | Not Started | Yes | 0,0 | 2014-04-07T08:00:00 | 2014-07-30T16:00:00 |
J2925 | Engineering - Flare interconnecting piping | Not Started | Yes | 0,0 | 2014-04-14T08:00:00 | 2014-08-06T16:00:00 |
307499 | Insulation | |||||
M2601 | Insulation Specs/Data Sheet/Purch.Reqn. | Not Started | No | 0,0 | 2014-06-06T08:00:00 | 2014-07-04T16:00:00 |
307500 | Flowline | |||||
M2901 | Typical Details | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-24T16:00:00 |
M2902 | Wall Thickness Study Specification | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-24T16:00:00 |
M2903 | Line Pipe Data Sheets & Req. | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-24T16:00:00 |
M2904 | Route Selection Study | Not Started | No | 0,0 | 2014-03-31T08:00:00 | 2014-05-01T16:00:00 |
M2905 | Ground Profile | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-05-08T16:00:00 |
M2906 | Stress Analysis & Calculations | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-24T16:00:00 |
M2907 | Location Class Report | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-24T16:00:00 |
M2908 | Detailed Drawings & Arrangements for critical area | Not Started | Yes | 0,0 | 2014-03-31T08:00:00 | 2014-06-08T16:00:00 |
M2909 | General Planimetry | Not Started | No | 0,0 | 2014-03-01T08:00:00 | 2014-03-24T16:00:00 |
307501 | BASIC ENGINEERING INCL. FEED ENDORSEMENT | |||||
F0900 | Basic Engineering | Not Started | Yes | 0,0 | 2014-03-01T08:00:00 | 2014-07-19T16:00:00 |
F0850 | Feed Endorsement | Not Started | Yes | 0,0 | 2014-03-01T08:00:00 | 2014-03-30T16:00:00 |
307502 | FINAL DOCUMENTATION | |||||
M3780 | Final Documentation - Water / Condensate Separator System | Not Started | No | 0,0 | 2015-08-16T08:00:00 | 2015-11-28T16:00:00 |
M3790 | Final Documentation - Condensate Stabilisation System | Not Started | No | 0,0 | 2015-08-16T08:00:00 | 2015-11-28T16:00:00 |
M3800 | Final Documentation - Test Separation and Metering System | Not Started | No | 0,0 | 2015-08-16T08:00:00 | 2015-11-28T16:00:00 |
M3810 | Final Documentation - Gas Reception System | Not Started | No | 0,0 | 2015-08-16T08:00:00 | 2015-11-28T16:00:00 |
M3820 | Final Documentation - Gas Separation System | Not Started | No | 0,0 | 2015-08-16T08:00:00 | 2015-11-28T16:00:00 |
M3830 | Final Documentation - Offgas Compression System | Not Started | No | 0,0 | 2015-08-16T08:00:00 | 2015-11-28T16:00:00 |
M3840 | Final Documentation - Gas Treatment System | Not Started | No | 0,0 | 2015-08-30T08:00:00 | 2015-12-12T16:00:00 |
M3850 | Final Documentation - Gas Conditioning (Dehydration) System | Not Started | No | 0,0 | 2015-09-02T08:00:00 | 2015-12-15T16:00:00 |
M3860 | Final Documentation - Gas Conditioning (Dew Pointing) System | Not Started | No | 0,0 | 2015-09-16T08:00:00 | 2015-12-29T16:00:00 |
M3870 | Final Documentation - Gas Export and Metering System | Not Started | No | 0,0 | 2015-07-20T08:00:00 | 2015-11-01T16:00:00 |
M3880 | Final Documentation - Gas Sweetening (Amine) System | Not Started | No | 0,0 | 2015-09-01T08:00:00 | 2015-12-14T16:00:00 |
M3890 | Final Documentation - Condensate Storage and Metering System | Not Started | No | 0,0 | 2015-07-26T08:00:00 | 2015-11-07T16:00:00 |
M3900 | Final Documentation - Cooling Medium (Propane) System | Not Started | No | 0,0 | 2015-09-16T08:00:00 | 2015-12-29T16:00:00 |
M3910 | Final Documentation - Heating Medium System | Not Started | No | 0,0 | 2015-07-04T08:00:00 | 2015-10-15T16:00:00 |
M3920 | Final Documentation - Chemical Injection System | Not Started | No | 0,0 | 2015-07-04T08:00:00 | 2015-10-15T16:00:00 |
M3960 | Final Documentation - Methanol Injection System | Not Started | No | 0,0 | 2015-09-23T08:00:00 | 2016-01-05T16:00:00 |
M3980 | Final Documentation - Utility Miscellaneous System | Not Started | No | 0,0 | 2015-09-09T08:00:00 | 2015-12-22T16:00:00 |
M3770 | Final Documentation - Gas Well System | Not Started | No | 0,0 | 2015-07-30T08:00:00 | 2015-11-11T16:00:00 |
M3895 | Final Documentation - Well Flowlines System | Not Started | No | 0,0 | 2015-07-05T08:00:00 | 2015-10-17T16:00:00 |
M3930 | Final Documentation - Flare System | Not Started | No | 0,0 | 2015-09-23T08:00:00 | 2016-01-05T16:00:00 |
M3940 | Final Documentation - Produced Water Treatment System and Evaporation Pond | Not Started | No | 0,0 | 2015-09-23T08:00:00 | 2016-01-05T16:00:00 |
M3950 | Final Documentation - Fuel Gas System | Not Started | No | 0,0 | 2015-09-23T08:00:00 | 2016-01-05T16:00:00 |
M3970 | Final Documentation - Chlorination System | Not Started | No | 0,0 | 2015-07-04T08:00:00 | 2015-10-15T16:00:00 |
M3990 | Final Documentation - Industrial Water System | Not Started | No | 0,0 | 2015-07-04T08:00:00 | 2015-10-15T16:00:00 |
M4000 | Final Documentation - Fresh / Potable / Demin Water System | Not Started | No | 0,0 | 2015-07-04T08:00:00 | 2015-10-15T16:00:00 |
M4010 | Final Documentation - Open Drains System | Not Started | No | 0,0 | 2015-07-04T08:00:00 | 2015-10-15T16:00:00 |
M4020 | Final Documentation - Closed Drains System | Not Started | No | 0,0 | 2015-07-04T08:00:00 | 2015-10-15T16:00:00 |
M4030 | Final Documentation - Diesel Oil System | Not Started | No | 0,0 | 2015-07-04T08:00:00 | 2015-10-15T16:00:00 |
M4040 | Final Documentation - Instrument and Plant Air System | Not Started | No | 0,0 | 2015-07-18T08:00:00 | 2015-10-29T16:00:00 |
M4050 | Final Documentation - Inert Gas (Nitrogen) System | Not Started | No | 0,0 | 2015-07-18T08:00:00 | 2015-10-29T16:00:00 |
M4060 | Final Documentation - Sewage Water System | Not Started | No | 0,0 | 2015-07-04T08:00:00 | 2015-10-15T16:00:00 |
M4070 | Final Documentation - Fire Water System | Not Started | No | 0,0 | 2015-07-04T08:00:00 | 2015-10-15T16:00:00 |
M4080 | Final Documentation - Main Power Generation System | Not Started | Yes | 0,0 | 2015-11-18T08:00:00 | 2016-03-01T16:00:00 |
M4090 | Final Documentation - Emergency Power Generators System | Not Started | No | 0,0 | 2015-07-04T08:00:00 | 2015-10-15T16:00:00 |
307503 | FLOWLINE & WELL HEAD | |||||
307504 | CPF | |||||
307505 | As-Built_Common | |||||
307506 | CONSTRUCTION | |||||
307507 | 570 - CLOSED DRAINS SYSTEM | |||||
M4132608 | Mechanical Completion - System 570 | Not Started | Yes | 0,0 | 2015-06-17T16:00:00 | 2015-06-17T16:00:00 |
307508 | Civil & Structural | |||||
307509 | Piping | |||||
M4132602 | Piping - Cosed Drains System | Not Started | No | 0,0 | 2015-02-23T08:00:00 | 2015-05-24T16:00:00 |
M4132609 | Hydrotest | Not Started | Yes | 0,0 | 2015-06-11T08:00:00 | 2015-06-17T16:00:00 |
M4132601 | Prefabrication | Not Started | Yes | 0,0 | 2014-12-25T08:00:00 | 2015-02-22T16:00:00 |
307510 | Mechanical / Eq | |||||
M4132603 | Mechanical / Equipment - Cosed Drains System | Not Started | Yes | 0,0 | 2015-03-12T08:00:00 | 2015-06-10T16:00:00 |
307511 | Electrical | |||||
M4132604 | Electrical - Cosed Drains System | Not Started | Yes | 0,0 | 2015-04-27T08:00:00 | 2015-06-17T16:00:00 |
307512 | Instrumentation & Telecomm | |||||
M4132605 | Instrumentation & Telecomm - Cosed Drains System | Not Started | Yes | 0,0 | 2015-04-27T08:00:00 | 2015-06-17T16:00:00 |
307513 | Paiting & Insulation | |||||
M4132606 | Paiting & Insulation - Cosed Drains System | Not Started | No | 0,0 | 2015-06-18T08:00:00 | 2015-07-01T16:00:00 |
307514 | Pre-commissioning | |||||
M4132607 | Pre-commissioning - Cosed Drains System | Not Started | No | 0,0 | 2015-06-18T08:00:00 | 2015-07-15T16:00:00 |
307515 | 440 - PRODUCED WATER AND EVAPORATION POND SYSTEM | |||||
M4131808 | Mechanical Completion - System 440 | Not Started | Yes | 0,0 | 2015-10-06T16:00:00 | 2015-10-06T16:00:00 |
M4131800 | Civil Works - Evaporation pond | Not Started | No | 0,0 | 2014-08-31T08:00:00 | 2014-12-13T16:00:00 |
307516 | Civil & Structural | |||||
307517 | Piping | |||||
M4131802 | Piping - Produced Water and Evaporation Pond System | Not Started | No | 0,0 | 2015-04-30T08:00:00 | 2015-07-29T16:00:00 |
M4131809 | Hydrotest | Not Started | Yes | 0,0 | 2015-09-30T08:00:00 | 2015-10-06T16:00:00 |
M4131801 | Prefabrication | Not Started | Yes | 0,0 | 2015-03-01T08:00:00 | 2015-04-29T16:00:00 |
307518 | Electrical | |||||
M4131804 | Electrical - Produced Water and Evaporation Pond System | Not Started | Yes | 0,0 | 2015-09-12T08:00:00 | 2015-10-05T16:00:00 |
307519 | Instrumentation & Telecomm | |||||
M4131805 | Instrumentation & Telecomm - Produced Water and Evaporation Pond System | Not Started | No | 0,0 | 2015-09-12T08:00:00 | 2015-10-05T16:00:00 |
307520 | Paiting & Insulation | |||||
M4131806 | Paiting & Insulation - Produced Water and Evaporation Pond System | Not Started | No | 0,0 | 2015-10-07T08:00:00 | 2015-10-20T16:00:00 |
307521 | Pre-commissioning | |||||
M4131807 | Pre-commissioning - Produced Water and Evaporation Pond System | Not Started | No | 0,0 | 2015-10-07T08:00:00 | 2015-10-27T16:00:00 |
307522 | Mechanical / Eq | |||||
M4131803 | Mechanical / Equipment - Produced Water System | Not Started | Yes | 0,0 | 2015-08-05T08:00:00 | 2015-09-29T16:00:00 |
307523 | 330 - CONDENSATE STORAGE AND METERING SYSTEM | |||||
M4131308 | Mechanical Completion - System 330 | Not Started | Yes | 0,0 | 2015-10-03T16:00:00 | 2015-10-03T16:00:00 |
307524 | Pre-commissioning | |||||
M4131307 | Pre-commissioning - Condensate Storage and Metering System | Not Started | Yes | 0,0 | 2015-10-04T08:00:00 | 2015-10-24T16:00:00 |
307525 | Civil & Structural | |||||
307526 | Electrical | |||||
M4131304 | Electrical - Condensate Storage and Metering System | Not Started | Yes | 0,0 | 2015-06-21T08:00:00 | 2015-10-03T16:00:00 |
307527 | Piping | |||||
M4131302 | Piping - Condensate Storage and Metering System | Not Started | No | 0,0 | 2015-01-19T08:00:00 | 2015-04-19T16:00:00 |
M4131309 | Hydrotest | Not Started | Yes | 0,0 | 2015-09-27T08:00:00 | 2015-10-03T16:00:00 |
M4131300 | Prefabrication (70%) | Not Started | Yes | 0,0 | 2014-12-20T08:00:00 | 2015-01-18T16:00:00 |
M4131301 | Prefabrication (100%) | Not Started | No | 0,0 | 2015-01-11T08:00:00 | 2015-02-09T16:00:00 |
307528 | Instrumentation & Telecomm | |||||
M4131305 | Instrumentation & Telecomm - Condensate Storage and Metering System | Not Started | Yes | 0,0 | 2015-06-21T08:00:00 | 2015-10-03T16:00:00 |
307529 | Paiting & Insulation | |||||
M4131306 | Paiting & Insulation - Metering System | Not Started | No | 0,0 | 2015-10-04T08:00:00 | 2015-10-17T16:00:00 |
M4134097 | Paiting & Insulation - Condensate Storage | Not Started | No | 0,0 | 2015-06-21T08:00:00 | 2015-07-04T16:00:00 |
307530 | Mechanical / Eq | |||||
M4131303 | Mechanical / Equipment - Condensate Storage | Not Started | Yes | 0,0 | 2015-04-21T08:00:00 | 2015-06-08T16:00:00 |
M4131310 | Mechanical / Equipment - Metering System | Not Started | Yes | 0,0 | 2015-07-14T08:00:00 | 2015-09-26T16:00:00 |
M4131311 | Hydrotest - Condensate Storage | Not Started | Yes | 0,0 | 2015-06-09T08:00:00 | 2015-06-20T16:00:00 |
307531 | CIVIL, STRUCTURAL STEEL | |||||
307532 | 220 - GAS RECEPTION SYSTEM | |||||
M413408 | Mechanical Completion - System 220A | Not Started | Yes | 0,0 | 2015-07-13T16:00:00 | 2015-07-13T16:00:00 |
307533 | Civil & Structural | |||||
307534 | Piping | |||||
M413402 | Piping - Gas Reception System | Not Started | Yes | 0,0 | 2015-01-03T08:00:00 | 2015-04-02T16:00:00 |
M413409 | Hydrotest | Not Started | No | 0,0 | 2015-04-03T08:00:00 | 2015-04-08T16:00:00 |
M413401 | Prefabrication | Not Started | No | 0,0 | 2014-11-03T08:00:00 | 2015-01-01T16:00:00 |
307535 | Electrical | |||||
M413404 | Electrical - Gas Reception System | Not Started | Yes | 0,0 | 2015-02-18T08:00:00 | 2015-07-13T16:00:00 |
307536 | Instrumentation & Telecommunication | |||||
M413405 | Instrumentation & Telecommunication - Gas Reception System | Not Started | Yes | 0,0 | 2015-02-18T08:00:00 | 2015-07-13T16:00:00 |
307537 | Pre-commissioning | |||||
M413407 | Pre-commissioning - Gas Reception System (Line 1-3) | Not Started | No | 0,0 | 2015-08-29T08:00:00 | 2015-09-24T16:00:00 |
M413411 | Pre-commissioning - Gas Reception System (Line 4-6) | Not Started | No | 0,0 | 2015-09-13T08:00:00 | 2015-10-10T16:00:00 |
M413412 | Pre-commissioning - Gas Reception System (Line 7-9) | Not Started | Yes | 0,0 | 2015-10-11T08:00:00 | 2015-11-07T16:00:00 |
307538 | Mechanical / Equipment | |||||
M413403 | Mechanical / Equipment - Gas Reception System | Not Started | Yes | 0,0 | 2015-04-14T08:00:00 | 2015-07-13T16:00:00 |
307539 | Paiting & Insulation | |||||
M413406 | Paiting & Insulation - Gas Reception System | Not Started | No | 0,0 | 2015-07-14T08:00:00 | 2015-07-27T16:00:00 |
307540 | 400 - COOLING MEDIUM (PROPANE) SYSTEM | |||||
M4131408 | Mechanical Completion - System 400 | Not Started | Yes | 0,0 | 2015-09-28T16:00:00 | 2015-09-28T16:00:00 |
307541 | Piping | |||||
M4131402 | Piping - Cooling Medium (Propane) System | Not Started | No | 0,0 | 2015-02-23T08:00:00 | 2015-05-24T16:00:00 |
M4131409 | Hydrotest | Not Started | No | 0,0 | 2015-08-18T08:00:00 | 2015-08-23T16:00:00 |
M4131401 | Prefabrication | Not Started | Yes | 0,0 | 2014-12-25T08:00:00 | 2015-02-22T16:00:00 |
307542 | Civil & Structural | |||||
307543 | Electrical | |||||
M4131404 | Electrical - Cooling Medium (Propane) System | Not Started | Yes | 0,0 | 2015-08-11T08:00:00 | 2015-09-28T16:00:00 |
307544 | Instrumentation & Telecomm | |||||
M4131405 | Instrumentation & Telecomm - Cooling Medium (Propane) System | Not Started | Yes | 0,0 | 2015-08-11T08:00:00 | 2015-09-28T16:00:00 |
307545 | Paiting & Insulation | |||||
M4131406 | Paiting & Insulation - Cooling Medium (Propane) System | Not Started | No | 0,0 | 2015-09-29T08:00:00 | 2015-10-12T16:00:00 |
307546 | Mechanical / Eq | |||||
M4131403 | Mechanical / Equipment - Cooling Medium (Propane) System | Not Started | Yes | 0,0 | 2015-08-11T08:00:00 | 2015-09-28T16:00:00 |
307547 | Pre-commissioining | |||||
M4131407 | Pre-commissioning - Cooling Medium (Propane) System | Not Started | No | 0,0 | 2015-09-29T08:00:00 | 2015-10-12T16:00:00 |
307548 | COMMON | |||||
307549 | Site Preparation | |||||
M411401 | Site Prepn.,Soil Stabilization,Grading etc. | Not Started | No | 0,0 | 2014-06-19T08:00:00 | 2014-10-01T16:00:00 |
307550 | Temporary Facilities | |||||
M411104 | Contractor's Site Offices / Field Offices | Not Started | No | 0,0 | 2014-06-02T08:00:00 | 2014-08-10T16:00:00 |
M411111 | Personnel Camp Accomodation | Not Started | Yes | 0,0 | 2014-06-02T08:00:00 | 2014-08-10T16:00:00 |
M411101 | Access Roads & Parkings | Not Started | Yes | 0,0 | 2014-05-01T08:00:00 | 2014-06-01T16:00:00 |
M411113 | Warehouses & Laydown Areas | Not Started | No | 0,0 | 2014-06-19T08:00:00 | 2014-08-27T16:00:00 |
M411108 | Maintenance Shops | Not Started | No | 0,0 | 2014-07-24T08:00:00 | 2014-10-01T16:00:00 |
M411103 | Concrete Batching Plant | Not Started | No | 0,0 | 2014-06-02T08:00:00 | 2014-08-10T16:00:00 |
M411110 | Personnel & Materials Transport | Not Started | No | 0,0 | 2014-06-02T08:00:00 | 2014-06-25T16:00:00 |
M411112 | Utilities | Not Started | No | 0,0 | 2014-06-19T08:00:00 | 2014-08-27T16:00:00 |
M411105 | Crane Installation | Not Started | No | 0,0 | 2014-07-07T08:00:00 | 2014-08-31T16:00:00 |
M411102 | Camp 1st Occupancy | Not Started | Yes | 0,0 | 2014-06-02T08:00:00 | 2014-06-02T08:00:00 |
M411106 | Fabrication & Testing Facilities | Not Started | No | 0,0 | 2014-07-24T08:00:00 | 2014-08-27T16:00:00 |
M411109 | Medical Facilities | Not Started | No | 0,0 | 2014-07-07T08:00:00 | 2014-08-10T16:00:00 |
M411107 | Fire & Safety Facilities | Not Started | No | 0,0 | 2014-07-24T08:00:00 | 2014-08-27T16:00:00 |
M411114 | Waste Management Facilities | Not Started | No | 0,0 | 2014-06-19T08:00:00 | 2014-07-23T16:00:00 |
307551 | Field Engineering | |||||
M411201 | Field Engineering works | Not Started | No | 0,0 | 2014-07-24T08:00:00 | 2015-09-10T16:00:00 |
307552 | Mobilization | |||||
M411301 | Mob. Complete Contruction Management Team | Not Started | Yes | 0,0 | 2014-06-02T08:00:00 | 2014-07-02T16:00:00 |
M411302 | Mob. Electrical Subcontractor | Not Started | No | 0,0 | 2014-07-03T08:00:00 | 2014-08-06T16:00:00 |
M411303 | Mob. Eqpt. Erection Subcontractors | Not Started | No | 0,0 | 2014-07-03T08:00:00 | 2014-08-06T16:00:00 |
M411316 | Mobilization Complete major works | Not Started | No | 0,0 | 2014-07-03T08:00:00 | 2014-08-06T16:00:00 |
M411314 | Mob.1st Project Management Team | Not Started | No | 0,0 | 2014-07-03T08:00:00 | 2014-08-06T16:00:00 |
M411304 | Mob. Hydrotest Subcontractors | Not Started | No | 0,0 | 2014-07-03T08:00:00 | 2014-08-06T16:00:00 |
M411310 | Mob. Project Management Team | Not Started | No | 0,0 | 2014-07-03T08:00:00 | 2014-08-06T16:00:00 |
M411305 | Mob. Instru & Control Sys. Subcontractor | Not Started | No | 0,0 | 2014-07-03T08:00:00 | 2014-08-06T16:00:00 |
M411308 | Mob. Pipeline Team | Not Started | No | 0,0 | 2014-07-03T08:00:00 | 2014-08-06T16:00:00 |
M411311 | Mob. Site Preparation Sub-contractor | Not Started | No | 0,0 | 2014-07-03T08:00:00 | 2014-08-06T16:00:00 |
M411307 | Mob. Painting/Lining S/Cr | Not Started | No | 0,0 | 2014-07-03T08:00:00 | 2014-08-06T16:00:00 |
M411312 | Mob. Steel Structure Subcontractor | Not Started | No | 0,0 | 2014-07-03T08:00:00 | 2014-08-06T16:00:00 |
M411306 | Mob. Insulation/Fireproofing S/Cr | Not Started | No | 0,0 | 2014-07-03T08:00:00 | 2014-08-06T16:00:00 |
M411309 | Mob. Piping Subcontractors | Not Started | No | 0,0 | 2014-07-03T08:00:00 | 2014-08-06T16:00:00 |
M411313 | Mob. Temp. Facilities Sub-contractors | Not Started | No | 0,0 | 2014-07-03T08:00:00 | 2014-08-06T16:00:00 |
M411315 | Mob.Tank Foundation & Erection Teams | Not Started | No | 0,0 | 2014-07-03T08:00:00 | 2014-08-06T16:00:00 |
307553 | Tie - ins | |||||
M411501 | Civil Roads & Drains Tie-ins | Not Started | No | 0,0 | 2014-07-01T08:00:00 | 2014-08-27T16:00:00 |
M411502 | E & I & Telecomm. Tie-ins | Not Started | No | 0,0 | 2014-07-01T08:00:00 | 2014-08-27T16:00:00 |
307554 | 830 - EMERGENCY POWER GENERATORS SYSTEM | |||||
M4133308 | Mechanical Completion - System 830 | Not Started | Yes | 0,0 | 2015-05-31T16:00:00 | 2015-05-31T16:00:00 |
307555 | Civil & Structural | |||||
307556 | Piping | |||||
M4133302 | Piping - Emergency Power Generator | Not Started | Yes | 0,0 | 2015-02-23T08:00:00 | 2015-05-24T16:00:00 |
M4133309 | Hydrotest | Not Started | Yes | 0,0 | 2015-05-25T08:00:00 | 2015-05-31T16:00:00 |
M4133301 | Prefabrication | Not Started | Yes | 0,0 | 2014-12-25T08:00:00 | 2015-02-22T16:00:00 |
307557 | Mechanical / Eq | |||||
M4133303 | Mechanical / Equipment - Emergency Power Generator | Not Started | Yes | 0,0 | 2015-02-16T08:00:00 | 2015-05-17T16:00:00 |
307558 | Electrical | |||||
M4133304 | Electrical - Emergency Power Generator | Not Started | Yes | 0,0 | 2015-04-02T08:00:00 | 2015-05-31T16:00:00 |
307559 | Paiting & Insulation | |||||
M4133306 | Paiting & Insulation - Emergency Power Generator | Not Started | No | 0,0 | 2015-06-01T08:00:00 | 2015-06-14T16:00:00 |
307560 | Pre-commissioning | |||||
M4133307 | Pre-commissioning - Emergency Power Generator | Not Started | No | 0,0 | 2015-06-01T08:00:00 | 2015-06-28T16:00:00 |
307561 | Instrumentation & Telecomm | |||||
M4133305 | Instrumentation & Telecomm - Emergency Power Generator | Not Started | Yes | 0,0 | 2015-04-02T08:00:00 | 2015-05-31T16:00:00 |
307562 | 630 - INSTRUMENT AND PLANT AIR SYSTEM | |||||
M4132808 | Mechanical Completion - System 630 | Not Started | Yes | 0,0 | 2015-09-21T16:00:00 | 2015-09-21T16:00:00 |
307563 | Civil & Structural | |||||
307564 | Piping | |||||
M4132802 | Piping - Instrument & Plant Air System | Not Started | Yes | 0,0 | 2015-06-16T08:00:00 | 2015-09-14T16:00:00 |
M4132809 | Hydrotest | Not Started | Yes | 0,0 | 2015-09-15T08:00:00 | 2015-09-21T16:00:00 |
M4132801 | Prefabrication | Not Started | Yes | 0,0 | 2015-04-17T08:00:00 | 2015-06-15T16:00:00 |
307565 | Mechanical / Eq | |||||
M4132803 | Mechanical / Equipment - Instrument & Plant Air System | Not Started | Yes | 0,0 | 2015-06-10T08:00:00 | 2015-09-08T16:00:00 |
307566 | Instrumentation & Telecomm | |||||
M4132805 | Instrumentation & Telecomm - Instrument & Plant Air System | Not Started | Yes | 0,0 | 2015-07-26T08:00:00 | 2015-09-21T16:00:00 |
307567 | Paiting & Insulation | |||||
M4132806 | Paiting & Insulation - Instrument & Plant Air System | Not Started | No | 0,0 | 2015-09-22T08:00:00 | 2015-10-05T16:00:00 |
307568 | Electrical | |||||
M4132804 | Electrical - Instrument & Plant Air System | Not Started | Yes | 0,0 | 2015-07-26T08:00:00 | 2015-09-21T16:00:00 |
307569 | Pre-commissioning | |||||
M4132807 | Pre-Commissioning - Instrument & Plant Air System | Not Started | No | 0,0 | 2015-09-22T08:00:00 | 2015-10-15T16:00:00 |
307570 | 220 - GAS SEPARATION SYSTEM | |||||
M413608 | Mechanical Completion - System 220B | Not Started | Yes | 0,0 | 2015-07-13T16:00:00 | 2015-07-13T16:00:00 |
307571 | Civil & Structural | |||||
307572 | Piping | |||||
M413602 | Piping - Gas Separation System | Not Started | Yes | 0,0 | 2015-01-03T08:00:00 | 2015-04-02T16:00:00 |
M413609 | Hydrotest | Not Started | No | 0,0 | 2015-04-03T08:00:00 | 2015-04-08T16:00:00 |
M413601 | Prefabrication | Not Started | No | 0,0 | 2014-11-03T08:00:00 | 2015-01-01T16:00:00 |
307573 | Electrical | |||||
M413604 | Electrical - Gas Separation System | Not Started | Yes | 0,0 | 2015-02-18T08:00:00 | 2015-07-13T16:00:00 |
307574 | Instrumentation & Telecommunication | |||||
M413605 | Instrumentation & Telecommunication - Gas Separation System | Not Started | Yes | 0,0 | 2015-02-18T08:00:00 | 2015-07-13T16:00:00 |
307575 | Mechanical / Eq | |||||
M413603 | Mechanical / Equipment - Gas Separation System | Not Started | Yes | 0,0 | 2015-04-14T08:00:00 | 2015-07-13T16:00:00 |
307576 | Paiting & Insulation | |||||
M413606 | Paiting & Insulation - Gas Separation System | Not Started | No | 0,0 | 2015-07-14T08:00:00 | 2015-07-27T16:00:00 |
307577 | Pre-commissioning | |||||
M413607 | Pre-commissioning - Gas Separation System | Not Started | No | 0,0 | 2015-08-22T08:00:00 | 2015-10-31T16:00:00 |
307578 | 360 - WELL FLOWLINES SYSTEM | |||||
M412101 | Right of way (line 1-3) | Not Started | Yes | 0,0 | 2014-11-29T08:00:00 | 2015-03-29T16:00:00 |
M412102 | Pipe stringing (line 1-3) | Not Started | Yes | 0,0 | 2014-12-06T08:00:00 | 2015-04-05T16:00:00 |
M412103 | Trenching (line 1-3) | Not Started | Yes | 0,0 | 2014-12-04T08:00:00 | 2015-04-04T16:00:00 |
M412104 | Laying (line 1-3) | Not Started | Yes | 0,0 | 2014-12-07T08:00:00 | 2015-04-06T16:00:00 |
M412105 | Lowring-in (line 1-3) | Not Started | No | 0,0 | 2014-12-08T08:00:00 | 2015-04-07T16:00:00 |
M412116 | Hydrotest | Not Started | Yes | 0,0 | 2015-09-27T08:00:00 | 2015-10-17T16:00:00 |
M412100 | Mechanical Completion - System 360 | Not Started | No | 0,0 | 2015-10-17T16:00:00 | 2015-10-17T16:00:00 |
M412106 | Right of way (line 4-6) | Not Started | Yes | 0,0 | 2015-01-27T08:00:00 | 2015-05-27T16:00:00 |
M412107 | Pipe stringing (line 4-6) | Not Started | Yes | 0,0 | 2015-02-03T08:00:00 | 2015-06-03T16:00:00 |
M412108 | Trenching (line 4-6) | Not Started | Yes | 0,0 | 2015-02-02T08:00:00 | 2015-06-02T16:00:00 |
M412109 | Laying (line 4-6) | Not Started | Yes | 0,0 | 2015-02-04T08:00:00 | 2015-06-04T16:00:00 |
M412110 | Lowring-in (line 4-6) | Not Started | No | 0,0 | 2015-02-05T08:00:00 | 2015-06-06T16:00:00 |
M412111 | Right of way (line 7-9) | Not Started | Yes | 0,0 | 2015-03-29T08:00:00 | 2015-07-27T16:00:00 |
M412112 | Pipe stringing (line 7-9) | Not Started | Yes | 0,0 | 2015-04-05T08:00:00 | 2015-08-03T16:00:00 |
M412113 | Trenching (line 7-9) | Not Started | Yes | 0,0 | 2015-04-04T08:00:00 | 2015-08-02T16:00:00 |
M412114 | Laying (line 7-9) | Not Started | Yes | 0,0 | 2015-04-06T08:00:00 | 2015-08-04T16:00:00 |
M412115 | Lowring-in (line 7-9) | Not Started | No | 0,0 | 2015-04-07T08:00:00 | 2015-08-05T16:00:00 |
307579 | 210 - TEST SEPARATION AND METERING SYSTEM | |||||
M413508 | Mechanical Completion - System 210 | Not Started | Yes | 0,0 | 2015-07-27T16:00:00 | 2015-07-27T16:00:00 |
307580 | Civil & Structural | |||||
307581 | Piping | |||||
M413502 | Piping - Test Separation and Metering System | Not Started | Yes | 0,0 | 2015-01-12T08:00:00 | 2015-04-23T16:00:00 |
M413509 | Hydrotest | Not Started | No | 0,0 | 2015-04-25T08:00:00 | 2015-04-30T16:00:00 |
M413500 | Prefabrication 60% | Not Started | Yes | 0,0 | 2014-11-03T08:00:00 | 2015-01-11T16:00:00 |
M413501 | Prefabrication 100% in MIG Workshop | Not Started | No | 0,0 | 2014-12-25T08:00:00 | 2015-03-04T16:00:00 |
307582 | Electrical | |||||
M413504 | Electrical - Test Separation and Metering System | Not Started | Yes | 0,0 | 2015-06-16T08:00:00 | 2015-07-27T16:00:00 |
307583 | Instrumentaion & Telecommunication | |||||
M413505 | Instrumentation & Telecommunication - Test Separation and Metering System | Not Started | Yes | 0,0 | 2015-06-16T08:00:00 | 2015-07-27T16:00:00 |
307584 | Pre-commissioning | |||||
M413507 | Pre-commissioning - Test Separation and Metering System | Not Started | No | 0,0 | 2015-07-28T08:00:00 | 2015-08-24T16:00:00 |
307585 | Mechanical / Equipment | |||||
M413503 | Mechanical / Equipment - Test Separation and Metering System | Not Started | Yes | 0,0 | 2015-05-05T08:00:00 | 2015-07-27T16:00:00 |
307586 | Painting & Insulation | |||||
M413506 | Paiting & Insulation - Test Separation and Metering System | Not Started | No | 0,0 | 2015-07-28T08:00:00 | 2015-11-09T16:00:00 |
307587 | CAMP | |||||
307588 | PLANT & PIPING (INTERCONNECTING) | |||||
307589 | INERTGAS PIPING | |||||
307590 | GAS PIPING | |||||
307591 | GAS / CONDENSATE PIPING | |||||
307592 | HEATING MEDIUM PIPING | |||||
307593 | CHEMICAL INJECTION PIPING | |||||
307594 | METHANOL INJECTION PIPING | |||||
307595 | CONDENSATE PIPING | |||||
307596 | FLARE CONNECTING PIPING | |||||
307597 | PRODUCED WATER PIPING | |||||
307598 | 640 - INERT GAS (NITROGEN) SYSTEM | |||||
M4132908 | Mechanical Completion - System 640 | Not Started | Yes | 0,0 | 2015-09-21T16:00:00 | 2015-09-21T16:00:00 |
307599 | Piping | |||||
M4132902 | Piping - Inert Gas (Nitrogen) System | Not Started | No | 0,0 | 2015-03-02T08:00:00 | 2015-05-31T16:00:00 |
M4133909 | Hydrotest | Not Started | Yes | 0,0 | 2015-09-15T08:00:00 | 2015-09-21T16:00:00 |
M4133901 | Prefabrication | Not Started | Yes | 0,0 | 2015-01-01T08:00:00 | 2015-03-01T16:00:00 |
307600 | Mechanical / Eq | |||||
M4132903 | Mechanical / Equipment - Inert Gas (Nitrogen) System | Not Started | Yes | 0,0 | 2015-06-16T08:00:00 | 2015-09-14T16:00:00 |
307601 | Instrumentation & Telecomm | |||||
M4132905 | Instrumentation & Telecomm - Inert Gas (Nitrogen) System | Not Started | Yes | 0,0 | 2015-08-01T08:00:00 | 2015-09-21T16:00:00 |
307602 | Civil & Structural | |||||
307603 | Electrical | |||||
M4132904 | Electrical - Inert Gas (Nitrogen) System | Not Started | Yes | 0,0 | 2015-08-01T08:00:00 | 2015-09-21T16:00:00 |
307604 | Paiting & Insulation | |||||
M4132906 | Paiting & Insulation - Inert Gas (Nitrogen) System | Not Started | No | 0,0 | 2015-09-22T08:00:00 | 2015-10-05T16:00:00 |
307605 | Pre-commissioning | |||||
M4132907 | Pre-Commissioning - Nitrogen System | Not Started | No | 0,0 | 2015-09-22T08:00:00 | 2015-10-15T16:00:00 |
307606 | 232 - OFFGAS COMPRESSION SYSTEM | |||||
M413708 | Mechanical Completion - System 232 | Not Started | Yes | 0,0 | 2015-09-28T16:00:00 | 2015-09-28T16:00:00 |
307607 | Piping | |||||
M413702 | Piping - Offgas Compression System | Not Started | Yes | 0,0 | 2015-04-25T08:00:00 | 2015-07-23T16:00:00 |
M413709 | Hydrotest | Not Started | No | 0,0 | 2015-07-24T08:00:00 | 2015-07-29T16:00:00 |
M413701 | Prefabrication | Not Started | No | 0,0 | 2015-02-23T08:00:00 | 2015-04-23T16:00:00 |
307608 | Instrumentation & Telecommunication | |||||
M413705 | Instrumentation & Telecommunication - Offgas Compression System | Not Started | Yes | 0,0 | 2015-08-11T08:00:00 | 2015-09-28T16:00:00 |
307609 | Paiting & Insulation | |||||
M413706 | Paiting & Insulation - Offgas Compression System | Not Started | No | 0,0 | 2015-09-29T08:00:00 | 2015-11-02T16:00:00 |
307610 | Mechanical / Eq | |||||
M413703 | Mechanical / Equipment - Offgas Compression System | Not Started | Yes | 0,0 | 2015-08-11T08:00:00 | 2015-09-28T16:00:00 |
307611 | Electrical | |||||
M413704 | Electrical - Offgas Compression System | Not Started | Yes | 0,0 | 2015-08-11T08:00:00 | 2015-09-28T16:00:00 |
307612 | Pre-commissioning | |||||
M413707 | Pre-commissioning - Offgas Compression System | Not Started | No | 0,0 | 2015-09-29T08:00:00 | 2015-10-26T16:00:00 |
307613 | Civil & Structural | |||||
307614 | 530 - FRESH/POTABLE/DEMINERALISED WATER SYSTEM | |||||
M4132408 | Mechanical Completion - System 530 | Not Started | Yes | 0,0 | 2015-06-01T16:00:00 | 2015-06-01T16:00:00 |
307615 | Civil & Structural | |||||
307616 | Piping | |||||
M4132402 | Piping - Fresh and Demin Water System | Not Started | Yes | 0,0 | 2015-03-25T08:00:00 | 2015-05-26T16:00:00 |
M4132409 | Hydrotest | Not Started | Yes | 0,0 | 2015-05-27T08:00:00 | 2015-06-01T16:00:00 |
M4132401 | Prefabrication | Not Started | Yes | 0,0 | 2015-01-24T08:00:00 | 2015-03-24T16:00:00 |
307617 | Mechanical / Eq | |||||
M4132403 | Mechanical / Equipment - Fresh and Demin Water System | Not Started | Yes | 0,0 | 2015-03-18T08:00:00 | 2015-05-19T16:00:00 |
307618 | Electrical | |||||
M4132404 | Electrical - Fresh and Demin Water System | Not Started | Yes | 0,0 | 2015-04-19T08:00:00 | 2015-06-01T16:00:00 |
307619 | Instrumentation & Telecomm | |||||
M4132405 | Instrumentation & Telecomm - Fresh and Demin Water System | Not Started | Yes | 0,0 | 2015-04-19T08:00:00 | 2015-06-01T16:00:00 |
307620 | Paiting & Insulation | |||||
M4132406 | Paiting & Insulation - Fresh and Demin Water System | Not Started | No | 0,0 | 2015-06-02T08:00:00 | 2015-10-19T16:00:00 |
307621 | Pre-commissioning | |||||
M4132407 | Pre-Commissioning - Fresh Water System | Not Started | No | 0,0 | 2015-06-02T08:00:00 | 2015-06-22T16:00:00 |
M4132410 | Pre-Commissioning - Demin Water System | Not Started | No | 0,0 | 2015-06-02T08:00:00 | 2015-06-22T16:00:00 |
307622 | 470 - CHLORINATION SYSTEM | |||||
M4132108 | Mechanical Completion - System 470 | Not Started | Yes | 0,0 | 2015-06-29T16:00:00 | 2015-06-29T16:00:00 |
307623 | Piping | |||||
M4132102 | Piping - Chlorination System | Not Started | Yes | 0,0 | 2015-03-25T08:00:00 | 2015-06-23T16:00:00 |
M4132109 | Hydrotest | Not Started | Yes | 0,0 | 2015-06-24T08:00:00 | 2015-06-29T16:00:00 |
M4132101 | Prefabrication | Not Started | Yes | 0,0 | 2015-01-24T08:00:00 | 2015-03-24T16:00:00 |
307624 | Mechanical / Eq | |||||
M4132103 | Mechanical / Equipment - Chlorination System | Not Started | Yes | 0,0 | 2015-03-18T08:00:00 | 2015-06-16T16:00:00 |
307625 | Instrumentation & Telecomm | |||||
M4132105 | Instrumentation & Telecomm - Chlorination System | Not Started | No | 0,0 | 2015-05-03T08:00:00 | 2015-06-27T16:00:00 |
307626 | Paiting & Insulation | |||||
M4132106 | Paiting & Insulation - Chlorination System | Not Started | No | 0,0 | 2015-06-30T08:00:00 | 2015-07-13T16:00:00 |
307627 | Civil & Structural | |||||
307628 | Electrical | |||||
M4132104 | Electrical - Chlorination System | Not Started | Yes | 0,0 | 2015-05-03T08:00:00 | 2015-06-29T16:00:00 |
307629 | Pre-commissioning | |||||
M4132107 | Pre-Commissioning - Chlorination System | Not Started | No | 0,0 | 2015-06-30T08:00:00 | 2015-07-27T16:00:00 |
307630 | EQUIPMENT, OFF-PACKAGE | |||||
307631 | VESSELS, OFF-PACKAGE | |||||
307632 | INSTRUMENTATION, CONTROL, ELECTRICAL | |||||
307633 | PLANT COMMUNICATION AND VISUALIZATION SYSTEM | |||||
J1850 | Erection - Plant Communication and Visualization System | Not Started | Yes | 0,0 | 2015-04-02T08:00:00 | 2015-06-30T16:00:00 |
J1860 | Commissioning - Plant Communication and Visualization System | Not Started | No | 0,0 | 2015-06-01T08:00:00 | 2015-08-29T16:00:00 |
307634 | FIELD INSTRUMENTS | |||||
307635 | SMALL POWER SYSTEM | |||||
J1570 | Erection - Small Power System (Ende 1. civil - start letzte civil works-4w Dauer anpassen) | Not Started | Yes | 0,0 | 2015-05-12T08:00:00 | 2015-06-18T12:00:00 |
J1580 | Commissioning - Small Power System | Not Started | No | 0,0 | 2015-06-18T12:00:00 | 2015-07-25T16:00:00 |
307636 | UPS 230V AC | |||||
J1660 | Erection - UPS 230V AC | Not Started | Yes | 0,0 | 2015-04-02T08:00:00 | 2015-05-31T16:00:00 |
J1670 | Pre-Commissioning - UPS 230V AC | Not Started | Yes | 0,0 | 2015-06-01T08:00:00 | 2015-06-30T16:00:00 |
J1680 | Ready for Energizing - UPS 230V AC | Not Started | No | 0,0 | 2015-07-01T08:00:00 | 2015-07-01T08:00:00 |
307637 | LIGHTNING AND GROUNDING SYSTEM | |||||
J1760 | Erection - Lighting and Grounding System (Start 1. civil excavation - Ende letzte civil Dauer anpassen) | Not Started | Yes | 0,0 | 2014-12-03T08:00:00 | 2015-01-09T12:00:00 |
J1770 | Commissioning - Lighting and Grounding System | Not Started | No | 0,0 | 2015-01-09T12:00:00 | 2015-01-16T12:00:00 |
307638 | CABLES AND CABLE TRAYS | |||||
J1930 | Erection - Cables and Cable Trays (mit 1. Rohrbr�cke Trays; Kabel im electrical substation Geb�ude; Ende letztes Sys) | Not Started | Yes | 0,0 | 2015-02-01T08:00:00 | 2015-03-10T12:00:00 |
J1940 | Pre-Commissioning - Cables and Cable Trays (gleiche duration wie erection +1M Versatz) | Not Started | No | 0,0 | 2015-03-03T08:00:00 | 2015-04-09T16:00:00 |
307639 | ICSS SYSTEM | |||||
J2020 | Erection - ICSS System | Not Started | Yes | 0,0 | 2015-04-24T12:00:00 | 2015-05-24T12:00:00 |
J2030 | Pre-Commissioning - ICSS System (�ber pre und hot verteilen) | Not Started | Yes | 0,0 | 2015-05-24T12:00:00 | 2016-01-03T16:00:00 |
307640 | LV SYSTEM 400V | |||||
J1170 | Erection - LV System 400V | Not Started | Yes | 0,0 | 2015-05-02T08:00:00 | 2015-07-30T16:00:00 |
J1180 | Pre-Commissioning - LV System 400V | Not Started | Yes | 0,0 | 2015-07-31T08:00:00 | 2015-08-29T16:00:00 |
J1190 | Ready for Energizing - LV System 400V | Not Started | No | 0,0 | 2015-08-30T08:00:00 | 2015-08-30T08:00:00 |
307641 | FIELD CABLING | |||||
J2210 | Erection - Field Cabling (1M nach Kabeltrassen - ROHRBR�CKENau�en MIG), kabeltrassen innen | Not Started | Yes | 0,0 | 2015-01-24T12:00:00 | 2015-03-02T16:00:00 |
J2220 | Pre-Commissioning - Field Cabling | Not Started | No | 0,0 | 2015-03-03T08:00:00 | 2015-05-16T16:00:00 |
307642 | MV SYSTEM 6.6kV | |||||
J1070 | Erection - MV System 6.6kV | Not Started | Yes | 0,0 | 2015-04-02T08:00:00 | 2015-05-31T16:00:00 |
J1080 | Pre-Commissioning - MV System 6.6kV | Not Started | Yes | 0,0 | 2015-06-01T08:00:00 | 2015-06-30T16:00:00 |
J1090 | Ready for Energizing - MV System 6.6kV | Not Started | No | 0,0 | 2015-07-01T08:00:00 | 2015-07-01T08:00:00 |
307643 | LV TRAFOS | |||||
J1270 | Erection - LV Trafos | Not Started | Yes | 0,0 | 2015-03-03T08:00:00 | 2015-04-01T16:00:00 |
J1280 | Pre-Commissioning - LV Trafos | Not Started | Yes | 0,0 | 2015-04-02T08:00:00 | 2015-04-22T16:00:00 |
J1290 | Ready for Energizing - LV Trafos | Not Started | No | 0,0 | 2015-04-23T08:00:00 | 2015-04-23T08:00:00 |
307644 | FREQUENCY INVERTER | |||||
J1370 | Erection - Frequency Inverter | Not Started | Yes | 0,0 | 2015-02-01T08:00:00 | 2015-02-14T16:00:00 |
J1380 | Pre-Commissioning - Frequency Inverter | Not Started | No | 0,0 | 2015-02-15T08:00:00 | 2015-02-28T16:00:00 |
307645 | BATTERY SYSTEM 220V DC | |||||
J1470 | Erection - Battery System 220V DC | Not Started | Yes | 0,0 | 2015-05-02T08:00:00 | 2015-06-30T16:00:00 |
J1480 | Pre-Commissioning - Battery System 220V DC | Not Started | Yes | 0,0 | 2015-07-01T08:00:00 | 2015-07-30T16:00:00 |
J1490 | Ready for Energizing - Battery System 220V DC | Not Started | No | 0,0 | 2015-07-31T08:00:00 | 2015-07-31T08:00:00 |
307646 | 430 - LP/FP FLARE SYSTEM | |||||
M4131708 | Mechanical Completion - System 430 | Not Started | Yes | 0,0 | 2015-09-06T16:00:00 | 2015-09-06T16:00:00 |
307647 | Civil & Structural | |||||
307648 | Piping | |||||
M4131702 | Piping - LP/FP Flare system | Not Started | No | 0,0 | 2015-03-02T08:00:00 | 2015-06-07T16:00:00 |
M4131709 | Hydrotest | Not Started | Yes | 0,0 | 2015-09-01T08:00:00 | 2015-09-06T16:00:00 |
M4131701 | Prefabrication | Not Started | Yes | 0,0 | 2015-01-01T08:00:00 | 2015-03-01T16:00:00 |
307649 | Electrical | |||||
M4131704 | Electrical - LP/FP Flare system | Not Started | Yes | 0,0 | 2015-07-18T08:00:00 | 2015-09-06T16:00:00 |
307650 | Instrumentation & Telecomm | |||||
M4131705 | Instrumentation & Telecomm - LP/FP Flare system | Not Started | Yes | 0,0 | 2015-07-18T08:00:00 | 2015-09-06T16:00:00 |
307651 | Paiting & Insulation | |||||
M4131706 | Paiting & Insulation - LP/FP Flare system | Not Started | No | 0,0 | 2015-09-07T08:00:00 | 2015-10-04T16:00:00 |
307652 | Pre-commissioning | |||||
M4131707 | Pre-commissioning - LP/FP Flare system | Not Started | No | 0,0 | 2015-09-07T08:00:00 | 2015-10-04T16:00:00 |
307653 | Mechanical / Eq | |||||
M4131703 | Mechanical / Equipment - LP/FP Flare system | Not Started | Yes | 0,0 | 2015-06-02T08:00:00 | 2015-08-31T16:00:00 |
307654 | 420 - CHEMICAL INJECTION SYSTEM | |||||
M4131608 | Mechanical Completion - System 420 | Not Started | Yes | 0,0 | 2015-08-16T16:00:00 | 2015-08-16T16:00:00 |
307655 | Civil & Structural | |||||
307656 | Piping | |||||
M4131602 | Piping - Chemical Injection System | Not Started | No | 0,0 | 2015-04-30T08:00:00 | 2015-07-29T16:00:00 |
M4131609 | Hydrotest | Not Started | Yes | 0,0 | 2015-08-11T08:00:00 | 2015-08-16T16:00:00 |
M4131601 | Prefabrication | Not Started | Yes | 0,0 | 2015-03-01T08:00:00 | 2015-04-29T16:00:00 |
307657 | Electrical | |||||
M4131604 | Elecrical - Chemical Injection System | Not Started | Yes | 0,0 | 2015-06-27T08:00:00 | 2015-08-06T16:00:00 |
307658 | Instrumentation & Telecomm | |||||
M4131605 | Instrumentation & Telecomm - Chemical Injection System | Not Started | No | 0,0 | 2015-06-27T08:00:00 | 2015-08-06T16:00:00 |
307659 | Paiting & Insulation | |||||
M4131606 | Paiting & Insulation - Chemical Injection System | Not Started | No | 0,0 | 2015-08-17T08:00:00 | 2015-08-30T16:00:00 |
307660 | Pre-commissioning | |||||
M4131607 | Pre-commissioning - Chemical Injection System | Not Started | No | 0,0 | 2015-08-17T08:00:00 | 2015-09-13T16:00:00 |
307661 | Mechanical / Eq | |||||
M4131603 | Mechanical / Equipment - Chemical Injection System | Not Started | Yes | 0,0 | 2015-05-12T08:00:00 | 2015-08-10T16:00:00 |
307662 | 660 - SEWAGE TREATMENT SYSTEM | |||||
M4133008 | Mechanical Completion - System 660 | Not Started | Yes | 0,0 | 2015-06-17T16:00:00 | 2015-06-17T16:00:00 |
307663 | Electrical | |||||
M4133004 | Electrical - Sewage Water System | Not Started | Yes | 0,0 | 2015-04-27T08:00:00 | 2015-06-17T16:00:00 |
307664 | Instrumentation & Telecomm | |||||
M4133005 | Instrumentation & Telecomm - Sewage Water System | Not Started | Yes | 0,0 | 2015-04-27T08:00:00 | 2015-06-17T16:00:00 |
307665 | Paiting & Insulation | |||||
M4133006 | Paiting & Insulation - Sewage Water System | Not Started | No | 0,0 | 2015-06-18T08:00:00 | 2015-07-01T16:00:00 |
307666 | Pre-commissioning | |||||
M4133007 | Pre-commissioning - Sewage Water System | Not Started | No | 0,0 | 2015-06-18T08:00:00 | 2015-07-15T16:00:00 |
307667 | Piping | |||||
M4133002 | Piping - Sewage Water System | Not Started | No | 0,0 | 2015-02-23T08:00:00 | 2015-05-24T16:00:00 |
M4133009 | Hydrotest | Not Started | Yes | 0,0 | 2015-06-11T08:00:00 | 2015-06-17T16:00:00 |
M4133001 | Prefabrication | Not Started | Yes | 0,0 | 2014-12-25T08:00:00 | 2015-02-22T16:00:00 |
307668 | Mechanical / Eq | |||||
M4133003 | Mechanical / Equipment - Sewage Water System | Not Started | Yes | 0,0 | 2015-03-12T08:00:00 | 2015-06-10T16:00:00 |
307669 | Civil & Structural | |||||
307670 | 110 - GAS WELL SYSTEM | |||||
M412201 | General leveling | Not Started | Yes | 0,0 | 2014-09-01T08:00:00 | 2014-10-01T16:00:00 |
M412202 | Fencing & Road | Not Started | Yes | 0,0 | 2014-10-02T08:00:00 | 2014-11-23T16:00:00 |
M412203 | Concrete Basement of Equipment | Not Started | No | 0,0 | 2014-11-24T08:00:00 | 2015-01-14T16:00:00 |
M412204 | Equipment Installation (Skid 1-3) | Not Started | Yes | 0,0 | 2015-06-23T08:00:00 | 2015-08-13T16:00:00 |
M412208 | Piping Interconnection | Not Started | Yes | 0,0 | 2015-06-23T08:00:00 | 2015-08-13T16:00:00 |
M412206 | Electrical (Skid 1-3) | Not Started | No | 0,0 | 2015-06-30T08:00:00 | 2015-08-15T16:00:00 |
M412207 | Instrumentation (Skid 1-3) | Not Started | No | 0,0 | 2015-06-30T08:00:00 | 2015-08-15T16:00:00 |
M412211 | Painting (Skid 1-3) | Not Started | No | 0,0 | 2015-08-22T08:00:00 | 2015-08-27T16:00:00 |
M412212 | Pre-commissioning (Skid 1-3) | Not Started | Yes | 0,0 | 2015-08-22T08:00:00 | 2015-09-17T16:00:00 |
M412214 | Equipment Installation (Skid 4-6) | Not Started | Yes | 0,0 | 2015-07-07T08:00:00 | 2015-08-27T16:00:00 |
M412216 | Electrical (Skid 4-6) | Not Started | Yes | 0,0 | 2015-07-14T08:00:00 | 2015-08-29T16:00:00 |
M412217 | Instrumentation (Skid 4-6) | Not Started | Yes | 0,0 | 2015-07-14T08:00:00 | 2015-08-29T16:00:00 |
M412218 | Painting (Skid 4-6) | Not Started | Yes | 0,0 | 2015-08-30T08:00:00 | 2015-09-05T16:00:00 |
M412219 | Pre-commissioning (Skid 4-6) | Not Started | Yes | 0,0 | 2015-09-06T08:00:00 | 2015-10-03T16:00:00 |
M412224 | Equipment Installation (Skid 7-9) | Not Started | Yes | 0,0 | 2015-08-04T08:00:00 | 2015-09-24T16:00:00 |
M412226 | Electrical (Skid 7-9) | Not Started | Yes | 0,0 | 2015-08-11T08:00:00 | 2015-09-26T16:00:00 |
M412227 | Instrumentation (Skid 7-9) | Not Started | Yes | 0,0 | 2015-08-11T08:00:00 | 2015-09-26T16:00:00 |
M412228 | Painting (Skid 7-9) | Not Started | Yes | 0,0 | 2015-09-27T08:00:00 | 2015-10-03T16:00:00 |
M412229 | Pre-commissioning (Skid 7-9) | Not Started | Yes | 0,0 | 2015-10-04T08:00:00 | 2015-10-31T16:00:00 |
M412213 | Mechanical Completion - System 110 (Skid 1-3) | Not Started | No | 0,0 | 2015-08-20T16:00:00 | 2015-08-20T16:00:00 |
M412220 | Mechanical Completion - System 110 (Skid 4-6) | Not Started | No | 0,0 | 2015-08-29T16:00:00 | 2015-08-29T16:00:00 |
M412230 | Mechanical Completion - System 110 (Skid 7-9) | Not Started | Yes | 0,0 | 2015-09-26T16:00:00 | 2015-09-26T16:00:00 |
M412209 | Hydrotest | Not Started | Yes | 0,0 | 2015-08-15T08:00:00 | 2015-08-20T16:00:00 |
307671 | 560 - OPEN DRAINS SYSTEM | |||||
M4132508 | Mechanical Completion - System 560 | Not Started | Yes | 0,0 | 2015-04-18T16:00:00 | 2015-04-18T16:00:00 |
307672 | Mechanical / Eq | |||||
M4132503 | Mechanical / Equipment - Open Drains System | Not Started | Yes | 0,0 | 2015-01-11T08:00:00 | 2015-04-11T16:00:00 |
307673 | Electrical | |||||
M4132504 | Electrical - Open Drains System | Not Started | Yes | 0,0 | 2015-02-25T08:00:00 | 2015-04-18T16:00:00 |
307674 | Instrumentation & Telecomm | |||||
M4132505 | Instrumentation & Telecomm - Open Drains System | Not Started | Yes | 0,0 | 2015-02-25T08:00:00 | 2015-04-18T16:00:00 |
307675 | Paiting & Insulation | |||||
M4132506 | Paiting & Insulation - Open Drains System | Not Started | No | 0,0 | 2015-04-19T08:00:00 | 2015-05-02T16:00:00 |
307676 | Pre-commissioning | |||||
M4132507 | Pre-commissioning - Open Drains System | Not Started | No | 0,0 | 2015-04-19T08:00:00 | 2015-05-16T16:00:00 |
307677 | Civil & Structural | |||||
307678 | Piping | |||||
M4132502 | Piping - Open Drains System | Not Started | No | 0,0 | 2015-01-03T08:00:00 | 2015-04-02T16:00:00 |
M4132509 | Hydrotest | Not Started | Yes | 0,0 | 2015-04-12T08:00:00 | 2015-04-18T16:00:00 |
M4132500 | Prefabrication (60%) | Not Started | No | 0,0 | 2014-11-03T08:00:00 | 2015-01-01T16:00:00 |
M4132501 | Prefabrication (100%) | Not Started | No | 0,0 | 2014-12-25T08:00:00 | 2015-02-22T16:00:00 |
307679 | 270 - GAS EXPORT AND METERING SYSTEM | |||||
M4131108 | Mechanical Completion - System 270 | Not Started | Yes | 0,0 | 2015-09-20T16:00:00 | 2015-09-20T16:00:00 |
307680 | Civil & Structural | |||||
307681 | Paiting & Insulation | |||||
M4131106 | Paiting & Insulation - Gas Export and Metering System | Not Started | No | 0,0 | 2015-09-21T08:00:00 | 2015-10-11T16:00:00 |
307682 | Pre -commisiioining | |||||
M4131107 | Pre-commissioning - Gas Export and Metering System | Not Started | Yes | 0,0 | 2015-09-21T08:00:00 | 2015-10-18T16:00:00 |
307683 | Piping | |||||
M4131109 | Hydrotest | Not Started | Yes | 0,0 | 2015-09-15T08:00:00 | 2015-09-20T16:00:00 |
307684 | Electrical | |||||
M4131104 | Electrical - Gas Export and Metering System | Not Started | Yes | 0,0 | 2015-08-10T08:00:00 | 2015-09-20T16:00:00 |
307685 | Instrumentation & Telecomm | |||||
M4131105 | Instrumentation & Telecomm - Gas Export and Metering System | Not Started | Yes | 0,0 | 2015-08-10T08:00:00 | 2015-09-20T16:00:00 |
307686 | Mechanical / Eq | |||||
M4131103 | Mechanical / Equipment - Gas Export and Metering System | Not Started | Yes | 0,0 | 2015-06-16T08:00:00 | 2015-09-14T16:00:00 |
307687 | 480 - UTILITY MISCELLANEOUS SYSTEM | |||||
M4132208 | Mechanical Completion - System 480 | Not Started | Yes | 0,0 | 2015-09-13T16:00:00 | 2015-09-13T16:00:00 |
307688 | AMINE PIPING | |||||
307689 | GLYCOL PIPING | |||||
307690 | Paiting & insulation | |||||
M4132206 | Paiting & Insulation - Utility Miscellaneous System | Not Started | No | 0,0 | 2015-09-14T08:00:00 | 2015-09-27T16:00:00 |
307691 | Pre-commissioning | |||||
M4132207 | Pre-commissioning - Utility Miscellaneous System | Not Started | No | 0,0 | 2015-09-14T08:00:00 | 2015-09-20T16:00:00 |
307692 | Piping | |||||
M4132202 | Piping - Utility Miscellaneous System | Not Started | No | 0,0 | 2015-04-01T08:00:00 | 2015-06-30T16:00:00 |
M4132209 | Hydrotest | Not Started | Yes | 0,0 | 2015-09-08T08:00:00 | 2015-09-13T16:00:00 |
M4132201 | Prefabrication | Not Started | Yes | 0,0 | 2015-01-31T08:00:00 | 2015-03-31T16:00:00 |
307693 | Mechanical / Eq | |||||
M4132203 | Mechanical / Equipment - Utility Miscellaneous System | Not Started | Yes | 0,0 | 2015-06-30T08:00:00 | 2015-09-07T16:00:00 |
307694 | Instrumentation & Telecomm | |||||
M4132205 | Instrumentation & Telecom - Utility Miscellaneous System | Not Started | Yes | 0,0 | 2015-08-15T08:00:00 | 2015-09-13T16:00:00 |
307695 | Civil & Structural | |||||
307696 | Electrical | |||||
M4132204 | Electrical - Utility Miscellaneous System | Not Started | Yes | 0,0 | 2015-08-15T08:00:00 | 2015-09-13T16:00:00 |
307697 | 460 - METHANOL INJECTION SYSTEM | |||||
M4132008 | Mechanical Completion - System 460 | Not Started | Yes | 0,0 | 2015-09-13T16:00:00 | 2015-09-13T16:00:00 |
307698 | Pre-commissioning | |||||
M4132007 | Pre-commissioning - Methanol Injection System | Not Started | No | 0,0 | 2015-09-14T08:00:00 | 2015-10-04T16:00:00 |
307699 | Civil & Structural | |||||
307700 | Piping | |||||
M4132002 | Piping - Methanol Injection System | Not Started | No | 0,0 | 2015-02-16T08:00:00 | 2015-05-10T16:00:00 |
M4132009 | Hydrotest | Not Started | Yes | 0,0 | 2015-09-08T08:00:00 | 2015-09-13T16:00:00 |
M4132001 | Prefabrication | Not Started | Yes | 0,0 | 2014-12-18T08:00:00 | 2015-02-15T16:00:00 |
307701 | Instrumentation & Telecomm | |||||
M4132005 | Instrumentation & Telecomm - Methanol Injection System | Not Started | No | 0,0 | 2015-07-25T08:00:00 | 2015-09-07T16:00:00 |
307702 | Paiting & Insulation | |||||
M4132006 | Paiting & Insulation - Methanol Injection System | Not Started | No | 0,0 | 2015-09-14T08:00:00 | 2015-10-11T16:00:00 |
307703 | Electrical | |||||
M4132004 | Electrical - Methanol Injection System | Not Started | Yes | 0,0 | 2015-07-25T08:00:00 | 2015-09-07T16:00:00 |
307704 | Mechanical / Eq | |||||
M4132003 | Mechanical / Equipment - Methanol Injection System | Not Started | Yes | 0,0 | 2015-06-09T08:00:00 | 2015-09-07T16:00:00 |
307705 | 710 - FIRE WATER SYSTEM | |||||
M4133108 | Mechanical Completion - System 710 | Not Started | Yes | 0,0 | 2015-06-17T16:00:00 | 2015-06-17T16:00:00 |
307706 | Paiting & Insulation | |||||
M4133106 | Paiting & Insulation - Fire Water System | Not Started | No | 0,0 | 2015-06-18T08:00:00 | 2015-07-01T16:00:00 |
307707 | Civil & Structural | |||||
307708 | Piping | |||||
M4133102 | Piping - Fire Water System | Not Started | No | 0,0 | 2015-02-23T08:00:00 | 2015-05-24T16:00:00 |
M4133109 | Hydrotest | Not Started | Yes | 0,0 | 2015-06-11T08:00:00 | 2015-06-17T16:00:00 |
M4133101 | Prefabrication | Not Started | Yes | 0,0 | 2014-12-25T08:00:00 | 2015-02-22T16:00:00 |
307709 | Mechanical / Eq | |||||
M4133103 | Mechanical / Equipment - Fire Water System | Not Started | Yes | 0,0 | 2015-03-12T08:00:00 | 2015-06-10T16:00:00 |
307710 | Electrical | |||||
M4133104 | Electrical - Fire Water System | Not Started | Yes | 0,0 | 2015-04-27T08:00:00 | 2015-06-17T16:00:00 |
307711 | Instrumentation & Telecomm | |||||
M4133105 | Instrumentation & Telecomm - Fire Water System | Not Started | Yes | 0,0 | 2015-04-27T08:00:00 | 2015-06-17T16:00:00 |
307712 | Pre-commissioning | |||||
M4133107 | Pre-commissioning - Fire Water System | Not Started | No | 0,0 | 2015-06-18T08:00:00 | 2015-07-15T16:00:00 |
307713 | 500 - INDUSTRIAL WATER SYSTEM | |||||
M4132308 | Mechanical Completion - System 500 | Not Started | Yes | 0,0 | 2015-06-21T16:00:00 | 2015-06-21T16:00:00 |
307714 | Pre-commissioning | |||||
M4132307 | Pre-Commissioning - Aquifer / Plant Water System | Not Started | Yes | 0,0 | 2015-06-22T08:00:00 | 2015-07-03T16:00:00 |
M4132310 | System Commissioning - Aquifer / Plant Water System | Not Started | No | 0,0 | 2015-06-22T08:00:00 | 2015-07-29T12:00:00 |
307715 | Electrical | |||||
M4132304 | Electrical - Industrial Water System | Not Started | Yes | 0,0 | 2015-05-09T08:00:00 | 2015-06-21T16:00:00 |
307716 | Civil & Structural | |||||
307717 | Piping | |||||
M4132302 | Piping - Industrial Water System | Not Started | No | 0,0 | 2015-03-25T08:00:00 | 2015-06-09T16:00:00 |
M4132309 | Hydrotest | Not Started | Yes | 0,0 | 2015-06-16T08:00:00 | 2015-06-21T16:00:00 |
M4132301 | Prefabrication | Not Started | Yes | 0,0 | 2015-01-24T08:00:00 | 2015-03-24T16:00:00 |
307718 | Mechanical / Eq | |||||
M4132303 | Mechanical / Equipment - Industrial Water System | Not Started | Yes | 0,0 | 2015-03-31T08:00:00 | 2015-06-15T16:00:00 |
307719 | Instrumentation & Telecomm | |||||
M4132305 | Instrumentation & Telecom - Industrial Water System | Not Started | Yes | 0,0 | 2015-05-09T08:00:00 | 2015-06-21T16:00:00 |
307720 | Paiting & Insulation | |||||
M4132306 | Paiting & Insulation - Industrial Water System | Not Started | No | 0,0 | 2015-06-22T08:00:00 | 2015-07-05T16:00:00 |
307721 | 240 - GAS TREATMENT SYSTEM | |||||
M413808 | Mechanical Completion - System 240 | Not Started | Yes | 0,0 | 2015-08-02T16:00:00 | 2015-08-02T16:00:00 |
307722 | Civil & Structural | |||||
307723 | Piping | |||||
M413802 | Piping - Gas Treatment System | Not Started | No | 0,0 | 2015-01-26T08:00:00 | 2015-04-26T16:00:00 |
M413809 | Hydrotest | Not Started | Yes | 0,0 | 2015-07-28T08:00:00 | 2015-08-02T16:00:00 |
M413800 | Prefabrication (80%) | Not Started | Yes | 0,0 | 2014-11-27T08:00:00 | 2015-01-25T16:00:00 |
M413801 | Prefabrication (100%) | Not Started | No | 0,0 | 2014-12-25T08:00:00 | 2015-02-22T16:00:00 |
307724 | Mechanical / Eq | |||||
M413803 | Mechanical / Equipment - Gas Treatment System | Not Started | Yes | 0,0 | 2015-04-28T08:00:00 | 2015-07-27T16:00:00 |
307725 | Electrical | |||||
M413804 | Electrical - Gas Treatment System | Not Started | Yes | 0,0 | 2015-06-15T08:00:00 | 2015-08-02T16:00:00 |
307726 | Paiting & Insulation | |||||
M413806 | Paiting & Insulation - Gas Treatment System | Not Started | No | 0,0 | 2015-08-03T08:00:00 | 2015-08-30T16:00:00 |
307727 | Instrumentation & Telecomm | |||||
M413805 | Instrumentation & Telecomm - Gas Treatment System | Not Started | Yes | 0,0 | 2015-06-15T08:00:00 | 2015-08-02T16:00:00 |
307728 | Pre-commissioning | |||||
M413807 | Pre-commissioning - Gas Treatment System | Not Started | No | 0,0 | 2015-08-03T08:00:00 | 2015-09-13T16:00:00 |
307729 | 450 - FUEL GAS SYSTEM | |||||
M4131908 | Mechanical Completion - System 450 | Not Started | Yes | 0,0 | 2015-09-01T16:00:00 | 2015-09-01T16:00:00 |
307730 | Civil & Structural | |||||
307731 | Piping | |||||
M4131902 | Piping - Fuel Gas Supply System | Not Started | No | 0,0 | 2015-03-18T08:00:00 | 2015-06-09T16:00:00 |
M4131909 | Hydrotest | Not Started | Yes | 0,0 | 2015-08-27T08:00:00 | 2015-09-01T16:00:00 |
M4131901 | Prefabrication | Not Started | Yes | 0,0 | 2015-01-17T08:00:00 | 2015-03-17T16:00:00 |
307732 | Electrical | |||||
M4131904 | Electrical - Fuel Gas Supply System | Not Started | Yes | 0,0 | 2015-07-16T08:00:00 | 2015-08-26T16:00:00 |
307733 | Instrumentation & Telecomm | |||||
M4131905 | Instrumentation & Telecomm - Fuel Gas Supply System | Not Started | No | 0,0 | 2015-07-16T08:00:00 | 2015-08-26T16:00:00 |
307734 | Paiting & Insulation | |||||
M4131906 | Paiting & Insulation - Fuel Gas Supply System | Not Started | No | 0,0 | 2015-09-02T08:00:00 | 2015-09-15T16:00:00 |
307735 | Pre -commissioning | |||||
M4131907 | Pre-Commissioning - Fuel Gas Supply System | Not Started | No | 0,0 | 2015-09-02T08:00:00 | 2015-09-29T16:00:00 |
307736 | Mechanical / Eq | |||||
M4131903 | Mechanical / Equipment - Fuel Gas Supply System | Not Started | Yes | 0,0 | 2015-07-16T08:00:00 | 2015-08-26T16:00:00 |
307737 | 250 - GAS CONDITIONING (DEHYDRATION) SYSTEM | |||||
M413908 | Mechanical Completion - System 250A | Not Started | Yes | 0,0 | 2015-09-22T16:00:00 | 2015-09-22T16:00:00 |
307738 | Piping | |||||
M413902 | Piping - Gas Conditioning (Dehydration) System | Not Started | No | 0,0 | 2015-05-14T08:00:00 | 2015-08-12T16:00:00 |
M413909 | Hydrotest | Not Started | Yes | 0,0 | 2015-09-16T08:00:00 | 2015-09-22T16:00:00 |
M413901 | Prefabrication | Not Started | Yes | 0,0 | 2015-03-15T08:00:00 | 2015-05-13T16:00:00 |
307739 | Civil & Structural | |||||
307740 | Pre-commissioning | |||||
M413907 | Pre-commissioning - Gas Conditioning (Dehydration) System | Not Started | Yes | 0,0 | 2015-09-23T08:00:00 | 2015-11-03T16:00:00 |
307741 | Mechanical / Eq | |||||
M413903 | Mechanical / Equipment - Gas Conditioning (Dehydration) System | Not Started | Yes | 0,0 | 2015-07-22T08:00:00 | 2015-09-15T16:00:00 |
307742 | Electrical | |||||
M413904 | Electrical - Gas Conditioning (Dehydration) System | Not Started | Yes | 0,0 | 2015-08-11T08:00:00 | 2015-09-22T16:00:00 |
307743 | Instrumentation & Telecomm | |||||
M413905 | Instrumentation & Telecomm - Gas Conditioning (Dehydration) System | Not Started | Yes | 0,0 | 2015-08-11T08:00:00 | 2015-09-22T16:00:00 |
307744 | Paiting & Insulation | |||||
M413906 | Paiting & Insulation - Gas Conditioning (Dehydration) System | Not Started | No | 0,0 | 2015-09-23T08:00:00 | 2015-10-20T16:00:00 |
307745 | 250 - GAS CONDITIONING (DEW POINTING) SYSTEM | |||||
M4131008 | Mechanical Completion - System 250B | Not Started | Yes | 0,0 | 2015-09-22T16:00:00 | 2015-09-22T16:00:00 |
307746 | Piping | |||||
M4131002 | Piping - Gas Conditioning (Dew Pointing) System | Not Started | No | 0,0 | 2015-05-14T08:00:00 | 2015-08-12T16:00:00 |
M4131009 | Hydrotest | Not Started | Yes | 0,0 | 2015-09-16T08:00:00 | 2015-09-22T16:00:00 |
M4131001 | Prefabrication | Not Started | Yes | 0,0 | 2015-03-15T08:00:00 | 2015-05-13T16:00:00 |
307747 | Electrical | |||||
M4131004 | Electrical - Gas Conditioning (Dew Pointing) System | Not Started | Yes | 0,0 | 2015-08-11T08:00:00 | 2015-09-22T16:00:00 |
307748 | Instrumentation & Telecomm | |||||
M4131005 | Instrumentation & Telecomm - Gas Conditioning (Dew Pointing) System | Not Started | Yes | 0,0 | 2015-08-11T08:00:00 | 2015-09-22T16:00:00 |
307749 | Paiting & Insulation | |||||
M4131006 | Paiting & Insulation - Gas Conditioning (Dew Pointing) System | Not Started | No | 0,0 | 2015-09-23T08:00:00 | 2015-10-20T16:00:00 |
307750 | Pre-commissioning | |||||
M4131007 | Pre-commissioning - Gas Conditioning (Dew Pointing) System | Not Started | No | 0,0 | 2015-09-23T08:00:00 | 2015-11-03T16:00:00 |
307751 | Civil & Structural | |||||
307752 | Mechanical /eq | |||||
M4131003 | Mechanical / Equipment - Gas Conditioning (Dew Pointing) System | Not Started | Yes | 0,0 | 2015-07-22T08:00:00 | 2015-09-15T16:00:00 |
307753 | 800 - MAIN POWER GENERATION SYSTEM | |||||
M4133208 | Mechanical Completion - System 800 | Not Started | Yes | 0,0 | 2015-12-06T16:00:00 | 2015-12-06T16:00:00 |
307754 | Piping | |||||
M4133202 | Piping - Gas Turbine System | Not Started | No | 0,0 | 2015-02-23T08:00:00 | 2015-05-11T16:00:00 |
M4133209 | Hydrotest | Not Started | Yes | 0,0 | 2015-11-30T08:00:00 | 2015-12-06T16:00:00 |
M4133201 | Prefabrication | Not Started | Yes | 0,0 | 2014-12-25T08:00:00 | 2015-02-22T16:00:00 |
307755 | Paiting & Insulation | |||||
M4133206 | Paiting & Insulation - Gas Turbine System | Not Started | No | 0,0 | 2015-12-07T08:00:00 | 2015-12-20T16:00:00 |
307756 | Pre-commissioning | |||||
M4133207 | Pre-commissioning - Gas Turbine System | Not Started | Yes | 0,0 | 2015-12-07T08:00:00 | 2016-01-03T16:00:00 |
307757 | Civil & Structural | |||||
307758 | Mechanical / Eq | |||||
M4133203 | Mechanical / Equipment - Gas Turbine System | Not Started | Yes | 0,0 | 2015-09-19T08:00:00 | 2015-11-29T16:00:00 |
307759 | Electrical | |||||
M4133204 | Electrical - Gas Turbine System | Not Started | Yes | 0,0 | 2015-10-28T08:00:00 | 2015-12-06T16:00:00 |
307760 | Instrumentation & Telecomm | |||||
M4133205 | Instrumentation & Telecomm - Gas Turbine System | Not Started | Yes | 0,0 | 2015-10-28T08:00:00 | 2015-12-06T16:00:00 |
307761 | 280 - GAS SWEETENING (AMINE) SYSTEM | |||||
M4131208 | Mechanical Completion - System 280 | Not Started | Yes | 0,0 | 2015-09-21T16:00:00 | 2015-09-21T16:00:00 |
307762 | Piping | |||||
M4131202 | Piping - Gas Sweetening (Amine) System | Not Started | No | 0,0 | 2015-01-03T08:00:00 | 2015-04-23T16:00:00 |
M4131209 | Hydrotest | Not Started | Yes | 0,0 | 2015-09-15T08:00:00 | 2015-09-21T16:00:00 |
M4131201 | Prefabrication | Not Started | No | 0,0 | 2014-11-03T08:00:00 | 2015-01-01T16:00:00 |
307763 | Civil & Structural | |||||
307764 | Electrical | |||||
M4131204 | Electrical - Gas Sweetening (Amine) System | Not Started | Yes | 0,0 | 2015-07-07T08:00:00 | 2015-09-21T16:00:00 |
307765 | Instrumentation & Telecomm | |||||
M4131205 | Instrumentation & Telecomm - Gas Sweetening (Amine) System | Not Started | Yes | 0,0 | 2015-07-07T08:00:00 | 2015-09-21T16:00:00 |
307766 | Paiting & Insulation | |||||
M4131206 | Paiting & Insulation - Gas Sweetening (Amine) System | Not Started | No | 0,0 | 2015-09-22T08:00:00 | 2015-12-14T16:00:00 |
307767 | Pre-commissioining | |||||
M4131207 | Pre-commissioning - Gas Sweetening (Amine) System | Not Started | Yes | 0,0 | 2015-09-22T08:00:00 | 2015-11-02T16:00:00 |
307768 | Mechanical / Eq | |||||
M4131203 | Mechanical / Equipment - Gas Sweetening (Amine) System | Not Started | Yes | 0,0 | 2015-06-16T08:00:00 | 2015-09-14T16:00:00 |
307769 | 620 - DIESEL OIL SYSTEM | |||||
M4132708 | Mechanical Completion - System 620 | Not Started | Yes | 0,0 | 2015-04-18T16:00:00 | 2015-04-18T16:00:00 |
307770 | Electrical | |||||
M4132704 | Electrical - Diesel Oil System | Not Started | Yes | 0,0 | 2015-02-25T08:00:00 | 2015-04-18T16:00:00 |
307771 | Instrumentation & Telecomm | |||||
M4132705 | Instrumentation & Telecomm - Diesel Oil System | Not Started | Yes | 0,0 | 2015-02-25T08:00:00 | 2015-04-18T16:00:00 |
307772 | Pre-commissioning | |||||
M4132707 | Pre-commissioning - Diesel Oil System | Not Started | No | 0,0 | 2015-04-19T08:00:00 | 2015-05-16T16:00:00 |
307773 | Civil & Structural | |||||
307774 | Paiting & Insulation | |||||
M4132706 | Paiting & Insulation - Diesel Oil System | Not Started | No | 0,0 | 2015-04-19T08:00:00 | 2015-05-02T16:00:00 |
307775 | Piping | |||||
M4132702 | Piping - Diesel Oil System | Not Started | No | 0,0 | 2015-01-03T08:00:00 | 2015-04-02T16:00:00 |
M4132709 | Hydrotest | Not Started | Yes | 0,0 | 2015-04-12T08:00:00 | 2015-04-18T16:00:00 |
M4132700 | Prefabrication (60%) | Not Started | No | 0,0 | 2014-11-03T08:00:00 | 2015-01-01T16:00:00 |
M4132701 | Prefabrication (100%) | Not Started | No | 0,0 | 2014-12-25T08:00:00 | 2015-02-22T16:00:00 |
307776 | Mechanical / Eq | |||||
M4132703 | Mechanical / Equipment - Diesel Oil System | Not Started | Yes | 0,0 | 2015-01-11T08:00:00 | 2015-04-11T16:00:00 |
307777 | 410 - HEATING MEDIUM SYSTEM | |||||
M4131508 | Mechanical Completion - System 410 | Not Started | Yes | 0,0 | 2015-07-26T16:00:00 | 2015-07-26T16:00:00 |
307778 | Civil & Structural | |||||
307779 | Piping | |||||
M4131502 | Piping - Heating Medium System | Not Started | No | 0,0 | 2015-04-08T08:00:00 | 2015-07-07T16:00:00 |
M4131509 | Hydrotest | Not Started | Yes | 0,0 | 2015-07-21T08:00:00 | 2015-07-26T16:00:00 |
M4131501 | Prefabrication | Not Started | Yes | 0,0 | 2015-02-07T08:00:00 | 2015-04-07T16:00:00 |
307780 | Electrical | |||||
M4131504 | Electrical - Heating Medium System | Not Started | Yes | 0,0 | 2015-06-16T08:00:00 | 2015-07-26T16:00:00 |
307781 | Instrumentation & Telecomm | |||||
M4131505 | Instrumentation & Telecomm - Heating Medium System | Not Started | Yes | 0,0 | 2015-06-16T08:00:00 | 2015-07-26T16:00:00 |
307782 | Paiting & Insulation | |||||
M4131506 | Paiting & Insulation - Heating Medium System | Not Started | No | 0,0 | 2015-07-27T08:00:00 | 2015-08-09T16:00:00 |
307783 | Pre-commissioning | |||||
M4131507 | Pre-commissioning - Heating Medium System | Not Started | No | 0,0 | 2015-07-27T08:00:00 | 2015-08-16T16:00:00 |
307784 | Mechanical / Eq | |||||
M4131503 | Mechanical / Equipment - Heating Medium System | Not Started | Yes | 0,0 | 2015-05-12T08:00:00 | 2015-07-20T16:00:00 |
307785 | 200 - CONDENSATE STABILIZATION SYSTEM | |||||
M413207 | Mechanical Completion - System 200B | Not Started | Yes | 0,0 | 2015-07-20T16:00:00 | 2015-07-20T16:00:00 |
307786 | Piping | |||||
M413202 | Piping - Condensate Stabilisation System | Not Started | Yes | 0,0 | 2014-11-20T08:00:00 | 2015-02-04T16:00:00 |
M413209 | Hydrotest | Not Started | No | 0,0 | 2015-02-05T08:00:00 | 2015-02-11T16:00:00 |
307787 | Mechanical / Equipment | |||||
M413203 | Mechanical / Equipment - Condensate Stabilisation System | Not Started | Yes | 0,0 | 2015-04-28T08:00:00 | 2015-07-20T16:00:00 |
307788 | Electrical & Instrumentation & Telecommunication | |||||
M413204 | Electrical & Instrumentation & Telecomm - Condensate Stabilisation System | Not Started | Yes | 0,0 | 2015-04-28T08:00:00 | 2015-07-20T16:00:00 |
307789 | Pre-Commissioning | |||||
M413206 | Pre-commissioning - Condensate Stabilisation System | Not Started | No | 0,0 | 2015-07-21T08:00:00 | 2015-08-17T16:00:00 |
307790 | Civil | |||||
307791 | Painting & Insulation | |||||
M413205 | Paiting & Insulation - Condensate Stabilisation System | Not Started | No | 0,0 | 2015-07-21T08:00:00 | 2015-08-03T16:00:00 |
307792 | 200 - WATER / CONDENSATE SEPARATOR SYSTEM | |||||
M413307 | Mechanical Completion - System 200A | Not Started | Yes | 0,0 | 2015-07-20T16:00:00 | 2015-07-20T16:00:00 |
307793 | Civil | |||||
307794 | Mechanical / Equipment | |||||
M413303 | Mechanical / Equipment - Water / Condensate Separator System | Not Started | Yes | 0,0 | 2015-04-28T08:00:00 | 2015-07-20T16:00:00 |
307795 | Piping | |||||
M413302 | Piping - Water / Condensate Separator System | Not Started | Yes | 0,0 | 2015-03-05T08:00:00 | 2015-05-20T16:00:00 |
M413312 | Hydrotest | Not Started | No | 0,0 | 2015-05-21T08:00:00 | 2015-05-27T16:00:00 |
M413301 | Pre-Fabrication 100% in MIG Workshop System 200 | Not Started | Yes | 0,0 | 2014-12-25T08:00:00 | 2015-03-04T16:00:00 |
307796 | Electrical & Instrumentation & Telecommunication | |||||
M413304 | Electrical & Instrumentation & Telecomm - Water / Condensate Separator System | Not Started | Yes | 0,0 | 2015-04-28T08:00:00 | 2015-07-20T16:00:00 |
307797 | Pre-Commissioning | |||||
M413306 | Pre-commissioning - Water / Condensate Separator System | Not Started | No | 0,0 | 2015-07-21T08:00:00 | 2015-08-17T16:00:00 |
307798 | Painting & Insulation | |||||
M413305 | Paiting & Insulation - Water / Condensate Separator System | Not Started | No | 0,0 | 2015-07-21T08:00:00 | 2015-08-03T16:00:00 |
307799 | COMMON CPF | |||||
307800 | General Levelling | |||||
M413101 | General Levelling | Not Started | Yes | 0,0 | 2014-06-01T08:00:00 | 2014-07-05T16:00:00 |
307801 | Fencing & Roads | |||||
M413102 | Fencing & Roads | Not Started | No | 0,0 | 2014-07-06T08:00:00 | 2015-03-18T16:00:00 |
307802 | Equipment Fundaments | |||||
M413100 | Fundaments of all CPF system | Not Started | Yes | 0,0 | 2014-07-06T08:00:00 | 2015-01-10T16:00:00 |
307803 | Concrete Basement | |||||
M413103 | Concrete Basement (410, 480, 570) | Not Started | No | 0,0 | 2014-07-06T08:00:00 | 2015-05-30T16:00:00 |
307804 | Pipe rack | |||||
M413104 | Civil works for Pipe Rack and Pipe rack | Not Started | No | 0,0 | 2014-07-06T08:00:00 | 2015-01-01T16:00:00 |
307805 | Evaporation Pond | |||||
307806 | PROCUREMENT | |||||
307807 | CIVIL, STRUCTURAL STEEL | |||||
307808 | 430 - LP/FP FLARE SYSTEM | |||||
307809 | LP/FP FLARE SKID | |||||
F5600 | Purchasing - Flare System | Not Started | Yes | 0,0 | 2014-05-24T08:00:00 | 2014-07-04T16:00:00 |
F5610 | PO placed - Flare System | Not Started | Yes | 0,0 | 2014-07-04T16:00:00 | 2014-07-04T16:00:00 |
F5630 | Ready for Shipment - Flare System | Not Started | Yes | 0,0 | 2015-04-10T16:00:00 | 2015-04-10T16:00:00 |
F5620 | Delievery Time - Flare System | Not Started | Yes | 0,0 | 2014-07-05T08:00:00 | 2015-04-10T16:00:00 |
M6160 | Shipment - Flare System | Not Started | Yes | 0,0 | 2015-04-18T08:00:00 | 2015-06-01T16:00:00 |
M6170 | At site - Flare System | Not Started | Yes | 0,0 | 2015-06-01T16:00:00 | 2015-06-01T16:00:00 |
F5635 | Transport to Port of Export - Flare System | Not Started | Yes | 0,0 | 2015-04-11T08:00:00 | 2015-04-17T16:00:00 |
307810 | FLARE SYSTEM CONNECTION PIPING | |||||
J2930 | Purchasing - Flare interconnecting piping | Not Started | Yes | 0,0 | 2014-05-29T08:00:00 | 2014-08-06T16:00:00 |
J2940 | First PO placed - Flare interconnecting piping | Not Started | Yes | 0,0 | 2014-06-13T08:00:00 | 2014-06-13T08:00:00 |
J2950 | Delivery Time - Flare interconnecting piping | Not Started | Yes | 0,0 | 2014-06-13T08:00:00 | 2014-11-09T16:00:00 |
J2970 | Ready for Shipment - Flare interconnecting piping | Not Started | Yes | 0,0 | 2014-11-10T08:00:00 | 2014-11-10T08:00:00 |
M6040 | Shipment - Flare interconnecting piping | Not Started | Yes | 0,0 | 2014-11-17T08:00:00 | 2014-12-31T16:00:00 |
M6050 | At site - Flare interconnecting piping | Not Started | Yes | 0,0 | 2014-12-31T16:00:00 | 2014-12-31T16:00:00 |
J2975 | Transport to Port of Export - Flare interconnecting piping | Not Started | Yes | 0,0 | 2014-11-10T08:00:00 | 2014-11-16T16:00:00 |
307811 | 440 - PRODUCED WATER TREATMENT SYSTEM | |||||
307812 | PRODUCED WATER TREATMENT SKID | |||||
F4950 | Purchasing - Produced Water Treatment System | Not Started | Yes | 0,0 | 2014-05-03T08:00:00 | 2014-06-13T16:00:00 |
F4960 | PO placed - Produced Water Treatment System | Not Started | Yes | 0,0 | 2014-06-13T16:00:00 | 2014-06-13T16:00:00 |
F4980 | Ready for Shipment - Produced Water Treatment System | Not Started | Yes | 0,0 | 2015-06-13T16:00:00 | 2015-06-13T16:00:00 |
F4970 | Delievery Time - Produced Water Treatment System | Not Started | Yes | 0,0 | 2014-06-14T08:00:00 | 2015-06-13T16:00:00 |
M4990 | Shipment - Produced Water Treatment System | Not Started | Yes | 0,0 | 2015-06-21T08:00:00 | 2015-08-04T16:00:00 |
M5000 | At site - Produced Water Treatment System | Not Started | Yes | 0,0 | 2015-08-04T16:00:00 | 2015-08-04T16:00:00 |
F4985 | Transport to Port of Export - Produced Water Treatment System | Not Started | Yes | 0,0 | 2015-06-14T08:00:00 | 2015-06-20T16:00:00 |
J5170 | Purchasing - Produced water treatment system piping | Not Started | Yes | 0,0 | 2014-05-22T08:00:00 | 2014-07-30T16:00:00 |
J5180 | First PO placed - Produced water treatment system piping | Not Started | Yes | 0,0 | 2014-06-06T08:00:00 | 2014-06-06T08:00:00 |
J5190 | Delivery Time - Produced water treatment system piping | Not Started | Yes | 0,0 | 2014-06-06T08:00:00 | 2015-01-01T16:00:00 |
J5210 | Ready for Shipment - Produced water treatment system piping | Not Started | Yes | 0,0 | 2015-01-02T08:00:00 | 2015-01-02T08:00:00 |
M5225 | Shipment - Produced water piping | Not Started | Yes | 0,0 | 2015-01-09T08:00:00 | 2015-02-22T16:00:00 |
M5235 | At site - Produced water piping | Not Started | No | 0,0 | 2015-02-22T16:00:00 | 2015-02-22T16:00:00 |
J5215 | Transport to Port of Export - Produced water treatment system piping | Not Started | Yes | 0,0 | 2015-01-02T08:00:00 | 2015-01-08T16:00:00 |
307813 | EVAPORATION POND | |||||
M3401 | Purchasing - Evaporation Pond | Not Started | Yes | 0,0 | 2014-05-17T08:00:00 | 2014-06-15T16:00:00 |
M3402 | PO placed - Evaporation Pond | Not Started | Yes | 0,0 | 2014-06-15T16:00:00 | 2014-06-15T16:00:00 |
M3404 | Ready for Shipment - Evaporation Pond | Not Started | Yes | 0,0 | 2014-10-16T16:00:00 | 2014-10-16T16:00:00 |
M3403 | Delievery Time - Evaporation Pond | Not Started | Yes | 0,0 | 2014-06-16T08:00:00 | 2014-10-16T16:00:00 |
M3405 | Shipment - Evaporation Pond | Not Started | Yes | 0,0 | 2014-10-18T08:00:00 | 2014-11-13T16:00:00 |
M3406 | At site - Evaporation Pond | Not Started | No | 0,0 | 2014-11-13T16:00:00 | 2014-11-13T16:00:00 |
307814 | PRODUCED WATER TREATMENT SYSTEM PIPING | |||||
J3030 | Purchasing - Produced water interconnecting piping | Not Started | Yes | 0,0 | 2014-06-21T08:00:00 | 2014-08-29T16:00:00 |
J3040 | First PO placed - Produced water interconnecting piping | Not Started | Yes | 0,0 | 2014-07-06T08:00:00 | 2014-07-06T08:00:00 |
J3050 | Delivery Time - Produced water interconnecting piping | Not Started | Yes | 0,0 | 2014-07-06T08:00:00 | 2014-12-02T16:00:00 |
J3070 | Ready for Shipment - Produced water interconnecting piping | Not Started | Yes | 0,0 | 2014-12-03T08:00:00 | 2014-12-03T08:00:00 |
M6060 | Shipment - Produced water interconnecting piping | Not Started | Yes | 0,0 | 2014-12-10T08:00:00 | 2015-01-23T16:00:00 |
M6070 | At site - Produced water interconnecting piping | Not Started | Yes | 0,0 | 2015-01-23T16:00:00 | 2015-01-23T16:00:00 |
J3075 | Transport to Port of Export - Produced water interconnecting piping | Not Started | Yes | 0,0 | 2014-12-03T08:00:00 | 2014-12-09T16:00:00 |
307815 | 440 - EVAPORATION POND | |||||
307816 | GENERAL | |||||
307817 | 420 - CHEMICAL INJECTION SYSTEM | |||||
307818 | CHEMICAL INJECTION PIPING | |||||
J2830 | Purchasing - Chemical injection interconnecting piping | Not Started | Yes | 0,0 | 2014-07-19T08:00:00 | 2014-09-26T16:00:00 |
J2840 | First PO placed - Chemical injection interconnecting piping | Not Started | Yes | 0,0 | 2014-08-03T08:00:00 | 2014-08-03T08:00:00 |
J2850 | Delivery Time - Chemical injection interconnecting piping | Not Started | Yes | 0,0 | 2014-08-03T08:00:00 | 2014-12-30T16:00:00 |
J2870 | Ready for Shipment - Chemical injection interconnecting piping | Not Started | Yes | 0,0 | 2014-12-31T08:00:00 | 2014-12-31T08:00:00 |
M6020 | Shipment - Chemical injection interconnecting piping | Not Started | Yes | 0,0 | 2015-01-07T08:00:00 | 2015-02-28T16:00:00 |
M6030 | At site - Chemical injection interconnecting piping | Not Started | Yes | 0,0 | 2015-02-28T16:00:00 | 2015-02-28T16:00:00 |
J2875 | Transport to Port of Export - Chemical injection interconnecting piping | Not Started | Yes | 0,0 | 2014-12-31T08:00:00 | 2015-01-06T16:00:00 |
307819 | CHEMICAL INJECTION SKID | |||||
F2800 | Purchasing - Chemical Injection System | Not Started | Yes | 0,0 | 2014-05-17T08:00:00 | 2014-06-27T16:00:00 |
F2810 | PO placed - Chemical Injection System | Not Started | Yes | 0,0 | 2014-06-27T16:00:00 | 2014-06-27T16:00:00 |
F2830 | Ready for Shipment - Chemical Injection System | Not Started | Yes | 0,0 | 2015-03-20T16:00:00 | 2015-03-20T16:00:00 |
F2820 | Delievery Time - Chemical Injection System | Not Started | Yes | 0,0 | 2014-06-28T08:00:00 | 2015-03-20T16:00:00 |
M2840 | Shipment - Chemical Injection System | Not Started | Yes | 0,0 | 2015-03-28T08:00:00 | 2015-05-11T16:00:00 |
M2850 | At site - Chemical Injection System | Not Started | Yes | 0,0 | 2015-05-11T16:00:00 | 2015-05-11T16:00:00 |
F2835 | Transport to Port of Export - Chemical Injection System | Not Started | Yes | 0,0 | 2015-03-21T08:00:00 | 2015-03-27T16:00:00 |
307820 | 200 - CONDENSATE STABILISATOR SYSTEM | |||||
307821 | CONDENSATE STABILISATION SKID | |||||
F1240 | Purchasing - Condensate Stabilisation System | Not Started | Yes | 0,0 | 2014-04-12T08:00:00 | 2014-05-23T16:00:00 |
F1250 | PO placed - Condensate Stabilisation System | Not Started | Yes | 0,0 | 2014-05-23T16:00:00 | 2014-05-23T16:00:00 |
F1270 | Ready for Shipment - Condensate Stabilisation System | Not Started | Yes | 0,0 | 2015-03-06T16:00:00 | 2015-03-06T16:00:00 |
F1260 | Delievery Time - Condensate Stabilisation System | Not Started | Yes | 0,0 | 2014-05-24T08:00:00 | 2015-03-06T16:00:00 |
M1280 | Shipment - Condensate Stabilisation System | Not Started | Yes | 0,0 | 2015-03-14T08:00:00 | 2015-04-27T16:00:00 |
M1290 | At site - Condensate Stabilisation System | Not Started | Yes | 0,0 | 2015-04-27T16:00:00 | 2015-04-27T16:00:00 |
F1275 | Transport to Port of Export - Condensate Stabilisation System | Not Started | Yes | 0,0 | 2015-03-07T08:00:00 | 2015-03-13T16:00:00 |
307822 | CONDENSATE PIPING | |||||
J3840 | Purchasing - Condensate Piping | Not Started | Yes | 0,0 | 2014-05-22T08:00:00 | 2014-07-30T16:00:00 |
J3850 | First PO placed - Condensate Piping | Not Started | Yes | 0,0 | 2014-06-06T08:00:00 | 2014-06-06T08:00:00 |
J3860 | Delivery Time - Condensate Piping | Not Started | Yes | 0,0 | 2014-06-06T08:00:00 | 2014-11-02T16:00:00 |
J3880 | Ready for Shipment (Ex Works) - Condensate Piping | Not Started | Yes | 0,0 | 2014-11-03T08:00:00 | 2014-11-03T08:00:00 |
M5580 | Shipment - Condensate Piping | Not Started | Yes | 0,0 | 2014-11-10T08:00:00 | 2014-12-24T16:00:00 |
M5590 | At workshop - Condensate Piping | Not Started | Yes | 0,0 | 2014-12-24T16:00:00 | 2014-12-24T16:00:00 |
J3885 | Transport to Port of Export - Condensate Piping | Not Started | Yes | 0,0 | 2014-11-03T08:00:00 | 2014-11-09T16:00:00 |
307823 | 210 - TEST SEPARATION AND METERING SYSTEM | |||||
F1360 | Purchasing - Test Separation and Metering System | Not Started | Yes | 0,0 | 2014-05-03T08:00:00 | 2014-06-13T16:00:00 |
F1370 | PO placed - Test Separation and Metering System | Not Started | Yes | 0,0 | 2014-06-13T16:00:00 | 2014-06-13T16:00:00 |
F1390 | Ready for Shipment - Test Separation and Metering System | Not Started | Yes | 0,0 | 2015-03-13T16:00:00 | 2015-03-13T16:00:00 |
F1380 | Delievery Time - Test Separation and Metering System | Not Started | Yes | 0,0 | 2014-06-14T08:00:00 | 2015-03-13T16:00:00 |
M1400 | Shipment - Test Separation and Metering System | Not Started | Yes | 0,0 | 2015-03-21T08:00:00 | 2015-05-04T16:00:00 |
M1410 | At site - Test Separation and Metering System | Not Started | Yes | 0,0 | 2015-05-04T16:00:00 | 2015-05-04T16:00:00 |
F1395 | Transport to Port of Export - Test Separation and Metering System | Not Started | Yes | 0,0 | 2015-03-14T08:00:00 | 2015-03-20T16:00:00 |
307824 | 220 - GAS RECEPTION SYSTEM | |||||
F1480 | Purchasing - Gas Reception System | Not Started | Yes | 0,0 | 2014-04-12T08:00:00 | 2014-05-23T16:00:00 |
F1490 | PO placed - Gas Reception System | Not Started | Yes | 0,0 | 2014-05-23T16:00:00 | 2014-05-23T16:00:00 |
F1510 | Ready for Shipment - Gas Reception System | Not Started | Yes | 0,0 | 2015-02-20T16:00:00 | 2015-02-20T16:00:00 |
F1500 | Delievery Time - Gas Reception System | Not Started | Yes | 0,0 | 2014-05-24T08:00:00 | 2015-02-20T16:00:00 |
M1520 | Shipment - Gas Reception System | Not Started | Yes | 0,0 | 2015-02-28T08:00:00 | 2015-04-13T16:00:00 |
M1530 | At site - Gas Reception System | Not Started | Yes | 0,0 | 2015-04-13T16:00:00 | 2015-04-13T16:00:00 |
M31201 | Inlet Manifold - HP, MP, LP (in MIG Workshop) | Not Started | No | 0,0 | 2014-09-01T08:00:00 | 2014-12-29T16:00:00 |
F1515 | Transport to Port of Export - Gas Reception System | Not Started | Yes | 0,0 | 2015-02-21T08:00:00 | 2015-02-27T16:00:00 |
307825 | 220 - GAS SEPARATION SYSTEM | |||||
F1600 | Purchasing - Gas Separation System | Not Started | Yes | 0,0 | 2014-04-12T08:00:00 | 2014-05-23T16:00:00 |
F1610 | PO placed - Gas Separation System | Not Started | Yes | 0,0 | 2014-05-23T16:00:00 | 2014-05-23T16:00:00 |
F1630 | Ready for Shipment - Gas Separation System | Not Started | Yes | 0,0 | 2015-02-20T16:00:00 | 2015-02-20T16:00:00 |
F1620 | Delievery Time - Gas Separation System | Not Started | Yes | 0,0 | 2014-05-24T08:00:00 | 2015-02-20T16:00:00 |
M1640 | Shipment - Gas Separation System | Not Started | Yes | 0,0 | 2015-02-28T08:00:00 | 2015-04-13T16:00:00 |
M1650 | At site - Gas Separation System | Not Started | Yes | 0,0 | 2015-04-13T16:00:00 | 2015-04-13T16:00:00 |
F1635 | Transport to Port of Export - Gas Separation System | Not Started | Yes | 0,0 | 2015-02-21T08:00:00 | 2015-02-27T16:00:00 |
307826 | 240 - GAS TREATMENT SYSTEM | |||||
F1840 | Purchasing - Gas Treatment System | Not Started | Yes | 0,0 | 2014-04-19T08:00:00 | 2014-05-30T16:00:00 |
F1850 | PO placed - Gas Treatment System | Not Started | Yes | 0,0 | 2014-05-30T16:00:00 | 2014-05-30T16:00:00 |
F1870 | Ready for Shipment - Gas Treatment System | Not Started | Yes | 0,0 | 2015-03-06T16:00:00 | 2015-03-06T16:00:00 |
F1860 | Delievery Time - Gas Treatment System | Not Started | Yes | 0,0 | 2014-05-31T08:00:00 | 2015-03-06T16:00:00 |
M1880 | Shipment - Gas Treatment System | Not Started | Yes | 0,0 | 2015-03-14T08:00:00 | 2015-04-27T16:00:00 |
M1890 | At site - Gas Treatment System | Not Started | Yes | 0,0 | 2015-04-27T16:00:00 | 2015-04-27T16:00:00 |
F1875 | Transport to Port of Export - Gas Treatment System | Not Started | Yes | 0,0 | 2015-03-07T08:00:00 | 2015-03-13T16:00:00 |
307827 | 270 - GAS EXPORT AND METERING SYSTEM | |||||
F2200 | Purchasing - Gas Export and Metering System | Not Started | Yes | 0,0 | 2014-04-26T08:00:00 | 2014-06-06T16:00:00 |
F2210 | PO placed - Gas Export and Metering System | Not Started | Yes | 0,0 | 2014-06-06T16:00:00 | 2014-06-06T16:00:00 |
F2230 | Ready for Shipment - Gas Export and Metering System | Not Started | Yes | 0,0 | 2015-04-24T16:00:00 | 2015-04-24T16:00:00 |
F2220 | Delievery Time - Gas Export and Metering System | Not Started | Yes | 0,0 | 2014-06-07T08:00:00 | 2015-04-24T16:00:00 |
M2240 | Shipment - Gas Export and Metering System | Not Started | Yes | 0,0 | 2015-05-02T08:00:00 | 2015-06-15T16:00:00 |
M2250 | At site - Gas Export and Metering System | Not Started | Yes | 0,0 | 2015-06-15T16:00:00 | 2015-06-15T16:00:00 |
F2235 | Transport to Port of Export - Gas Export and Metering System | Not Started | Yes | 0,0 | 2015-04-25T08:00:00 | 2015-05-01T16:00:00 |
307828 | 330 - CONDENSATE STORAGE AND METERING SYSTEM | |||||
307829 | CONDENSATE METERING SKID | |||||
F2440 | Purchasing - Condensate Metering System and Pumps | Not Started | Yes | 0,0 | 2014-05-24T08:00:00 | 2014-07-04T16:00:00 |
F2450 | PO placed - Condensate Metering System and Pumps | Not Started | Yes | 0,0 | 2014-07-04T16:00:00 | 2014-07-04T16:00:00 |
F2470 | Ready for Shipment - Condensate Metering System and Pumps | Not Started | Yes | 0,0 | 2015-05-22T16:00:00 | 2015-05-22T16:00:00 |
F2460 | Delievery Time - Condensate Metering System and Pumps | Not Started | Yes | 0,0 | 2014-07-05T08:00:00 | 2015-05-22T16:00:00 |
M2480 | Shipment - Condensate Metering System and Pumps | Not Started | Yes | 0,0 | 2015-05-30T08:00:00 | 2015-07-13T16:00:00 |
M2490 | At site - Condensate Metering System and Pumps | Not Started | Yes | 0,0 | 2015-07-13T16:00:00 | 2015-07-13T16:00:00 |
F2475 | Transport to Port of Export - Condensate Metering System and Pumps | Not Started | Yes | 0,0 | 2015-05-23T08:00:00 | 2015-05-29T16:00:00 |
J5345 | data sheet and techn. requirements for purchasing available | Not Started | Yes | 0,0 | 2014-05-24T08:00:00 | 2014-05-24T08:00:00 |
307830 | CONDENSATE SYSTEM PIPING | |||||
J2230 | Purchasing - Condensate System Piping | Not Started | Yes | 0,0 | 2014-06-08T08:00:00 | 2014-08-16T16:00:00 |
J2240 | First PO placed - Condensate System Piping | Not Started | Yes | 0,0 | 2014-06-23T08:00:00 | 2014-06-23T08:00:00 |
J2250 | Delivery Time - Condensate System Piping | Not Started | Yes | 0,0 | 2014-06-23T08:00:00 | 2014-11-19T16:00:00 |
J2270 | Ready for Shipment - Condensate System Piping | Not Started | Yes | 0,0 | 2014-11-20T08:00:00 | 2014-11-20T08:00:00 |
M5620 | Shipment - Condensate System Piping | Not Started | Yes | 0,0 | 2014-11-27T08:00:00 | 2015-01-10T16:00:00 |
M5630 | At site - Condensate System Piping | Not Started | Yes | 0,0 | 2015-01-10T16:00:00 | 2015-01-10T16:00:00 |
J2275 | Transport to Port of Export - Condensate System Piping | Not Started | Yes | 0,0 | 2014-11-20T08:00:00 | 2014-11-26T16:00:00 |
J5405 | Ready for Shipment - (70%) Condensate System Piping | Not Started | Yes | 0,0 | 2014-10-29T08:00:00 | 2014-10-29T08:00:00 |
M5415 | Shipment - (70%) Condensate System Piping | Not Started | Yes | 0,0 | 2014-11-05T08:00:00 | 2014-12-19T16:00:00 |
M5425 | At site - (70%) Condensate System Piping | Not Started | Yes | 0,0 | 2014-12-19T16:00:00 | 2014-12-19T16:00:00 |
J5415 | Transport to Port of Export - (70%) Condensate System Piping | Not Started | Yes | 0,0 | 2014-10-29T08:00:00 | 2014-11-04T16:00:00 |
307831 | CONDENSATE STORAGE SKID | |||||
M7010 | Purchasing - Condensate Storage System | Not Started | Yes | 0,0 | 2014-07-05T08:00:00 | 2014-08-29T16:00:00 |
M7020 | PO placed - Condensate Storage System | Not Started | Yes | 0,0 | 2014-08-29T16:00:00 | 2014-08-29T16:00:00 |
M7045 | Ready for Shipment - Condensate Storage System | Not Started | Yes | 0,0 | 2015-03-27T16:00:00 | 2015-03-27T16:00:00 |
M7040 | Delievery Time - Condensate Storage System | Not Started | Yes | 0,0 | 2014-08-30T08:00:00 | 2015-03-27T16:00:00 |
M7055 | Shipment - Condensate Storage System | Not Started | Yes | 0,0 | 2015-03-28T08:00:00 | 2015-04-20T16:00:00 |
M7065 | At site - Condensate Storage System | Not Started | Yes | 0,0 | 2015-04-20T16:00:00 | 2015-04-20T16:00:00 |
307832 | 400 - COOLING MEDIUM (PROPANE) SYSTEM | |||||
F2560 | Purchasing - Cooling Medium (Propane) System | Not Started | Yes | 0,0 | 2014-04-26T08:00:00 | 2014-06-06T16:00:00 |
F2570 | PO placed - Cooling Medium (Propane) System | Not Started | Yes | 0,0 | 2014-06-06T16:00:00 | 2014-06-06T16:00:00 |
F2590 | Ready for Shipment - Cooling Medium (Propane) System | Not Started | Yes | 0,0 | 2015-06-19T16:00:00 | 2015-06-19T16:00:00 |
F2580 | Delievery Time - Cooling Medium (Propane) System | Not Started | Yes | 0,0 | 2014-06-07T08:00:00 | 2015-06-19T16:00:00 |
M2600 | Shipment - Cooling Medium (Propane) System | Not Started | Yes | 0,0 | 2015-06-27T08:00:00 | 2015-08-10T16:00:00 |
M2610 | At site - Cooling Medium (Propane) System | Not Started | Yes | 0,0 | 2015-08-10T16:00:00 | 2015-08-10T16:00:00 |
F2595 | Transport to Port of Export - Cooling Medium (Propane) System | Not Started | Yes | 0,0 | 2015-06-20T08:00:00 | 2015-06-26T16:00:00 |
307833 | 410 - HEATING MEDIUM SYSTEM | |||||
307834 | HEATING MEDIUM SKID | |||||
F2680 | Purchasing - Heating Medium System | Not Started | Yes | 0,0 | 2014-05-17T08:00:00 | 2014-06-27T16:00:00 |
F2690 | PO placed - Heating Medium System | Not Started | Yes | 0,0 | 2014-06-27T16:00:00 | 2014-06-27T16:00:00 |
F2710 | Ready for Shipment - Heating Medium System | Not Started | Yes | 0,0 | 2015-03-20T16:00:00 | 2015-03-20T16:00:00 |
F2700 | Delievery Time - Heating Medium System | Not Started | Yes | 0,0 | 2014-06-28T08:00:00 | 2015-03-20T16:00:00 |
M2720 | Shipment - Heating Medium System | Not Started | Yes | 0,0 | 2015-03-28T08:00:00 | 2015-05-11T16:00:00 |
M2730 | At site - Heating Medium System | Not Started | Yes | 0,0 | 2015-05-11T16:00:00 | 2015-05-11T16:00:00 |
F2715 | Transport to Port of Export - Heating Medium System | Not Started | Yes | 0,0 | 2015-03-21T08:00:00 | 2015-03-27T16:00:00 |
307835 | HEATING MEDIUM PIPING | |||||
J2730 | Purchasing - Heat medium interconnecting piping | Not Started | Yes | 0,0 | 2014-07-05T08:00:00 | 2014-09-12T16:00:00 |
J2740 | First PO placed - Heat medium interconnecting piping | Not Started | Yes | 0,0 | 2014-07-20T08:00:00 | 2014-07-20T08:00:00 |
J2750 | Delivery Time - Heat medium interconnecting piping | Not Started | Yes | 0,0 | 2014-07-20T08:00:00 | 2014-12-16T16:00:00 |
J2770 | Ready for Shipment - Heat medium interconnecting piping | Not Started | Yes | 0,0 | 2014-12-17T08:00:00 | 2014-12-17T08:00:00 |
M6000 | Shipment - Heat medium interconnecting piping | Not Started | Yes | 0,0 | 2014-12-24T08:00:00 | 2015-02-06T16:00:00 |
M6010 | At site - Heat medium interconnecting piping | Not Started | Yes | 0,0 | 2015-02-06T16:00:00 | 2015-02-06T16:00:00 |
J2775 | Transport to Port of Export - Heat medium interconnecting piping | Not Started | Yes | 0,0 | 2014-12-17T08:00:00 | 2014-12-23T16:00:00 |
307836 | 450 - FUEL GAS SYSTEM | |||||
307837 | FUEL GAS SUPPLY SYSTEM PIPING | |||||
J3450 | Purchasing - Fuel Gas Supply System Piping | Not Started | Yes | 0,0 | 2014-06-14T08:00:00 | 2014-08-22T16:00:00 |
J3460 | First PO placed - Fuel Gas Supply System Piping | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2014-06-29T08:00:00 |
J3470 | Delivery Time - Fuel Gas Supply System Piping | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2014-11-25T16:00:00 |
J3490 | Ready for Shipment - Fuel Gas Supply System Piping | Not Started | Yes | 0,0 | 2014-11-26T08:00:00 | 2014-11-26T08:00:00 |
M5720 | Shipment - Fuel Gas Supply System Piping | Not Started | Yes | 0,0 | 2014-12-03T08:00:00 | 2015-01-16T16:00:00 |
M5730 | At site - Fuel Gas Supply System Piping | Not Started | Yes | 0,0 | 2015-01-16T16:00:00 | 2015-01-16T16:00:00 |
J3495 | Transport to Port of Export - Fuel Gas Supply System Piping | Not Started | Yes | 0,0 | 2014-11-26T08:00:00 | 2014-12-02T16:00:00 |
307838 | FUEL GAS SUPPLY SYSTEM | |||||
J3340 | Purchasing - Fuel Gas Supply System | Not Started | Yes | 0,0 | 2014-05-30T08:00:00 | 2014-06-28T16:00:00 |
J3350 | PO placed - Fuel Gas Supply System | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2014-06-29T08:00:00 |
J3360 | Delivery Time (incl. Detail Engineering) - Fuel Gas Supply System | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2015-05-24T16:00:00 |
J3370 | FAT - Fuel Gas Supply System | Not Started | No | 0,0 | 2015-05-11T08:00:00 | 2015-05-17T16:00:00 |
J3380 | Ready for Shipment - Fuel Gas Supply System | Not Started | Yes | 0,0 | 2015-05-25T08:00:00 | 2015-05-25T08:00:00 |
M3390 | Shipment (Placeholder / MIG Scope) - Fuel Gas Supply System | Not Started | Yes | 0,0 | 2015-06-01T08:00:00 | 2015-07-15T16:00:00 |
M3400 | At site - Fuel Gas Supply System | Not Started | Yes | 0,0 | 2015-07-15T16:00:00 | 2015-07-15T16:00:00 |
J3385 | Transport to Port of Export - Fuel Gas Supply System | Not Started | Yes | 0,0 | 2015-05-25T08:00:00 | 2015-05-31T16:00:00 |
J3390 | data sheet | Not Started | Yes | 0,0 | 2014-05-30T08:00:00 | 2014-05-30T08:00:00 |
307839 | 460 - METHANOL INJECTION SYSTEM | |||||
307840 | METHANOL INJECTION SKID | |||||
F2920 | Purchasing - Methanol Injection System | Not Started | Yes | 0,0 | 2014-05-17T08:00:00 | 2014-06-27T16:00:00 |
F2930 | PO placed - Methanol Injection System | Not Started | Yes | 0,0 | 2014-06-27T16:00:00 | 2014-06-27T16:00:00 |
F2950 | Ready for Shipment - Methanol Injection System | Not Started | Yes | 0,0 | 2015-04-17T16:00:00 | 2015-04-17T16:00:00 |
F2940 | Delievery Time - Methanol Injection System | Not Started | Yes | 0,0 | 2014-06-28T08:00:00 | 2015-04-17T16:00:00 |
M2960 | Shipment - Methanol Injection System | Not Started | Yes | 0,0 | 2015-04-25T08:00:00 | 2015-06-08T16:00:00 |
M2970 | At site - Methanol Injection System | Not Started | Yes | 0,0 | 2015-06-08T16:00:00 | 2015-06-08T16:00:00 |
F2955 | Transport to Port of Export - Methanol Injection System | Not Started | Yes | 0,0 | 2015-04-18T08:00:00 | 2015-04-24T16:00:00 |
F2960 | data sheet | Not Started | Yes | 0,0 | 2014-05-17T08:00:00 | 2014-05-17T08:00:00 |
307841 | METHANOL PIPING | |||||
J4190 | Purchasing - Methanol injection interconnecting piping | Not Started | Yes | 0,0 | 2014-05-15T08:00:00 | 2014-07-23T16:00:00 |
J4200 | First PO placed - Methanol injection interconnecting piping | Not Started | Yes | 0,0 | 2014-05-30T08:00:00 | 2014-05-30T08:00:00 |
J4210 | Delivery Time - Methanol injection interconnecting piping | Not Started | Yes | 0,0 | 2014-05-30T08:00:00 | 2014-10-26T16:00:00 |
J4230 | Ready for Shipment - Methanol injection interconnecting piping | Not Started | Yes | 0,0 | 2014-10-27T08:00:00 | 2014-10-27T08:00:00 |
M6080 | Shipment - Methanol injection interconnecting piping | Not Started | Yes | 0,0 | 2014-11-03T08:00:00 | 2014-12-17T16:00:00 |
M6090 | At site - Methanol injection interconnecting piping | Not Started | Yes | 0,0 | 2014-12-17T16:00:00 | 2014-12-17T16:00:00 |
J4235 | Transport to Port of Export - Methanol injection interconnecting piping | Not Started | Yes | 0,0 | 2014-10-27T08:00:00 | 2014-11-02T16:00:00 |
307842 | METHANOL STORAGE SKID | |||||
M7050 | Purchasing - Methanol Storage System | Not Started | Yes | 0,0 | 2014-05-17T08:00:00 | 2014-07-28T16:00:00 |
M7060 | PO placed - Methanol Storage System | Not Started | Yes | 0,0 | 2014-07-28T16:00:00 | 2014-07-28T16:00:00 |
M7080 | Ready for Shipment - Methanol Storage System | Not Started | Yes | 0,0 | 2014-12-31T16:00:00 | 2014-12-31T16:00:00 |
M7070 | Delievery Time - Methanol Storage System | Not Started | Yes | 0,0 | 2014-07-29T08:00:00 | 2014-12-31T16:00:00 |
M7085 | Shipment - Methanol Storage System | Not Started | Yes | 0,0 | 2015-01-01T08:00:00 | 2015-02-22T16:00:00 |
M7095 | At site - Methanol Storage System | Not Started | No | 0,0 | 2015-02-22T16:00:00 | 2015-02-22T16:00:00 |
307843 | 480 - UTILITY MISCELLANEOUS SYSTEM | |||||
307844 | UTILITY MISCELLANEOUS SKIDS | |||||
F3040 | Purchasing - Utility Miscellaneous System | Not Started | Yes | 0,0 | 2014-05-10T08:00:00 | 2014-06-20T16:00:00 |
F3050 | PO placed - Utility Miscellaneous System | Not Started | Yes | 0,0 | 2014-06-20T16:00:00 | 2014-06-20T16:00:00 |
F3070 | Ready for Shipment - Utility Miscellaneous System | Not Started | Yes | 0,0 | 2015-05-08T16:00:00 | 2015-05-08T16:00:00 |
F3060 | Delievery Time - Utility Miscellaneous System | Not Started | Yes | 0,0 | 2014-06-21T08:00:00 | 2015-05-08T16:00:00 |
M3080 | Shipment - Utility Miscellaneous System | Not Started | Yes | 0,0 | 2015-05-16T08:00:00 | 2015-06-29T16:00:00 |
M3090 | At site - Utility Miscellaneous System | Not Started | Yes | 0,0 | 2015-06-29T16:00:00 | 2015-06-29T16:00:00 |
F3075 | Transport to Port of Export - Utility Miscellaneous System | Not Started | Yes | 0,0 | 2015-05-09T08:00:00 | 2015-05-15T16:00:00 |
307845 | AMINE PIPING | |||||
J4250 | Purchasing - Amine Piping | Not Started | Yes | 0,0 | 2014-06-28T08:00:00 | 2014-09-05T16:00:00 |
J4260 | First PO placed - Amine Piping | Not Started | Yes | 0,0 | 2014-07-13T08:00:00 | 2014-07-13T08:00:00 |
J4270 | Delivery Time - Amine Piping | Not Started | Yes | 0,0 | 2014-07-13T08:00:00 | 2014-12-09T16:00:00 |
J4290 | Ready for Shipment - Amine Piping | Not Started | Yes | 0,0 | 2014-12-10T08:00:00 | 2014-12-10T08:00:00 |
M5800 | Shipment - Amine Piping | Not Started | Yes | 0,0 | 2014-12-17T08:00:00 | 2015-01-30T16:00:00 |
M5810 | At site - Amine Piping | Not Started | Yes | 0,0 | 2015-01-30T16:00:00 | 2015-01-30T16:00:00 |
J4295 | Transport to Port of Export - Amine Piping | Not Started | Yes | 0,0 | 2014-12-10T08:00:00 | 2014-12-16T16:00:00 |
307846 | GLYCOL PIPING | |||||
J4310 | Purchasing - Glycol Piping | Not Started | Yes | 0,0 | 2014-06-28T08:00:00 | 2014-09-05T16:00:00 |
J4320 | First PO placed - Glycol Piping | Not Started | Yes | 0,0 | 2014-07-13T08:00:00 | 2014-07-13T08:00:00 |
J4330 | Delivery Time - Glycol Piping | Not Started | Yes | 0,0 | 2014-07-13T08:00:00 | 2014-12-09T16:00:00 |
J4350 | Ready for Shipment - Glycol Piping | Not Started | Yes | 0,0 | 2014-12-10T08:00:00 | 2014-12-10T08:00:00 |
M5820 | Shipment - Glycol Piping | Not Started | Yes | 0,0 | 2014-12-17T08:00:00 | 2015-01-30T16:00:00 |
M5830 | At site - Glycol Piping | Not Started | Yes | 0,0 | 2015-01-30T16:00:00 | 2015-01-30T16:00:00 |
J4355 | Transport to Port of Export - Glycol Piping | Not Started | Yes | 0,0 | 2014-12-10T08:00:00 | 2014-12-16T16:00:00 |
307847 | PLANT & PIPING (INTERCONNECTING) | |||||
307848 | INERTGAS INTERCONNECTING PIPING | |||||
307849 | CONDENSATE INTERCONNECTING PIPING | |||||
307850 | METHANOL INJECTION INTERCONNECTING PIPING | |||||
307851 | INTERCONNECTING PIPING (BULK) | |||||
J4020 | Purchasing - Interconnecting Piping | Not Started | Yes | 0,0 | 2014-05-22T08:00:00 | 2014-07-30T16:00:00 |
J4030 | First PO placed - Interconnecting Piping | Not Started | Yes | 0,0 | 2014-06-06T08:00:00 | 2014-06-06T08:00:00 |
J4040 | Delivery Time - Interconnecting Piping | Not Started | Yes | 0,0 | 2014-06-06T08:00:00 | 2014-11-02T16:00:00 |
J4060 | Ready for Shipment - Interconnecting Piping | Not Started | Yes | 0,0 | 2014-11-03T08:00:00 | 2014-11-03T08:00:00 |
M5940 | Shipment - Interconnecting Piping | Not Started | Yes | 0,0 | 2014-11-10T08:00:00 | 2014-12-24T16:00:00 |
M5950 | At site - Interconnecting Piping | Not Started | Yes | 0,0 | 2014-12-24T16:00:00 | 2014-12-24T16:00:00 |
J4065 | Transport to Port of Export - Interconnecting Piping | Not Started | Yes | 0,0 | 2014-11-03T08:00:00 | 2014-11-09T16:00:00 |
J5365 | Ready for Shipment - Interconnecting Piping 60% | Not Started | Yes | 0,0 | 2014-09-12T08:00:00 | 2014-09-12T08:00:00 |
M5385 | Shipment - Interconnecting Piping 60% | Not Started | Yes | 0,0 | 2014-09-19T08:00:00 | 2014-11-02T16:00:00 |
M5395 | At site - Interconnecting Piping 60% | Not Started | Yes | 0,0 | 2014-11-02T16:00:00 | 2014-11-02T16:00:00 |
J5375 | Transport to Port of Export - Interconnecting Piping 60% | Not Started | Yes | 0,0 | 2014-09-12T08:00:00 | 2014-09-18T16:00:00 |
J5385 | Ready for Shipment - Interconnecting Piping 80% | Not Started | Yes | 0,0 | 2014-10-06T08:00:00 | 2014-10-06T08:00:00 |
M5405 | Shipment - Interconnecting Piping 80% | Not Started | Yes | 0,0 | 2014-10-13T08:00:00 | 2014-11-26T16:00:00 |
M5435 | At site - Interconnecting Piping 80% | Not Started | Yes | 0,0 | 2014-11-26T16:00:00 | 2014-11-26T16:00:00 |
J5395 | Transport to Port of Export - Interconnecting Piping 80% | Not Started | Yes | 0,0 | 2014-10-06T08:00:00 | 2014-10-12T16:00:00 |
307852 | FLARE CONNECTING INTERCONNECTING PIPING | |||||
307853 | GAS INTERCONNECTING PIPING | |||||
307854 | CHEMICAL INJECTION INTERCONNECTING PIPING | |||||
307855 | PRODUCED WATER INTERCONNECTING PIPING | |||||
307856 | HEATING MEDIUM INTERCONNECTING PIPING | |||||
307857 | 110 - GAS WELLS SYSTEM | |||||
307858 | GAS WELLS SKID | |||||
F4830 | Purchasing - Gas Wells System | Not Started | Yes | 0,0 | 2014-05-03T08:00:00 | 2014-06-13T16:00:00 |
F4840 | PO placed - Gas Wells System | Not Started | Yes | 0,0 | 2014-06-13T16:00:00 | 2014-06-13T16:00:00 |
F4860 | Ready for Shipment - Gas Wells System (Skid 1-3) | Not Started | Yes | 0,0 | 2015-05-01T16:00:00 | 2015-05-01T16:00:00 |
F4850 | Delievery Time - Gas Wells System (Skid 1-3) | Not Started | Yes | 0,0 | 2014-06-14T08:00:00 | 2015-05-01T16:00:00 |
M4870 | Shipment - Gas Wells System (Skid 1-3) | Not Started | Yes | 0,0 | 2015-05-09T08:00:00 | 2015-06-22T16:00:00 |
M4880 | At site - Gas Wells System (Skid 1-3) | Not Started | Yes | 0,0 | 2015-06-22T16:00:00 | 2015-06-22T16:00:00 |
F5570 | Ready for Shipment - Gas Wells System (Skid 4-6) | Not Started | Yes | 0,0 | 2015-05-15T16:00:00 | 2015-05-15T16:00:00 |
F5560 | Delievery Time - Gas Wells System (Skid 4-6) | Not Started | Yes | 0,0 | 2014-06-14T08:00:00 | 2015-05-15T16:00:00 |
M6120 | Shipment - Gas Wells System (Skid 4-6) | Not Started | Yes | 0,0 | 2015-05-23T08:00:00 | 2015-07-06T16:00:00 |
M6130 | At site - Gas Wells System (Skid 4-6) | Not Started | Yes | 0,0 | 2015-07-06T16:00:00 | 2015-07-06T16:00:00 |
F5590 | Ready for Shipment - Gas Wells System (Skid 7-9) | Not Started | Yes | 0,0 | 2015-06-12T16:00:00 | 2015-06-12T16:00:00 |
F5580 | Delievery Time - Gas Wells System (Skid 7-9) | Not Started | Yes | 0,0 | 2014-06-14T08:00:00 | 2015-06-12T16:00:00 |
M6140 | Shipment - Gas Wells System (Skid 7-9) | Not Started | Yes | 0,0 | 2015-06-20T08:00:00 | 2015-08-03T16:00:00 |
M6150 | At site - Gas Wells System (Skid 7-9) | Not Started | Yes | 0,0 | 2015-08-03T16:00:00 | 2015-08-03T16:00:00 |
F4865 | Transport to Port of Export - Gas Wells System (Skid 1-3) | Not Started | Yes | 0,0 | 2015-05-02T08:00:00 | 2015-05-08T16:00:00 |
F5575 | Transport to Port of Export - Gas Wells System (Skid 4-6) | Not Started | Yes | 0,0 | 2015-05-16T08:00:00 | 2015-05-22T16:00:00 |
F5595 | Transport to Port of Export - Gas Wells System (Skid 7-9) | Not Started | Yes | 0,0 | 2015-06-13T08:00:00 | 2015-06-19T16:00:00 |
307859 | 200 - WATER / CONDENSATE SEPARATOR SYSTEM | |||||
307860 | WATER / CONDENSATE SEPARATOR SKID | |||||
F1120 | Purchasing - Water / Condensate Separator System | Not Started | Yes | 0,0 | 2014-04-12T08:00:00 | 2014-05-23T16:00:00 |
F1130 | PO placed - Water / Condensate Separator System | Not Started | Yes | 0,0 | 2014-05-23T16:00:00 | 2014-05-23T16:00:00 |
F1150 | Ready for Shipment - Water / Condensate Separator System | Not Started | Yes | 0,0 | 2015-03-06T16:00:00 | 2015-03-06T16:00:00 |
F1140 | Delievery Time - Water / Condensate Separator System | Not Started | Yes | 0,0 | 2014-05-24T08:00:00 | 2015-03-06T16:00:00 |
M1160 | Shipment - Water / Condensate Separator System | Not Started | Yes | 0,0 | 2015-03-14T08:00:00 | 2015-04-27T16:00:00 |
M1170 | At site - Water / Condensate Separator System | Not Started | Yes | 0,0 | 2015-04-27T16:00:00 | 2015-04-27T16:00:00 |
F1155 | Transport to Port of Export - Water / Condensate Separator System | Not Started | Yes | 0,0 | 2015-03-07T08:00:00 | 2015-03-13T16:00:00 |
307861 | 232 - OFFGAS COMPRESSION SYSTEM | |||||
307862 | OFFGAS CONNECTION SKID | |||||
F1720 | Purchasing - Offgas Compression System | Not Started | Yes | 0,0 | 2014-04-12T08:00:00 | 2014-05-23T16:00:00 |
F1730 | PO placed - Offgas Compression System | Not Started | Yes | 0,0 | 2014-05-23T16:00:00 | 2014-05-23T16:00:00 |
F1750 | Ready for Shipment - Offgas Compression System | Not Started | Yes | 0,0 | 2015-06-19T16:00:00 | 2015-06-19T16:00:00 |
F1740 | Delievery Time - Offgas Compression System | Not Started | Yes | 0,0 | 2014-05-24T08:00:00 | 2015-06-19T16:00:00 |
M1760 | Shipment - Offgas Compression System | Not Started | Yes | 0,0 | 2015-06-27T08:00:00 | 2015-08-10T16:00:00 |
M1770 | At site - Offgas Compression System | Not Started | Yes | 0,0 | 2015-08-10T16:00:00 | 2015-08-10T16:00:00 |
F1755 | Transport to Port of Export - Offgas Compression System | Not Started | Yes | 0,0 | 2015-06-20T08:00:00 | 2015-06-26T16:00:00 |
307863 | OFFGAS CONNECTION PIPING | |||||
J3900 | Purchasing - Off gas interconnecting piping | Not Started | Yes | 0,0 | 2014-05-22T08:00:00 | 2014-07-30T16:00:00 |
J3910 | First PO placed - Off gas interconnecting piping | Not Started | Yes | 0,0 | 2014-06-06T08:00:00 | 2014-06-06T08:00:00 |
J3920 | Delivery Time - Off gas interconnecting piping | Not Started | Yes | 0,0 | 2014-06-06T08:00:00 | 2015-01-01T16:00:00 |
J3940 | Ready for Shipment (Ex Works) - Off gas interconnecting piping | Not Started | Yes | 0,0 | 2015-01-02T08:00:00 | 2015-01-02T08:00:00 |
M5600 | Shipment - Off gas interconnecting piping | Not Started | Yes | 0,0 | 2015-01-09T08:00:00 | 2015-02-22T16:00:00 |
M5610 | At site - Off gas interconnecting piping | Not Started | Yes | 0,0 | 2015-02-22T16:00:00 | 2015-02-22T16:00:00 |
J3945 | Transport to Port of Export - Off gas interconnecting piping | Not Started | Yes | 0,0 | 2015-01-02T08:00:00 | 2015-01-08T16:00:00 |
307864 | 630 - INSTRUMENT AND PLANT AIR SYSTEM | |||||
307865 | PLANT AIR PIPING | |||||
J5050 | Purchasing - Plant Air Piping | Not Started | Yes | 0,0 | 2014-05-15T08:00:00 | 2014-07-23T16:00:00 |
J5060 | First PO placed - Plant Air Piping | Not Started | Yes | 0,0 | 2014-05-30T08:00:00 | 2014-05-30T08:00:00 |
J5070 | Delivery Time - Plant Air Piping | Not Started | Yes | 0,0 | 2014-05-30T08:00:00 | 2014-10-26T16:00:00 |
J5090 | Ready for Shipment - Plant Air Piping | Not Started | Yes | 0,0 | 2014-10-27T08:00:00 | 2014-10-27T08:00:00 |
M5900 | Shipment - Plant Air Piping | Not Started | Yes | 0,0 | 2014-11-03T08:00:00 | 2014-12-17T16:00:00 |
M5910 | At site - Plant Air Piping | Not Started | No | 0,0 | 2014-12-17T16:00:00 | 2014-12-17T16:00:00 |
J5095 | Transport to Port of Export - Plant Air Piping | Not Started | Yes | 0,0 | 2014-10-27T08:00:00 | 2014-11-02T16:00:00 |
307866 | INSTRUMENT AND PLANT AIR SYSTEM | |||||
J4940 | Purchasing - Instrument & Plant Air System | Not Started | Yes | 0,0 | 2014-05-30T08:00:00 | 2014-06-28T16:00:00 |
J4950 | PO placed - Instrument & Plant Air System | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2014-06-29T08:00:00 |
J4960 | Delivery Time (incl. Detail Engineering) - Instrument & Plant Air System | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2014-12-25T16:00:00 |
J4970 | FAT - Instrument & Plant Air System | Not Started | No | 0,0 | 2014-12-12T08:00:00 | 2014-12-18T16:00:00 |
J4980 | Ready for Shipment - Instrument & Plant Air System | Not Started | Yes | 0,0 | 2014-12-26T08:00:00 | 2014-12-26T08:00:00 |
M3120 | Shipment (Placeholder / MIG Scope) - Instrument & Plant Air System | Not Started | Yes | 0,0 | 2015-01-02T08:00:00 | 2015-02-15T16:00:00 |
M3130 | At site - Instrument & Plant Air System | Not Started | No | 0,0 | 2015-02-15T16:00:00 | 2015-02-15T16:00:00 |
J4985 | Transport to Port of Export - Instrument & Plant Air System | Not Started | Yes | 0,0 | 2014-12-26T08:00:00 | 2015-01-01T16:00:00 |
307867 | INSTRUMENT AIR SYSTEM | |||||
J5110 | Purchasing - Instrument Air Piping | Not Started | Yes | 0,0 | 2014-05-15T08:00:00 | 2014-07-23T16:00:00 |
J5120 | First PO placed - Instrument Air Piping | Not Started | No | 0,0 | 2014-05-30T08:00:00 | 2014-05-30T08:00:00 |
J5130 | Delivery Time - Instrument Air Piping | Not Started | Yes | 0,0 | 2014-10-27T08:00:00 | 2015-03-25T16:00:00 |
J5150 | Ready for Shipment - Instrument Air Piping | Not Started | Yes | 0,0 | 2015-03-26T08:00:00 | 2015-03-26T08:00:00 |
M5920 | Shipment - Instrument Air Piping | Not Started | Yes | 0,0 | 2015-04-02T08:00:00 | 2015-05-16T16:00:00 |
M5930 | At site - Instrument Air Piping | Not Started | Yes | 0,0 | 2015-05-16T16:00:00 | 2015-05-16T16:00:00 |
J5155 | Transport to Port of Export - Instrument Air Piping | Not Started | Yes | 0,0 | 2015-03-26T08:00:00 | 2015-04-01T16:00:00 |
307868 | 560 - OPEN DRAINS SYSTEM | |||||
M3501 | Purchasing - Open Drains System | Not Started | Yes | 0,0 | 2014-07-20T08:00:00 | 2014-08-19T16:00:00 |
M3502 | PO placed - Open Drains System | Not Started | Yes | 0,0 | 2014-08-19T16:00:00 | 2014-08-19T16:00:00 |
M3504 | Ready for Shipment - Open Drains System | Not Started | Yes | 0,0 | 2014-11-17T16:00:00 | 2014-11-17T16:00:00 |
M3503 | Delievery Time - Open Drains System | Not Started | Yes | 0,0 | 2014-08-20T08:00:00 | 2014-11-17T16:00:00 |
M3505 | Shipment - Open Drains System | Not Started | Yes | 0,0 | 2014-11-18T08:00:00 | 2014-12-18T16:00:00 |
M3506 | At site - Open Drains System | Not Started | No | 0,0 | 2014-12-18T16:00:00 | 2014-12-18T16:00:00 |
307869 | CAMP | |||||
M31001 | Camp | Not Started | No | 0,0 | 2014-06-01T08:00:00 | 2014-09-29T16:00:00 |
307870 | INSTRUMENTATION, CONTROL, ELECTRICAL | |||||
307871 | UPS 230V AC | |||||
J1590 | Purchasing - UPS 230V AC | Not Started | Yes | 0,0 | 2014-05-30T08:00:00 | 2014-06-28T16:00:00 |
J1600 | PO placed - UPS 230V AC | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2014-06-29T08:00:00 |
J1610 | Delivery Time (incl. Detail Engineering) - UPS 230V AC | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2015-01-24T16:00:00 |
J1620 | FAT - UPS 230V AC | Not Started | No | 0,0 | 2015-01-11T08:00:00 | 2015-01-17T16:00:00 |
J1630 | Ready for Shipment - UPS 230V AC | Not Started | Yes | 0,0 | 2015-01-25T08:00:00 | 2015-01-25T08:00:00 |
M1570 | Shipment (Placeholder / MIG Scope) - UPS 230V AC | Not Started | Yes | 0,0 | 2015-02-01T08:00:00 | 2015-04-01T16:00:00 |
M1580 | At site - UPS 230V AC | Not Started | Yes | 0,0 | 2015-04-01T16:00:00 | 2015-04-01T16:00:00 |
J1635 | Transport to Port of Export - UPS 230V AC | Not Started | Yes | 0,0 | 2015-01-25T08:00:00 | 2015-01-31T16:00:00 |
307872 | LV SYSTEM 400V | |||||
J1100 | Purchasing - LV System 400V | Not Started | Yes | 0,0 | 2014-05-30T08:00:00 | 2014-06-28T16:00:00 |
J1110 | PO placed - LV System 400V | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2014-06-29T08:00:00 |
J1120 | Delivery Time (incl. Detail Engineering) - LV System 400V | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2015-02-23T16:00:00 |
J1130 | FAT - LV System 400V | Not Started | No | 0,0 | 2015-02-10T08:00:00 | 2015-02-16T16:00:00 |
J1140 | Ready for Shipment - LV System 400V | Not Started | Yes | 0,0 | 2015-02-24T08:00:00 | 2015-02-24T08:00:00 |
M1180 | Shipment (Placeholder / MIG Scope) - LV System 400V | Not Started | Yes | 0,0 | 2015-03-03T08:00:00 | 2015-05-01T16:00:00 |
M1190 | At site - LV System 400V | Not Started | Yes | 0,0 | 2015-05-01T16:00:00 | 2015-05-01T16:00:00 |
J1145 | Transport to Port of Export - LV System 400V | Not Started | Yes | 0,0 | 2015-02-24T08:00:00 | 2015-03-02T16:00:00 |
307873 | PLANT COMMUNICATION AND VISUALIZATION SYSTEM | |||||
J1780 | Purchasing - Plant Communication and Visualization System | Not Started | Yes | 0,0 | 2014-05-30T08:00:00 | 2014-06-28T16:00:00 |
J1790 | PO placed - Plant Communication and Visualization System | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2014-06-29T08:00:00 |
J1800 | Delivery Time (incl. Detail Engineering) - Plant Communication and Visualization System | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2015-01-24T16:00:00 |
J1810 | FAT - Plant Communication and Visualization System | Not Started | No | 0,0 | 2015-01-11T08:00:00 | 2015-01-17T16:00:00 |
J1820 | Ready for Shipment - Plant Communication and Visualization System | Not Started | Yes | 0,0 | 2015-01-25T08:00:00 | 2015-01-25T08:00:00 |
M1830 | Shipment (Placeholder / MIG Scope) - Plant Communication and Visualization System | Not Started | Yes | 0,0 | 2015-02-01T08:00:00 | 2015-04-01T16:00:00 |
M1840 | At site - Plant Communication and Visualization System | Not Started | Yes | 0,0 | 2015-04-01T16:00:00 | 2015-04-01T16:00:00 |
J1825 | Transport to Port of Export - Plant Communication and Visualization System | Not Started | Yes | 0,0 | 2015-01-25T08:00:00 | 2015-01-31T16:00:00 |
307874 | BATTERY SYSTEM 220V DC | |||||
J1400 | Purchasing - Battery System 220V DC | Not Started | Yes | 0,0 | 2014-05-30T08:00:00 | 2014-06-28T16:00:00 |
J1410 | PO placed - Battery System 220V DC | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2014-06-29T08:00:00 |
J1420 | Delivery Time (incl. Detail Engineering) - Battery System 220V DC | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2015-02-23T16:00:00 |
J1430 | FAT - Battery System 220V DC | Not Started | No | 0,0 | 2015-02-10T08:00:00 | 2015-02-16T16:00:00 |
J1440 | Ready for Shipment - Battery System 220V DC | Not Started | Yes | 0,0 | 2015-02-24T08:00:00 | 2015-02-24T08:00:00 |
M1450 | Shipment (Placeholder / MIG Scope) - Battery System 220V DC | Not Started | Yes | 0,0 | 2015-03-03T08:00:00 | 2015-05-01T16:00:00 |
M1460 | At site - Battery System 220V DC | Not Started | Yes | 0,0 | 2015-05-01T16:00:00 | 2015-05-01T16:00:00 |
J1445 | Transport to Port of Export - Battery System 220V DC | Not Started | Yes | 0,0 | 2015-02-24T08:00:00 | 2015-03-02T16:00:00 |
307875 | LIGHTNING AND GROUNDING SYSTEM | |||||
J1690 | Purchasing - Lighting and Grounding System | Not Started | Yes | 0,0 | 2014-05-30T08:00:00 | 2014-06-28T16:00:00 |
J1700 | PO placed - Lighting and Grounding System | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2014-06-29T08:00:00 |
J1710 | Delivery Time (incl. Detail Engineering) - Lighting and Grounding System | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2014-09-26T16:00:00 |
J1720 | FAT - Lighting and Grounding System | Not Started | No | 0,0 | 2014-09-13T08:00:00 | 2014-09-19T16:00:00 |
J1730 | Ready for Shipment - Lighting and Grounding System | Not Started | Yes | 0,0 | 2014-09-27T08:00:00 | 2014-09-27T08:00:00 |
M1740 | Shipment (Placeholder / MIG Scope) - Lighting and Grounding System | Not Started | Yes | 0,0 | 2014-10-04T08:00:00 | 2014-12-02T16:00:00 |
M1750 | At site - Lighting and Grounding System | Not Started | Yes | 0,0 | 2014-12-02T16:00:00 | 2014-12-02T16:00:00 |
J1735 | Transport to Port of Export - Lighting and Grounding System | Not Started | Yes | 0,0 | 2014-09-27T08:00:00 | 2014-10-03T16:00:00 |
307876 | FIELD INSTRUMENTS | |||||
J2050 | Purchasing - Field Instruments | Not Started | Yes | 0,0 | 2014-06-10T10:00:00 | 2014-07-10T10:00:00 |
J2060 | PO placed - Field Instruments | Not Started | Yes | 0,0 | 2014-07-10T10:00:00 | 2014-07-10T10:00:00 |
J2070 | Delivery Time (incl. Detail Engineering) - Field Instruments | Not Started | Yes | 0,0 | 2014-07-10T10:00:00 | 2014-10-08T10:00:00 |
J2080 | FAT - Field Instruments | Not Started | No | 0,0 | 2014-09-24T10:00:00 | 2014-10-01T10:00:00 |
J2090 | Ready for Shipment - Field Instruments | Not Started | Yes | 0,0 | 2014-10-08T10:00:00 | 2014-10-08T10:00:00 |
M2100 | Shipment (Placeholder / MIG Scope) - Field Instruments | Not Started | Yes | 0,0 | 2014-10-15T10:00:00 | 2014-12-14T10:00:00 |
M2115 | At site - Field Instruments | Not Started | No | 0,0 | 2014-12-14T10:00:00 | 2014-12-14T10:00:00 |
J2095 | Transport to Port of Export - Field Instruments | Not Started | Yes | 0,0 | 2014-10-08T10:00:00 | 2014-10-15T10:00:00 |
307877 | FIELD CABLING | |||||
J2150 | Purchasing - Field Cabling | Not Started | Yes | 0,0 | 2014-05-22T12:00:00 | 2014-06-21T12:00:00 |
J2160 | PO placed - Field Cabling | Not Started | Yes | 0,0 | 2014-06-21T12:00:00 | 2014-06-21T12:00:00 |
J2170 | Delivery Time (incl. Detail Engineering) - Field Cabling | Not Started | Yes | 0,0 | 2014-06-21T12:00:00 | 2014-11-18T12:00:00 |
J2180 | Ready for Shipment - Field Cabling | Not Started | Yes | 0,0 | 2014-11-18T12:00:00 | 2014-11-18T12:00:00 |
M2190 | Shipment (Placeholder / MIG Scope) - Field Cabling | Not Started | Yes | 0,0 | 2014-11-25T12:00:00 | 2015-01-24T12:00:00 |
M2200 | At site - Field Cabling | Not Started | Yes | 0,0 | 2015-01-24T12:00:00 | 2015-01-24T12:00:00 |
J2185 | Transport to Port of Export - Field Cabling | Not Started | Yes | 0,0 | 2014-11-18T12:00:00 | 2014-11-25T12:00:00 |
307878 | MV SYSTEM 6.6kV | |||||
J1000 | Purchasing - MV System 6.6kV | Not Started | Yes | 0,0 | 2014-05-30T08:00:00 | 2014-06-28T16:00:00 |
J1010 | PO placed - MV System 6.6kV | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2014-06-29T08:00:00 |
J1020 | Delivery Time (incl. Detail Engineering) - MV System 6.6kV | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2015-01-24T16:00:00 |
J1030 | FAT - MV System 6.6kV | Not Started | No | 0,0 | 2015-01-11T08:00:00 | 2015-01-17T16:00:00 |
J1040 | Ready for Shipment - MV System 6.6kV | Not Started | Yes | 0,0 | 2015-01-25T08:00:00 | 2015-01-25T08:00:00 |
M1050 | Shipment (Placeholder / MIG Scope) - MV System 6.6kV | Not Started | Yes | 0,0 | 2015-02-01T08:00:00 | 2015-04-01T16:00:00 |
M1060 | At site - MV System 6.6kV | Not Started | Yes | 0,0 | 2015-04-01T16:00:00 | 2015-04-01T16:00:00 |
J1045 | Transport to Port of Export - MV System 6.6kV | Not Started | Yes | 0,0 | 2015-01-25T08:00:00 | 2015-01-31T16:00:00 |
307879 | FREQUENCY INVERTER | |||||
J1300 | Purchasing - Frequency Inverter | Not Started | Yes | 0,0 | 2014-04-30T08:00:00 | 2014-05-29T16:00:00 |
J1310 | PO placed - Frequency Inverter | Not Started | Yes | 0,0 | 2014-05-30T08:00:00 | 2014-05-30T08:00:00 |
J1320 | Delivery Time (incl. Detail Engineering) - Frequency Inverter | Not Started | Yes | 0,0 | 2014-05-30T08:00:00 | 2014-08-27T16:00:00 |
J1330 | FAT - Frequency Inverter | Not Started | No | 0,0 | 2014-08-14T08:00:00 | 2014-08-20T16:00:00 |
J1340 | Ready for Shipment - Frequency Inverter | Not Started | Yes | 0,0 | 2014-08-28T08:00:00 | 2014-08-28T08:00:00 |
M1350 | Shipment (Placeholder / MIG Scope) - Frequency Inverter | Not Started | Yes | 0,0 | 2014-09-04T08:00:00 | 2014-11-02T16:00:00 |
M1360 | At site - Frequency Inverter | Not Started | Yes | 0,0 | 2014-11-02T16:00:00 | 2014-11-02T16:00:00 |
J1345 | Transport to Port of Export - Frequency Inverter | Not Started | Yes | 0,0 | 2014-08-28T08:00:00 | 2014-09-03T16:00:00 |
307880 | LV TRAFOS | |||||
J1200 | Purchasing - LV Trafos | Not Started | Yes | 0,0 | 2014-04-30T08:00:00 | 2014-05-29T16:00:00 |
J1210 | PO placed - LV Trafos | Not Started | Yes | 0,0 | 2014-05-30T08:00:00 | 2014-05-30T08:00:00 |
J1220 | Delivery Time (incl. Detail Engineering) - LV Trafos | Not Started | Yes | 0,0 | 2014-05-30T08:00:00 | 2014-12-25T16:00:00 |
J1230 | FAT - LV Trafos | Not Started | No | 0,0 | 2014-12-12T08:00:00 | 2014-12-18T16:00:00 |
J1240 | Ready for Shipment - LV Trafos | Not Started | Yes | 0,0 | 2014-12-26T08:00:00 | 2014-12-26T08:00:00 |
M1250 | Shipment (Placeholder / MIG Scope) - LV Trafos | Not Started | Yes | 0,0 | 2015-01-02T08:00:00 | 2015-03-02T16:00:00 |
M1260 | At site - LV Trafos | Not Started | Yes | 0,0 | 2015-03-02T16:00:00 | 2015-03-02T16:00:00 |
J1245 | Transport to Port of Export - LV Trafos | Not Started | Yes | 0,0 | 2014-12-26T08:00:00 | 2015-01-01T16:00:00 |
307881 | ICSS SYSTEM | |||||
J1950 | Purchasing - ICSS System | Not Started | Yes | 0,0 | 2014-06-21T12:00:00 | 2014-07-21T12:00:00 |
J1960 | PO placed - ICSS System | Not Started | Yes | 0,0 | 2014-07-21T12:00:00 | 2014-07-21T12:00:00 |
J1970 | Delivery Time (incl. Detail Engineering) - ICSS System | Not Started | Yes | 0,0 | 2014-07-21T12:00:00 | 2015-02-16T12:00:00 |
J1980 | FAT - ICSS System | Not Started | No | 0,0 | 2015-02-02T12:00:00 | 2015-02-09T12:00:00 |
J1990 | Ready for Shipment - ICSS System | Not Started | Yes | 0,0 | 2015-02-16T12:00:00 | 2015-02-16T12:00:00 |
M1930 | Shipment (Placeholder / MIG Scope) - ICSS System | Not Started | Yes | 0,0 | 2015-02-23T12:00:00 | 2015-04-24T12:00:00 |
M1940 | At site - ICSS System | Not Started | Yes | 0,0 | 2015-04-24T12:00:00 | 2015-04-24T12:00:00 |
J1995 | Transport to Port of Export - ICSS System | Not Started | Yes | 0,0 | 2015-02-16T12:00:00 | 2015-02-23T12:00:00 |
307882 | CABLES AND CABLE TRAYS | |||||
J1870 | Purchasing - Cables and Cable Trays | Not Started | Yes | 0,0 | 2014-05-30T08:00:00 | 2014-06-28T16:00:00 |
J1880 | PO placed - Cables and Cable Trays | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2014-06-29T08:00:00 |
J1890 | Delivery Time (incl. Detail Engineering) - Cables and Cable Trays | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2014-11-25T16:00:00 |
J1900 | Ready for Shipment - Cables and Cable Trays | Not Started | Yes | 0,0 | 2014-11-26T08:00:00 | 2014-11-26T08:00:00 |
M1910 | Shipment (Placeholder / MIG Scope) - Cables and Cable Trays | Not Started | Yes | 0,0 | 2014-12-03T08:00:00 | 2015-01-31T16:00:00 |
M1920 | At site - Cables and Cable Trays | Not Started | Yes | 0,0 | 2015-01-31T16:00:00 | 2015-01-31T16:00:00 |
J1905 | Transport to Port of Export - Cables and Cable Trays | Not Started | Yes | 0,0 | 2014-11-26T08:00:00 | 2014-12-02T16:00:00 |
307883 | SMALL POWER SYSTEM | |||||
J1500 | Purchasing - Small Power System | Not Started | Yes | 0,0 | 2014-06-09T08:00:00 | 2014-07-08T16:00:00 |
J1510 | PO placed - Small Power System | Not Started | Yes | 0,0 | 2014-07-09T08:00:00 | 2014-07-09T08:00:00 |
J1520 | Delivery Time (incl. Detail Engineering) - Small Power System | Not Started | Yes | 0,0 | 2014-07-09T08:00:00 | 2015-03-05T16:00:00 |
J1530 | FAT - Small Power System | Not Started | No | 0,0 | 2015-02-20T08:00:00 | 2015-02-26T16:00:00 |
J1540 | Ready for Shipment - Small Power System | Not Started | Yes | 0,0 | 2015-03-06T08:00:00 | 2015-03-06T08:00:00 |
M1550 | Shipment (Placeholder / MIG Scope) - Small Power System | Not Started | Yes | 0,0 | 2015-03-13T08:00:00 | 2015-05-11T16:00:00 |
M1560 | At site - Small Power System | Not Started | Yes | 0,0 | 2015-05-11T16:00:00 | 2015-05-11T16:00:00 |
J1545 | Transport to Port of Export - Small Power System | Not Started | Yes | 0,0 | 2015-03-06T08:00:00 | 2015-03-12T16:00:00 |
307884 | 640 - INERT GAS (NITROGEN) SYSTEM | |||||
307885 | NITROGEN SYSTEM PIPING | |||||
J3230 | Purchasing - Inertgas interconnecting Piping | Not Started | Yes | 0,0 | 2014-05-15T08:00:00 | 2014-07-23T16:00:00 |
J3240 | First PO placed - Inertgas interconnecting Piping | Not Started | Yes | 0,0 | 2014-05-30T08:00:00 | 2014-05-30T08:00:00 |
J3250 | Delivery Time - Inertgas interconnecting Piping | Not Started | Yes | 0,0 | 2014-05-30T08:00:00 | 2014-10-26T16:00:00 |
J3270 | Ready for Shipment - Inertgas interconnecting Piping | Not Started | Yes | 0,0 | 2014-10-27T08:00:00 | 2014-10-27T08:00:00 |
M6100 | Shipment - Inertgas interconnecting Piping | Not Started | Yes | 0,0 | 2014-11-03T08:00:00 | 2014-12-17T16:00:00 |
M6110 | At site - Inertgas interconnecting Piping | Not Started | Yes | 0,0 | 2014-12-17T16:00:00 | 2014-12-17T16:00:00 |
J3275 | Transport to Port of Export - Inertgas interconnecting Piping | Not Started | Yes | 0,0 | 2014-10-27T08:00:00 | 2014-11-02T16:00:00 |
307886 | NITROGEN SYSTEM | |||||
J2430 | Purchasing - Nitrogen System | Not Started | Yes | 0,0 | 2014-05-30T08:00:00 | 2014-06-28T16:00:00 |
J2440 | PO placed - Nitrogen System | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2014-06-29T08:00:00 |
J2450 | Delivery Time (incl. Detail Engineering) - Nitrogen System | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2015-04-24T16:00:00 |
J2460 | FAT - Nitrogen System | Not Started | No | 0,0 | 2015-04-11T08:00:00 | 2015-04-17T16:00:00 |
J2470 | Ready for Shipment - Nitrogen System | Not Started | Yes | 0,0 | 2015-04-25T08:00:00 | 2015-04-25T08:00:00 |
M3100 | Shipment (Placeholder / MIG Scope) - Nitrogen System | Not Started | Yes | 0,0 | 2015-05-02T08:00:00 | 2015-06-15T16:00:00 |
M3110 | At site - Nitrogen System | Not Started | Yes | 0,0 | 2015-06-15T16:00:00 | 2015-06-15T16:00:00 |
J2475 | Transport to Port of Export - Nitrogen System | Not Started | Yes | 0,0 | 2015-04-25T08:00:00 | 2015-05-01T16:00:00 |
307887 | 500 - INDUSTRIAL WATER SYSTEM | |||||
307888 | AQUIFER / PLANT WATER SYSTEM | |||||
J4370 | Purchasing - Aquifer / Plant Water System | Not Started | Yes | 0,0 | 2014-06-12T08:00:00 | 2014-07-11T16:00:00 |
J4380 | PO placed - Aquifer / Plant Water System | Not Started | Yes | 0,0 | 2014-07-12T08:00:00 | 2014-07-12T08:00:00 |
J4390 | Delivery Time (incl. Detail Engineering) - Aquifer / Plant Water System | Not Started | Yes | 0,0 | 2014-07-12T08:00:00 | 2015-02-06T16:00:00 |
J4400 | FAT - Aquifer / Plant Water System | Not Started | No | 0,0 | 2015-01-24T08:00:00 | 2015-01-30T16:00:00 |
J4410 | Ready for Shipment - Aquifer / Plant Water System | Not Started | Yes | 0,0 | 2015-02-07T08:00:00 | 2015-02-07T08:00:00 |
M4420 | Shipment (Placeholder / MIG Scope) - Aquifer / Plant Water System | Not Started | Yes | 0,0 | 2015-02-14T08:00:00 | 2015-03-30T16:00:00 |
M4430 | At site - Aquifer / Plant Water System | Not Started | Yes | 0,0 | 2015-03-30T16:00:00 | 2015-03-30T16:00:00 |
J4415 | Transport to Port of Export - Aquifer / Plant Water System | Not Started | Yes | 0,0 | 2015-02-07T08:00:00 | 2015-02-13T16:00:00 |
307889 | PLANT WATER PIPING | |||||
J4480 | Purchasing - Plant Water Piping | Not Started | Yes | 0,0 | 2014-06-21T08:00:00 | 2014-08-29T16:00:00 |
J4490 | First PO placed - Plant Water Piping | Not Started | Yes | 0,0 | 2014-07-06T08:00:00 | 2014-07-06T08:00:00 |
J4500 | Delivery Time - Plant Water Piping | Not Started | Yes | 0,0 | 2014-07-06T08:00:00 | 2014-12-02T16:00:00 |
J4520 | Ready for Shipment - Plant Water Piping | Not Started | Yes | 0,0 | 2014-12-03T08:00:00 | 2014-12-03T08:00:00 |
M5840 | Shipment - Plant Water Piping | Not Started | Yes | 0,0 | 2014-12-10T08:00:00 | 2015-01-23T16:00:00 |
M5850 | At site - Plant Water Piping | Not Started | Yes | 0,0 | 2015-01-23T16:00:00 | 2015-01-23T16:00:00 |
J4525 | Transport to Port of Export - Plant Water Piping | Not Started | Yes | 0,0 | 2014-12-03T08:00:00 | 2014-12-09T16:00:00 |
307890 | 470 - CHLORINATION SYSTEM | |||||
307891 | CHLORINATION SYSTEM | |||||
J3530 | Purchasing - Chlorination System | Not Started | Yes | 0,0 | 2014-05-30T08:00:00 | 2014-06-28T16:00:00 |
J3540 | PO placed - Chlorination System | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2014-06-29T08:00:00 |
J3550 | Delivery Time - Chlorination System | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2015-01-24T16:00:00 |
J3560 | FAT - Chlorination System | Not Started | No | 0,0 | 2015-01-11T08:00:00 | 2015-01-17T16:00:00 |
J3570 | Ready for Shipment - Chlorination System | Not Started | Yes | 0,0 | 2015-01-25T08:00:00 | 2015-01-25T08:00:00 |
M3580 | Shipment (Placeholder / MIG Scope) - Chlorination System | Not Started | Yes | 0,0 | 2015-02-01T08:00:00 | 2015-03-17T16:00:00 |
M3590 | At site - Chlorination System | Not Started | Yes | 0,0 | 2015-03-17T16:00:00 | 2015-03-17T16:00:00 |
J3575 | Transport to Port of Export - Chlorination System | Not Started | Yes | 0,0 | 2015-01-25T08:00:00 | 2015-01-31T16:00:00 |
307892 | CHLORINATION SYSTEM PIPING | |||||
J3640 | Purchasing - Chlorination System Piping | Not Started | Yes | 0,0 | 2014-06-21T08:00:00 | 2014-08-29T16:00:00 |
J3650 | First PO placed - Chlorination System Piping | Not Started | Yes | 0,0 | 2014-07-06T08:00:00 | 2014-07-06T08:00:00 |
J3660 | Delivery Time - Chlorination System Piping | Not Started | Yes | 0,0 | 2014-07-06T08:00:00 | 2014-12-02T16:00:00 |
J3680 | Ready for Shipment - Chlorination System Piping | Not Started | Yes | 0,0 | 2014-12-03T08:00:00 | 2014-12-03T08:00:00 |
M5780 | Shipment - Chlorination System Piping | Not Started | Yes | 0,0 | 2014-12-10T08:00:00 | 2015-01-23T16:00:00 |
M5790 | At site - Chlorination System Piping | Not Started | Yes | 0,0 | 2015-01-23T16:00:00 | 2015-01-23T16:00:00 |
J3685 | Transport to Port of Export - Chlorination System Piping | Not Started | Yes | 0,0 | 2014-12-03T08:00:00 | 2014-12-09T16:00:00 |
307893 | 530 - FRESH/POTABLE/DEMINERALISED WATER SYSTEM | |||||
307894 | DEMIN WATER SYSTEM PIPING | |||||
J4820 | Purchasing - Demin Water System Piping | Not Started | Yes | 0,0 | 2014-06-21T08:00:00 | 2014-08-29T16:00:00 |
J4830 | First PO placed - Demin Water System Piping | Not Started | Yes | 0,0 | 2014-07-06T08:00:00 | 2014-07-06T08:00:00 |
J4840 | Delivery Time - Demin Water System Piping | Not Started | Yes | 0,0 | 2014-07-06T08:00:00 | 2014-12-02T16:00:00 |
J4860 | Ready for Shipment - Demin Water System Piping | Not Started | Yes | 0,0 | 2014-12-03T08:00:00 | 2014-12-03T08:00:00 |
M5880 | Shipment - Demin Water System Piping | Not Started | Yes | 0,0 | 2014-12-10T08:00:00 | 2015-01-23T16:00:00 |
M5890 | At site - Demin Water System Piping | Not Started | Yes | 0,0 | 2015-01-23T16:00:00 | 2015-01-23T16:00:00 |
J4865 | Transport to Port of Export - Demin Water System Piping | Not Started | Yes | 0,0 | 2014-12-03T08:00:00 | 2014-12-09T16:00:00 |
307895 | DEMIN WATER SYSTEM | |||||
J4650 | Purchasing - Demin Water System | Not Started | Yes | 0,0 | 2014-05-30T08:00:00 | 2014-06-28T16:00:00 |
J4660 | PO placed - Demin Water System | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2014-06-29T08:00:00 |
J4670 | Delivery Time (incl. Detail Engineering) - Demin Water System | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2015-01-24T16:00:00 |
J4680 | FAT - Demin Water System | Not Started | No | 0,0 | 2015-01-11T08:00:00 | 2015-01-17T16:00:00 |
J4690 | Ready for Shipment - Demin Water System | Not Started | Yes | 0,0 | 2015-01-25T08:00:00 | 2015-01-25T08:00:00 |
M4700 | Shipment (Placeholder / MIG Scope) - Demin Water System | Not Started | Yes | 0,0 | 2015-02-01T08:00:00 | 2015-03-17T16:00:00 |
M4710 | At site - Demin Water System | Not Started | Yes | 0,0 | 2015-03-17T16:00:00 | 2015-03-17T16:00:00 |
J4695 | Transport to Port of Export - Demin Water System | Not Started | Yes | 0,0 | 2015-01-25T08:00:00 | 2015-01-31T16:00:00 |
307896 | FRESH WATER SYSTEM | |||||
J4540 | Purchasing - Fresh Water System | Not Started | Yes | 0,0 | 2014-05-30T08:00:00 | 2014-06-28T16:00:00 |
J4550 | PO placed - Fresh Water System | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2014-06-29T08:00:00 |
J4560 | Delivery Time (incl. Detail Engineering) - Fresh Water System | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2015-01-24T16:00:00 |
J4570 | FAT - Fresh Water System | Not Started | No | 0,0 | 2015-01-11T08:00:00 | 2015-01-17T16:00:00 |
J4580 | Ready for Shipment - Fresh Water System | Not Started | Yes | 0,0 | 2015-01-25T08:00:00 | 2015-01-25T08:00:00 |
M4590 | Shipment (Placeholder / MIG Scope) - Fresh Water System | Not Started | Yes | 0,0 | 2015-02-01T08:00:00 | 2015-03-17T16:00:00 |
M4600 | At site - Fresh Water System | Not Started | Yes | 0,0 | 2015-03-17T16:00:00 | 2015-03-17T16:00:00 |
J4585 | Transport to Port of Export - Fresh Water System | Not Started | Yes | 0,0 | 2015-01-25T08:00:00 | 2015-01-31T16:00:00 |
307897 | FRESH WATER SYSTEM PIPING | |||||
J4760 | Purchasing - Fresh Water System Piping | Not Started | Yes | 0,0 | 2014-06-21T08:00:00 | 2014-08-29T16:00:00 |
J4770 | First PO placed - Fresh Water System Piping | Not Started | Yes | 0,0 | 2014-07-06T08:00:00 | 2014-07-06T08:00:00 |
J4780 | Delivery Time - Fresh Water System Piping | Not Started | Yes | 0,0 | 2014-07-06T08:00:00 | 2014-12-02T16:00:00 |
J4800 | Ready for Shipment - Fresh Water System Piping | Not Started | Yes | 0,0 | 2014-12-03T08:00:00 | 2014-12-03T08:00:00 |
M5860 | Shipment - Fresh Water System Piping | Not Started | Yes | 0,0 | 2014-12-10T08:00:00 | 2015-01-23T16:00:00 |
M5870 | At site - Fresh Water System Piping | Not Started | Yes | 0,0 | 2015-01-23T16:00:00 | 2015-01-23T16:00:00 |
J4805 | Transport to Port of Export - Fresh Water System Piping | Not Started | Yes | 0,0 | 2014-12-03T08:00:00 | 2014-12-09T16:00:00 |
307898 | 570 - CLOSED DRAINS SYSTEM | |||||
M3601 | Purchasing - Closed Drains System | Not Started | Yes | 0,0 | 2014-07-20T08:00:00 | 2014-08-19T16:00:00 |
M3602 | PO placed - Closed Drains System | Not Started | Yes | 0,0 | 2014-08-19T16:00:00 | 2014-08-19T16:00:00 |
M3604 | Ready for Shipment - Closed Drains System | Not Started | Yes | 0,0 | 2014-11-19T16:00:00 | 2014-11-19T16:00:00 |
M3603 | Delievery Time - Closed Drains System | Not Started | Yes | 0,0 | 2014-08-20T08:00:00 | 2014-11-19T16:00:00 |
M3605 | Shipment - Closed Drains System | Not Started | Yes | 0,0 | 2014-11-20T08:00:00 | 2014-12-22T16:00:00 |
M3606 | At site - Closed Drains System | Not Started | No | 0,0 | 2014-12-22T16:00:00 | 2014-12-22T16:00:00 |
307899 | CONNECTING PIPING | |||||
307900 | 710 - FIRE WATER SYSTEM | |||||
M3901 | Purchasing - Fire Water System | Not Started | Yes | 0,0 | 2014-07-20T08:00:00 | 2014-08-19T16:00:00 |
M3902 | PO placed - Fire Water System | Not Started | Yes | 0,0 | 2014-08-19T16:00:00 | 2014-08-19T16:00:00 |
M3904 | Ready for Shipment - Fire Water System | Not Started | Yes | 0,0 | 2014-11-18T16:00:00 | 2014-11-18T16:00:00 |
M3903 | Delievery Time - Fire Water System | Not Started | Yes | 0,0 | 2014-08-20T08:00:00 | 2014-11-18T16:00:00 |
M3905 | Shipment - Fire Water System | Not Started | Yes | 0,0 | 2014-11-19T08:00:00 | 2014-12-20T16:00:00 |
M3906 | At site - Fire Water System | Not Started | No | 0,0 | 2014-12-20T16:00:00 | 2014-12-20T16:00:00 |
307901 | 660 - SEWAGE TREATMENT SYSTEM | |||||
M3801 | Purchasing - Sewage Treatment System | Not Started | Yes | 0,0 | 2014-07-20T08:00:00 | 2014-08-19T16:00:00 |
M3802 | PO placed - Sewage Treatment System | Not Started | Yes | 0,0 | 2014-08-19T16:00:00 | 2014-08-19T16:00:00 |
M3804 | Ready for Shipment - Sewage Treatment System | Not Started | Yes | 0,0 | 2014-12-02T16:00:00 | 2014-12-02T16:00:00 |
M3803 | Delievery Time - Sewage Treatment System | Not Started | Yes | 0,0 | 2014-08-20T08:00:00 | 2014-12-02T16:00:00 |
M3805 | Shipment - Sewage Treatment System | Not Started | Yes | 0,0 | 2014-12-03T08:00:00 | 2015-01-03T16:00:00 |
M3806 | At site - Sewage Treatment System | Not Started | No | 0,0 | 2015-01-03T16:00:00 | 2015-01-03T16:00:00 |
307902 | VESSELS, OFF-PACKAGE | |||||
F5460 | Purchasing - Vessels off-package | Not Started | Yes | 0,0 | 2014-05-04T08:00:00 | 2014-07-19T16:00:00 |
F5470 | PO placed - Vessels off-package | Not Started | Yes | 0,0 | 2014-07-19T16:00:00 | 2014-07-19T16:00:00 |
F5490 | Ready for Shipment - Vessels off-package | Not Started | Yes | 0,0 | 2015-05-23T16:00:00 | 2015-05-23T16:00:00 |
F5480 | Delievery Time - Vessels off-package | Not Started | Yes | 0,0 | 2014-07-20T08:00:00 | 2015-05-23T16:00:00 |
M5500 | Shipment - Vessels off-package | Not Started | Yes | 0,0 | 2015-05-31T08:00:00 | 2015-07-29T16:00:00 |
M5510 | At site - Vessels off-package | Not Started | No | 0,0 | 2015-07-29T16:00:00 | 2015-07-29T16:00:00 |
F5495 | Transport to Port of Export - Vessels off-package | Not Started | Yes | 0,0 | 2015-05-24T08:00:00 | 2015-05-30T16:00:00 |
307903 | 830 - EMERGENCY POWER GENERATORS SYSTEM | |||||
J5230 | Purchasing - Emergency Power Generator | Not Started | Yes | 0,0 | 2014-05-30T08:00:00 | 2014-06-28T16:00:00 |
J5240 | PO placed - Emergency Power Generator | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2014-06-29T08:00:00 |
J5250 | Delivery Time (incl. Detail Engineering) - Emergency Power Generator | Not Started | Yes | 0,0 | 2014-06-29T08:00:00 | 2014-12-25T16:00:00 |
J5260 | FAT - Emergency Power Generator | Not Started | No | 0,0 | 2014-12-12T08:00:00 | 2014-12-18T16:00:00 |
J5270 | Ready for Shipment - Emergency Power Generator | Not Started | Yes | 0,0 | 2014-12-26T08:00:00 | 2014-12-26T08:00:00 |
M5285 | Shipment (Placeholder / MIG Scope) - Emergency Power Generator | Not Started | Yes | 0,0 | 2015-01-02T08:00:00 | 2015-02-15T16:00:00 |
M5295 | At site - Emergency Power Generator | Not Started | Yes | 0,0 | 2015-02-15T16:00:00 | 2015-02-15T16:00:00 |
J5275 | Transport to Port of Export - Emergency Power Generator | Not Started | Yes | 0,0 | 2014-12-26T08:00:00 | 2015-01-01T16:00:00 |
307904 | 800 - MAIN POWER GENERATION SYSTEM | |||||
307905 | GAS TURBINE SYSTEM | |||||
J3130 | Purchasing - Gas Turbine System | Not Started | Yes | 0,0 | 2014-05-30T08:00:00 | 2014-07-28T16:00:00 |
J3140 | PO placed - Gas Turbine System | Not Started | Yes | 0,0 | 2014-07-29T08:00:00 | 2014-07-29T08:00:00 |
J3150 | Delivery Time (incl. Detail Engineering) - Gas Turbine System | Not Started | Yes | 0,0 | 2014-07-29T08:00:00 | 2015-07-28T16:00:00 |
J3160 | FAT - Gas Turbine System | Not Started | No | 0,0 | 2015-07-15T08:00:00 | 2015-07-21T16:00:00 |
J3170 | Ready for Shipment - Gas Turbine System | Not Started | Yes | 0,0 | 2015-07-29T08:00:00 | 2015-07-29T08:00:00 |
M3180 | Shipment (Placeholder / MIG Scope) - Gas Turbine System | Not Started | Yes | 0,0 | 2015-08-05T08:00:00 | 2015-09-18T16:00:00 |
M3190 | At site - Gas Turbine System | Not Started | Yes | 0,0 | 2015-09-18T16:00:00 | 2015-09-18T16:00:00 |
J3175 | Transport to Port of Export - Gas Turbine System | Not Started | Yes | 0,0 | 2015-07-29T08:00:00 | 2015-08-04T16:00:00 |
307906 | 280 - GAS SWEETENING (AMINE) SYSTEM | |||||
F2320 | Purchasing - Gas Sweetening (Amine) System | Not Started | Yes | 0,0 | 2014-04-26T08:00:00 | 2014-06-06T16:00:00 |
F2330 | PO placed - Gas Sweetening (Amine) System | Not Started | Yes | 0,0 | 2014-06-06T16:00:00 | 2014-06-06T16:00:00 |
F2350 | Ready for Shipment - Gas Sweetening (Amine) System | Not Started | Yes | 0,0 | 2015-04-24T16:00:00 | 2015-04-24T16:00:00 |
F2340 | Delievery Time - Gas Sweetening (Amine) System | Not Started | Yes | 0,0 | 2014-06-07T08:00:00 | 2015-04-24T16:00:00 |
M2360 | Shipment - Gas Sweetening (Amine) System | Not Started | Yes | 0,0 | 2015-05-02T08:00:00 | 2015-06-15T16:00:00 |
M2370 | At site - Gas Sweetening (Amine) System | Not Started | Yes | 0,0 | 2015-06-15T16:00:00 | 2015-06-15T16:00:00 |
F2355 | Transport to Port of Export - Gas Sweetening (Amine) System | Not Started | Yes | 0,0 | 2015-04-25T08:00:00 | 2015-05-01T16:00:00 |
307907 | 250 - GAS CONDITIONING (DEW POINTING) SYSTEM | |||||
F2080 | Purchasing - Gas Conditioning (Dew Pointing) System | Not Started | Yes | 0,0 | 2014-04-19T08:00:00 | 2014-05-30T16:00:00 |
F2090 | PO placed - Gas Conditioning (Dew Pointing) System | Not Started | Yes | 0,0 | 2014-05-30T16:00:00 | 2014-05-30T16:00:00 |
F2110 | Ready for Shipment - Gas Conditioning (Dew Pointing) System | Not Started | Yes | 0,0 | 2015-05-30T16:00:00 | 2015-05-30T16:00:00 |
F2100 | Delievery Time - Gas Conditioning (Dew Pointing) System | Not Started | Yes | 0,0 | 2014-05-31T08:00:00 | 2015-05-30T16:00:00 |
M2120 | Shipment - Gas Conditioning (Dew Pointing) System | Not Started | Yes | 0,0 | 2015-06-07T08:00:00 | 2015-07-21T16:00:00 |
M2130 | At site - Gas Conditioning (Dew Pointing) System | Not Started | Yes | 0,0 | 2015-07-21T16:00:00 | 2015-07-21T16:00:00 |
F2115 | Transport to Port of Export - Gas Conditioning (Dew Pointing) System | Not Started | Yes | 0,0 | 2015-05-31T08:00:00 | 2015-06-06T16:00:00 |
307908 | 620 - DIESEL OIL SYSTEM | |||||
M3701 | Purchasing - Diesel Oil System | Not Started | Yes | 0,0 | 2014-05-24T08:00:00 | 2014-06-23T16:00:00 |
M3702 | PO placed - Diesel Oil System | Not Started | Yes | 0,0 | 2014-06-23T16:00:00 | 2014-06-23T16:00:00 |
M3704 | Ready for Shipment - Diesel Oil System | Not Started | Yes | 0,0 | 2014-08-14T16:00:00 | 2014-08-14T16:00:00 |
M3703 | Delievery Time - Diesel Oil System | Not Started | Yes | 0,0 | 2014-06-24T08:00:00 | 2014-08-14T16:00:00 |
M3705 | Shipment - Diesel Oil System | Not Started | No | 0,0 | 2014-08-16T08:00:00 | 2014-09-15T16:00:00 |
M3706 | At site - Diesel Oil System | Not Started | No | 0,0 | 2014-09-30T08:00:00 | 2014-09-30T08:00:00 |
307909 | EQUIPMENT, OFF-PACKAGE | |||||
F5400 | Purchasing - Equipment off-package | Not Started | Yes | 0,0 | 2014-05-04T08:00:00 | 2014-07-19T16:00:00 |
F5410 | PO placed - Equipment off-package | Not Started | Yes | 0,0 | 2014-07-19T16:00:00 | 2014-07-19T16:00:00 |
F5430 | Ready for Shipment - Equipment off-package | Not Started | Yes | 0,0 | 2015-05-23T16:00:00 | 2015-05-23T16:00:00 |
F5420 | Delievery Time - Equipment off-package | Not Started | Yes | 0,0 | 2014-07-20T08:00:00 | 2015-05-23T16:00:00 |
M5440 | Shipment - Equipment off-package | Not Started | Yes | 0,0 | 2015-05-31T08:00:00 | 2015-07-29T16:00:00 |
M5450 | At site - Equipment off-package | Not Started | No | 0,0 | 2015-07-29T16:00:00 | 2015-07-29T16:00:00 |
F5435 | Transport to Port of Export - Equipment off-package | Not Started | Yes | 0,0 | 2015-05-24T08:00:00 | 2015-05-30T16:00:00 |
307910 | 250 - GAS CONDITIONING (DEHYDRATION) SYSTEM | |||||
F1960 | Purchasing - Gas Conditioning (Dehydration) System | Not Started | Yes | 0,0 | 2014-04-19T08:00:00 | 2014-05-30T16:00:00 |
F1970 | PO placed - Gas Conditioning (Dehydration) System | Not Started | Yes | 0,0 | 2014-05-30T16:00:00 | 2014-05-30T16:00:00 |
F1990 | Ready for Shipment - Gas Conditioning (Dehydration) System | Not Started | Yes | 0,0 | 2015-05-30T16:00:00 | 2015-05-30T16:00:00 |
F1980 | Delievery Time - Gas Conditioning (Dehydration) System | Not Started | Yes | 0,0 | 2014-05-31T08:00:00 | 2015-05-30T16:00:00 |
M2000 | Shipment - Gas Conditioning (Dehydration) System | Not Started | Yes | 0,0 | 2015-06-07T08:00:00 | 2015-07-21T16:00:00 |
M2010 | At site - Gas Conditioning (Dehydration) System | Not Started | Yes | 0,0 | 2015-07-21T16:00:00 | 2015-07-21T16:00:00 |
F1995 | Transport to Port of Export - Gas Conditioning (Dehydration) System | Not Started | Yes | 0,0 | 2015-05-31T08:00:00 | 2015-06-06T16:00:00 |
307911 | 360 - WELL FLOWLINES SYSTEM | |||||
307912 | WELL HEAD FLOWLINES | |||||
J3720 | Purchasing - Well Flowlines | Not Started | Yes | 0,0 | 2014-06-09T08:00:00 | 2014-08-07T16:00:00 |
J3730 | PO placed - Well Flowlines | Not Started | Yes | 0,0 | 2014-08-08T08:00:00 | 2014-08-08T08:00:00 |
J3740 | Delivery Time - Well Flowlines | Not Started | Yes | 0,0 | 2014-08-08T08:00:00 | 2015-02-03T16:00:00 |
J3760 | Ready for Shipment - (100%) Well Flowlines | Not Started | Yes | 0,0 | 2015-02-04T08:00:00 | 2015-02-04T08:00:00 |
M3105 | Shipment - (100%) Well Flowlines | Not Started | Yes | 0,0 | 2015-02-11T08:00:00 | 2015-04-04T16:00:00 |
M3106 | At site - (100%) Well Flowlines | Not Started | Yes | 0,0 | 2015-04-04T16:00:00 | 2015-04-04T16:00:00 |
J3765 | Transport to Port of Export - (100%) Well Flowlines | Not Started | Yes | 0,0 | 2015-02-04T08:00:00 | 2015-02-10T16:00:00 |
J5425 | Ready for Shipment - (30%) Well Flowlines | Not Started | Yes | 0,0 | 2014-10-07T08:00:00 | 2014-10-07T08:00:00 |
M5445 | Shipment - (30%) Well Flowlines | Not Started | Yes | 0,0 | 2014-10-14T08:00:00 | 2014-12-04T16:00:00 |
M5455 | At site - (30%) Well Flowlines | Not Started | Yes | 0,0 | 2014-12-04T16:00:00 | 2014-12-04T16:00:00 |
J5435 | Transport to Port of Export - (30%) Well Flowlines | Not Started | Yes | 0,0 | 2014-10-07T08:00:00 | 2014-10-13T16:00:00 |
J5445 | Ready for Shipment - (60%) Well Flowlines | Not Started | Yes | 0,0 | 2014-12-06T08:00:00 | 2014-12-06T08:00:00 |
M5465 | Shipment - (60%) Well Flowlines | Not Started | Yes | 0,0 | 2014-12-13T08:00:00 | 2015-02-02T16:00:00 |
M5475 | At site - (60%) Well Flowlines | Not Started | Yes | 0,0 | 2015-02-02T16:00:00 | 2015-02-02T16:00:00 |
J5455 | Transport to Port of Export - (60%) Well Flowlines | Not Started | Yes | 0,0 | 2014-12-06T08:00:00 | 2014-12-12T16:00:00 |
307913 | METHANOL LINES | |||||
J3780 | Purchasing - Methanol lines | Not Started | Yes | 0,0 | 2014-06-09T08:00:00 | 2014-08-07T16:00:00 |
J3790 | PO placed - Methanol lines | Not Started | Yes | 0,0 | 2014-08-08T08:00:00 | 2014-08-08T08:00:00 |
J3800 | Delivery Time - Methanol lines | Not Started | Yes | 0,0 | 2014-08-08T08:00:00 | 2015-02-03T16:00:00 |
J3820 | Ready for Shipment - (100%) Methanol lines | Not Started | Yes | 0,0 | 2015-02-04T08:00:00 | 2015-02-04T08:00:00 |
M5660 | Shipment - (100%) Methanol lines | Not Started | Yes | 0,0 | 2015-02-11T08:00:00 | 2015-04-04T16:00:00 |
M5670 | At site - (100%) Methanol lines | Not Started | Yes | 0,0 | 2015-04-04T16:00:00 | 2015-04-04T16:00:00 |
J3825 | Transport to Port of Export - (100%) Methanol lines | Not Started | Yes | 0,0 | 2015-02-04T08:00:00 | 2015-02-10T16:00:00 |
J5465 | Ready for Shipment - (30%) Methanol lines | Not Started | Yes | 0,0 | 2014-10-07T08:00:00 | 2014-10-07T08:00:00 |
M5485 | Shipment - (30%) Methanol lines | Not Started | Yes | 0,0 | 2014-10-14T08:00:00 | 2014-12-04T16:00:00 |
M5495 | At site - (30%) Methanol lines | Not Started | No | 0,0 | 2014-12-04T16:00:00 | 2014-12-04T16:00:00 |
J5475 | Transport to Port of Export - (30%) Methanol lines | Not Started | Yes | 0,0 | 2014-10-07T08:00:00 | 2014-10-13T16:00:00 |
J5485 | Ready for Shipment - (60%) Methanol lines | Not Started | Yes | 0,0 | 2014-12-06T08:00:00 | 2014-12-06T08:00:00 |
M5505 | Shipment - (60%) Methanol lines | Not Started | Yes | 0,0 | 2014-12-13T08:00:00 | 2015-02-02T16:00:00 |
M5515 | At site - (60%) Methanol lines | Not Started | Yes | 0,0 | 2015-02-02T16:00:00 | 2015-02-02T16:00:00 |
J5495 | Transport to Port of Export - (60%) Methanol lines | Not Started | Yes | 0,0 | 2014-12-06T08:00:00 | 2014-12-12T16:00:00 |
307914 | WELL FLOWLINES SKID | |||||
F4890 | Purchasing - Well Flowlines System | Not Started | Yes | 0,0 | 2014-05-03T08:00:00 | 2014-06-13T16:00:00 |
F4900 | PO placed - Well Flowlines System | Not Started | Yes | 0,0 | 2014-06-13T16:00:00 | 2014-06-13T16:00:00 |
F4920 | Ready for Shipment - Well Flowlines System | Not Started | Yes | 0,0 | 2015-04-03T16:00:00 | 2015-04-03T16:00:00 |
F4910 | Delievery Time - Well Flowlines System | Not Started | Yes | 0,0 | 2014-06-14T08:00:00 | 2015-04-03T16:00:00 |
M4930 | Shipment - Well Flowlines System | Not Started | Yes | 0,0 | 2015-04-11T08:00:00 | 2015-05-25T16:00:00 |
M4940 | At site - Well Flowlines System | Not Started | No | 0,0 | 2015-05-25T16:00:00 | 2015-05-25T16:00:00 |
F4925 | Transport to Port of Export - Well Flowlines System | Not Started | Yes | 0,0 | 2015-04-04T08:00:00 | 2015-04-10T16:00:00 |
307915 | Structural Steel & Steel Plate | |||||
M310101 | Purchasing - Structural Steel & Steel Plate | Not Started | Yes | 0,0 | 2014-06-01T08:00:00 | 2014-06-30T16:00:00 |
M310102 | PO placed - Structural Steel & Steel Plate | Not Started | Yes | 0,0 | 2014-07-01T08:00:00 | 2014-07-01T08:00:00 |
M310103 | Delivery Time ( 60%) - Structural Steel & Steel Plate | Not Started | Yes | 0,0 | 2014-07-01T08:00:00 | 2014-08-31T16:00:00 |
M310104 | Delivery Time ( 35%) - Structural Steel & Steel Plate | Not Started | Yes | 0,0 | 2014-09-01T08:00:00 | 2014-10-02T16:00:00 |
M310105 | Delivery Time ( 5%) - Structural Steel & Steel Plate | Not Started | No | 0,0 | 2014-10-04T08:00:00 | 2014-10-14T16:00:00 |
307916 | MIG WORKSHOP FABRICATION | |||||
M312001 | Pressure Vessels | Not Started | No | 0,0 | 2014-09-01T08:00:00 | 2014-11-20T16:00:00 |
M312002 | Tanks | Not Started | No | 0,0 | 2014-09-01T08:00:00 | 2014-10-16T16:00:00 |
M312003 | Piping | Not Started | No | 0,0 | 2014-09-01T08:00:00 | 2014-12-25T16:00:00 |
307917 | COMMISSIONING, PERFORMANCE TEST | |||||
307918 | COMMISSIONING UTILITIES | |||||
F0790 | Commissioning - System 270 | Not Started | Yes | 0,0 | 2015-10-19T08:00:00 | 2015-11-01T16:00:00 |
F0820 | Commissioning - System 330 | Not Started | Yes | 0,0 | 2015-10-25T08:00:00 | 2015-11-07T16:00:00 |
F0860 | Commissioning - System 420 | Not Started | Yes | 0,0 | 2015-09-19T08:00:00 | 2015-10-15T16:00:00 |
F0920 | Commissioning - System 470 | Not Started | Yes | 0,0 | 2015-09-19T08:00:00 | 2015-10-15T16:00:00 |
F0940 | Commissioning - System 500 | Not Started | Yes | 0,0 | 2015-09-19T08:00:00 | 2015-10-15T16:00:00 |
F0950 | Commissioning - System 530 | Not Started | Yes | 0,0 | 2015-09-19T08:00:00 | 2015-10-15T16:00:00 |
F0960 | Commissioning - System 560 | Not Started | Yes | 0,0 | 2015-09-19T08:00:00 | 2015-10-15T16:00:00 |
F0970 | Commissioning - System 570 | Not Started | Yes | 0,0 | 2015-09-19T08:00:00 | 2015-10-15T16:00:00 |
F0980 | Commissioning - System 620 | Not Started | Yes | 0,0 | 2015-09-19T08:00:00 | 2015-10-15T16:00:00 |
F0990 | Commissioning - System 630 | Not Started | Yes | 0,0 | 2015-10-17T08:00:00 | 2015-10-29T16:00:00 |
F1000 | Commissioning - System 640 | Not Started | Yes | 0,0 | 2015-10-17T08:00:00 | 2015-10-29T16:00:00 |
F1010 | Commissioning - System 660 | Not Started | Yes | 0,0 | 2015-09-19T08:00:00 | 2015-10-15T16:00:00 |
F1020 | Commissioning - System 710 | Not Started | Yes | 0,0 | 2015-09-19T08:00:00 | 2015-10-15T16:00:00 |
F1040 | Commissioning - System 830 | Not Started | Yes | 0,0 | 2015-09-19T08:00:00 | 2015-10-15T16:00:00 |
F0815 | Commissioning - System 410 | Not Started | Yes | 0,0 | 2015-09-19T08:00:00 | 2015-10-15T16:00:00 |
307919 | COMMISSIONING GROUP A | |||||
F0720 | Commissioning - System 200 | Not Started | Yes | 0,0 | 2015-11-01T08:00:00 | 2015-11-28T16:00:00 |
F0730 | Commissioning - System 210 | Not Started | Yes | 0,0 | 2015-11-01T08:00:00 | 2015-11-28T16:00:00 |
F0740 | Commissioning - System 220 | Not Started | Yes | 0,0 | 2015-11-01T08:00:00 | 2015-11-28T16:00:00 |
F0750 | Commissioning - System 232 | Not Started | Yes | 0,0 | 2015-11-01T08:00:00 | 2015-11-28T16:00:00 |
307920 | COMMISSIONING GROUP B | |||||
F0760 | Commissioning - System 240 | Not Started | Yes | 0,0 | 2015-11-01T08:00:00 | 2015-12-12T16:00:00 |
F0770 | Commissioning - System 250A | Not Started | Yes | 0,0 | 2015-11-04T08:00:00 | 2015-12-15T16:00:00 |
F0800 | Commissioning - System 280 | Not Started | Yes | 0,0 | 2015-11-03T08:00:00 | 2015-12-14T16:00:00 |
307921 | COMMISSIONING GROUP C | |||||
F0830 | Commissioning - System 400 | Not Started | Yes | 0,0 | 2015-12-16T08:00:00 | 2015-12-29T16:00:00 |
F0780 | Commissioning - System 250B | Not Started | Yes | 0,0 | 2015-12-16T08:00:00 | 2015-12-29T16:00:00 |
307922 | COMMISSIONING GROUP D | |||||
F0930 | Commissioning - System 480 | Not Started | Yes | 0,0 | 2015-12-16T08:00:00 | 2015-12-22T16:00:00 |
307923 | COMMISSIONING GROUP E | |||||
F0840 | Commissioning - System 410 | Not Started | Yes | 0,0 | 2015-12-16T08:00:00 | 2016-01-05T16:00:00 |
F0870 | Commissioning - System 430 | Not Started | Yes | 0,0 | 2015-12-16T08:00:00 | 2016-01-05T16:00:00 |
F0880 | Commissioning - System 440 | Not Started | Yes | 0,0 | 2015-12-16T08:00:00 | 2016-01-05T16:00:00 |
F0910 | Commissioning - System 460 | Not Started | Yes | 0,0 | 2015-12-16T08:00:00 | 2016-01-05T16:00:00 |
307924 | COMMISSIONING GROUP F | |||||
F6090 | First Fire | Not Started | Yes | 0,0 | 2016-01-20T08:00:00 | 2016-01-20T08:00:00 |
F6100 | First Synchronization | Not Started | No | 0,0 | 2016-01-27T08:00:00 | 2016-01-27T08:00:00 |
F6110 | Energizing | Not Started | Yes | 0,0 | 2015-11-04T08:00:00 | 2016-01-05T16:00:00 |
F0890 | Commissioning - System 450 | Not Started | Yes | 0,0 | 2015-12-16T08:00:00 | 2016-01-05T16:00:00 |
F1030 | Commissioning - System 800 | Not Started | Yes | 0,0 | 2016-01-06T08:00:00 | 2016-03-01T16:00:00 |
307925 | COMMISSIONING WELL HEAD, FLOWLINES | |||||
F0710 | Commissioning - System 110 (1-3) | Not Started | No | 0,0 | 2015-09-19T08:00:00 | 2015-09-29T16:00:00 |
F0714 | Commissioning - System 110 (4-6) | Not Started | No | 0,0 | 2015-10-04T08:00:00 | 2015-10-14T16:00:00 |
F0718 | Commissioning - System 110 (7-9) | Not Started | Yes | 0,0 | 2015-11-01T08:00:00 | 2015-11-11T16:00:00 |
F5660 | Start Commissioning | Not Started | Yes | 0,0 | 2015-09-19T08:00:00 | 2015-09-19T08:00:00 |
307926 | COMMISSIONING ELECTRICAL, I&C EQUIPMENT | |||||
J1390 | Commissioning - Frequency Inverter | Not Started | Yes | 0,0 | 2015-10-19T08:00:00 | 2015-11-03T16:00:00 |
307927 | PERFORMANCE TEST | |||||
F5640 | Prepartion of Performance Test | Not Started | Yes | 0,0 | 2016-03-02T08:00:00 | 2016-03-03T16:00:00 |
F5645 | Overall Performance Test (Minimum Capacity) | Not Started | Yes | 0,0 | 2016-03-04T08:00:00 | 2016-03-05T16:00:00 |
F5650 | Overall Performance Test (Full Capacity) | Not Started | Yes | 0,0 | 2016-03-06T08:00:00 | 2016-03-08T16:00:00 |
307929 | COMMISSIONING |
Unique ID | Title | Author | Description | External Document Key | Deliverable | Document Category | Revision Date |
Unique ID | WBS Code | WBS Name | Project Status | Sort Order | Project Node | Project | WBS Category | Parent WBS | Original Budget | Independent ETC Total Cost | Independent ETC Labor Units | Responsible Manager | User Reviewing Status | Contains Summary Data | Methodology Global Unique ID | ||
307477 | Nawara - CPF, Wellpads, Flowlines - Rev. 0 (25.11.2013) | ||||||||||||||||
307478 | PROJECT MILESTONES AND GENERAL ITEMS | ||||||||||||||||
307479 | ENGINEERING | ||||||||||||||||
307480 | EXHIBIT C - KEY DATES | ||||||||||||||||
307481 | ENGINEERING BY DISCIPLINES | ||||||||||||||||
307482 | Fire and Safety | ||||||||||||||||
307483 | CIVIL | ||||||||||||||||
307484 | Civil, Structural and Buildings | ||||||||||||||||
307485 | ROTATING/STATIC EQUIPMENT, HVAC | ||||||||||||||||
307486 | HVAC Engineering | ||||||||||||||||
307487 | General | ||||||||||||||||
307488 | STATIC EQUIPMENT | ||||||||||||||||
307489 | Mechanical and Equipment | ||||||||||||||||
307490 | Tanks | ||||||||||||||||
307491 | STEEL STRUCTURE | ||||||||||||||||
307492 | HSE | ||||||||||||||||
307493 | ELECTRICAL | ||||||||||||||||
307494 | PROCESS | ||||||||||||||||
307495 | Corrosion Control and Mettalurgy | ||||||||||||||||
307496 | AUXILIARY EQUIPMENT | ||||||||||||||||
307497 | AUTOMATION, INSTRUMENTATION, CONTROL | ||||||||||||||||
307498 | PIPING | ||||||||||||||||
307499 | Insulation | ||||||||||||||||
307500 | Flowline | ||||||||||||||||
307501 | BASIC ENGINEERING INCL. FEED ENDORSEMENT | ||||||||||||||||
307502 | FINAL DOCUMENTATION | ||||||||||||||||
307503 | FLOWLINE & WELL HEAD | ||||||||||||||||
307504 | CPF | ||||||||||||||||
307505 | As-Built_Common | ||||||||||||||||
307506 | CONSTRUCTION | ||||||||||||||||
307507 | 570 - CLOSED DRAINS SYSTEM | ||||||||||||||||
307508 | Civil & Structural | ||||||||||||||||
307509 | Piping | ||||||||||||||||
307510 | Mechanical / Eq | ||||||||||||||||
307511 | Electrical | ||||||||||||||||
307512 | Instrumentation & Telecomm | ||||||||||||||||
307513 | Paiting & Insulation | ||||||||||||||||
307514 | Pre-commissioning | ||||||||||||||||
307515 | 440 - PRODUCED WATER AND EVAPORATION POND SYSTEM | ||||||||||||||||
307516 | Civil & Structural | ||||||||||||||||
307517 | Piping | ||||||||||||||||
307518 | Electrical | ||||||||||||||||
307519 | Instrumentation & Telecomm | ||||||||||||||||
307520 | Paiting & Insulation | ||||||||||||||||
307521 | Pre-commissioning | ||||||||||||||||
307522 | Mechanical / Eq | ||||||||||||||||
307523 | 330 - CONDENSATE STORAGE AND METERING SYSTEM | ||||||||||||||||
307524 | Pre-commissioning | ||||||||||||||||
307525 | Civil & Structural | ||||||||||||||||
307526 | Electrical | ||||||||||||||||
307527 | Piping | ||||||||||||||||
307528 | Instrumentation & Telecomm | ||||||||||||||||
307529 | Paiting & Insulation | ||||||||||||||||
307530 | Mechanical / Eq | ||||||||||||||||
307531 | CIVIL, STRUCTURAL STEEL | ||||||||||||||||
307532 | 220 - GAS RECEPTION SYSTEM | ||||||||||||||||
307533 | Civil & Structural | ||||||||||||||||
307534 | Piping | ||||||||||||||||
307535 | Electrical | ||||||||||||||||
307536 | Instrumentation & Telecommunication | ||||||||||||||||
307537 | Pre-commissioning | ||||||||||||||||
307538 | Mechanical / Equipment | ||||||||||||||||
307539 | Paiting & Insulation | ||||||||||||||||
307540 | 400 - COOLING MEDIUM (PROPANE) SYSTEM | ||||||||||||||||
307541 | Piping | ||||||||||||||||
307542 | Civil & Structural | ||||||||||||||||
307543 | Electrical | ||||||||||||||||
307544 | Instrumentation & Telecomm | ||||||||||||||||
307545 | Paiting & Insulation | ||||||||||||||||
307546 | Mechanical / Eq | ||||||||||||||||
307547 | Pre-commissioining | ||||||||||||||||
307548 | COMMON | ||||||||||||||||
307549 | Site Preparation | ||||||||||||||||
307550 | Temporary Facilities | ||||||||||||||||
307551 | Field Engineering | ||||||||||||||||
307552 | Mobilization | ||||||||||||||||
307553 | Tie - ins | ||||||||||||||||
307554 | 830 - EMERGENCY POWER GENERATORS SYSTEM | ||||||||||||||||
307555 | Civil & Structural | ||||||||||||||||
307556 | Piping | ||||||||||||||||
307557 | Mechanical / Eq | ||||||||||||||||
307558 | Electrical | ||||||||||||||||
307559 | Paiting & Insulation | ||||||||||||||||
307560 | Pre-commissioning | ||||||||||||||||
307561 | Instrumentation & Telecomm | ||||||||||||||||
307562 | 630 - INSTRUMENT AND PLANT AIR SYSTEM | ||||||||||||||||
307563 | Civil & Structural | ||||||||||||||||
307564 | Piping | ||||||||||||||||
307565 | Mechanical / Eq | ||||||||||||||||
307566 | Instrumentation & Telecomm | ||||||||||||||||
307567 | Paiting & Insulation | ||||||||||||||||
307568 | Electrical | ||||||||||||||||
307569 | Pre-commissioning | ||||||||||||||||
307570 | 220 - GAS SEPARATION SYSTEM | ||||||||||||||||
307571 | Civil & Structural | ||||||||||||||||
307572 | Piping | ||||||||||||||||
307573 | Electrical | ||||||||||||||||
307574 | Instrumentation & Telecommunication | ||||||||||||||||
307575 | Mechanical / Eq | ||||||||||||||||
307576 | Paiting & Insulation | ||||||||||||||||
307577 | Pre-commissioning | ||||||||||||||||
307578 | 360 - WELL FLOWLINES SYSTEM | ||||||||||||||||
307579 | 210 - TEST SEPARATION AND METERING SYSTEM | ||||||||||||||||
307580 | Civil & Structural | ||||||||||||||||
307581 | Piping | ||||||||||||||||
307582 | Electrical | ||||||||||||||||
307583 | Instrumentaion & Telecommunication | ||||||||||||||||
307584 | Pre-commissioning | ||||||||||||||||
307585 | Mechanical / Equipment | ||||||||||||||||
307586 | Painting & Insulation | ||||||||||||||||
307587 | CAMP | ||||||||||||||||
307588 | PLANT & PIPING (INTERCONNECTING) | ||||||||||||||||
307589 | INERTGAS PIPING | ||||||||||||||||
307590 | GAS PIPING | ||||||||||||||||
307591 | GAS / CONDENSATE PIPING | ||||||||||||||||
307592 | HEATING MEDIUM PIPING | ||||||||||||||||
307593 | CHEMICAL INJECTION PIPING | ||||||||||||||||
307594 | METHANOL INJECTION PIPING | ||||||||||||||||
307595 | CONDENSATE PIPING | ||||||||||||||||
307596 | FLARE CONNECTING PIPING | ||||||||||||||||
307597 | PRODUCED WATER PIPING | ||||||||||||||||
307598 | 640 - INERT GAS (NITROGEN) SYSTEM | ||||||||||||||||
307599 | Piping | ||||||||||||||||
307600 | Mechanical / Eq | ||||||||||||||||
307601 | Instrumentation & Telecomm | ||||||||||||||||
307602 | Civil & Structural | ||||||||||||||||
307603 | Electrical | ||||||||||||||||
307604 | Paiting & Insulation | ||||||||||||||||
307605 | Pre-commissioning | ||||||||||||||||
307606 | 232 - OFFGAS COMPRESSION SYSTEM | ||||||||||||||||
307607 | Piping | ||||||||||||||||
307608 | Instrumentation & Telecommunication | ||||||||||||||||
307609 | Paiting & Insulation | ||||||||||||||||
307610 | Mechanical / Eq | ||||||||||||||||
307611 | Electrical | ||||||||||||||||
307612 | Pre-commissioning | ||||||||||||||||
307613 | Civil & Structural | ||||||||||||||||
307614 | 530 - FRESH/POTABLE/DEMINERALISED WATER SYSTEM | ||||||||||||||||
307615 | Civil & Structural | ||||||||||||||||
307616 | Piping | ||||||||||||||||
307617 | Mechanical / Eq | ||||||||||||||||
307618 | Electrical | ||||||||||||||||
307619 | Instrumentation & Telecomm | ||||||||||||||||
307620 | Paiting & Insulation | ||||||||||||||||
307621 | Pre-commissioning | ||||||||||||||||
307622 | 470 - CHLORINATION SYSTEM | ||||||||||||||||
307623 | Piping | ||||||||||||||||
307624 | Mechanical / Eq | ||||||||||||||||
307625 | Instrumentation & Telecomm | ||||||||||||||||
307626 | Paiting & Insulation | ||||||||||||||||
307627 | Civil & Structural | ||||||||||||||||
307628 | Electrical | ||||||||||||||||
307629 | Pre-commissioning | ||||||||||||||||
307630 | EQUIPMENT, OFF-PACKAGE | ||||||||||||||||
307631 | VESSELS, OFF-PACKAGE | ||||||||||||||||
307632 | INSTRUMENTATION, CONTROL, ELECTRICAL | ||||||||||||||||
307633 | PLANT COMMUNICATION AND VISUALIZATION SYSTEM | ||||||||||||||||
307634 | FIELD INSTRUMENTS | ||||||||||||||||
307635 | SMALL POWER SYSTEM | ||||||||||||||||
307636 | UPS 230V AC | ||||||||||||||||
307637 | LIGHTNING AND GROUNDING SYSTEM | ||||||||||||||||
307638 | CABLES AND CABLE TRAYS | ||||||||||||||||
307639 | ICSS SYSTEM | ||||||||||||||||
307640 | LV SYSTEM 400V | ||||||||||||||||
307641 | FIELD CABLING | ||||||||||||||||
307642 | MV SYSTEM 6.6kV | ||||||||||||||||
307643 | LV TRAFOS | ||||||||||||||||
307644 | FREQUENCY INVERTER | ||||||||||||||||
307645 | BATTERY SYSTEM 220V DC | ||||||||||||||||
307646 | 430 - LP/FP FLARE SYSTEM | ||||||||||||||||
307647 | Civil & Structural | ||||||||||||||||
307648 | Piping | ||||||||||||||||
307649 | Electrical | ||||||||||||||||
307650 | Instrumentation & Telecomm | ||||||||||||||||
307651 | Paiting & Insulation | ||||||||||||||||
307652 | Pre-commissioning | ||||||||||||||||
307653 | Mechanical / Eq | ||||||||||||||||
307654 | 420 - CHEMICAL INJECTION SYSTEM | ||||||||||||||||
307655 | Civil & Structural | ||||||||||||||||
307656 | Piping | ||||||||||||||||
307657 | Electrical | ||||||||||||||||
307658 | Instrumentation & Telecomm | ||||||||||||||||
307659 | Paiting & Insulation | ||||||||||||||||
307660 | Pre-commissioning | ||||||||||||||||
307661 | Mechanical / Eq | ||||||||||||||||
307662 | 660 - SEWAGE TREATMENT SYSTEM | ||||||||||||||||
307663 | Electrical | ||||||||||||||||
307664 | Instrumentation & Telecomm | ||||||||||||||||
307665 | Paiting & Insulation | ||||||||||||||||
307666 | Pre-commissioning | ||||||||||||||||
307667 | Piping | ||||||||||||||||
307668 | Mechanical / Eq | ||||||||||||||||
307669 | Civil & Structural | ||||||||||||||||
307670 | 110 - GAS WELL SYSTEM | ||||||||||||||||
307671 | 560 - OPEN DRAINS SYSTEM | ||||||||||||||||
307672 | Mechanical / Eq | ||||||||||||||||
307673 | Electrical | ||||||||||||||||
307674 | Instrumentation & Telecomm | ||||||||||||||||
307675 | Paiting & Insulation | ||||||||||||||||
307676 | Pre-commissioning | ||||||||||||||||
307677 | Civil & Structural | ||||||||||||||||
307678 | Piping | ||||||||||||||||
307679 | 270 - GAS EXPORT AND METERING SYSTEM | ||||||||||||||||
307680 | Civil & Structural | ||||||||||||||||
307681 | Paiting & Insulation | ||||||||||||||||
307682 | Pre -commisiioining | ||||||||||||||||
307683 | Piping | ||||||||||||||||
307684 | Electrical | ||||||||||||||||
307685 | Instrumentation & Telecomm | ||||||||||||||||
307686 | Mechanical / Eq | ||||||||||||||||
307687 | 480 - UTILITY MISCELLANEOUS SYSTEM | ||||||||||||||||
307688 | AMINE PIPING | ||||||||||||||||
307689 | GLYCOL PIPING | ||||||||||||||||
307690 | Paiting & insulation | ||||||||||||||||
307691 | Pre-commissioning | ||||||||||||||||
307692 | Piping | ||||||||||||||||
307693 | Mechanical / Eq | ||||||||||||||||
307694 | Instrumentation & Telecomm | ||||||||||||||||
307695 | Civil & Structural | ||||||||||||||||
307696 | Electrical | ||||||||||||||||
307697 | 460 - METHANOL INJECTION SYSTEM | ||||||||||||||||
307698 | Pre-commissioning | ||||||||||||||||
307699 | Civil & Structural | ||||||||||||||||
307700 | Piping | ||||||||||||||||
307701 | Instrumentation & Telecomm | ||||||||||||||||
307702 | Paiting & Insulation | ||||||||||||||||
307703 | Electrical | ||||||||||||||||
307704 | Mechanical / Eq | ||||||||||||||||
307705 | 710 - FIRE WATER SYSTEM | ||||||||||||||||
307706 | Paiting & Insulation | ||||||||||||||||
307707 | Civil & Structural | ||||||||||||||||
307708 | Piping | ||||||||||||||||
307709 | Mechanical / Eq | ||||||||||||||||
307710 | Electrical | ||||||||||||||||
307711 | Instrumentation & Telecomm | ||||||||||||||||
307712 | Pre-commissioning | ||||||||||||||||
307713 | 500 - INDUSTRIAL WATER SYSTEM | ||||||||||||||||
307714 | Pre-commissioning | ||||||||||||||||
307715 | Electrical | ||||||||||||||||
307716 | Civil & Structural | ||||||||||||||||
307717 | Piping | ||||||||||||||||
307718 | Mechanical / Eq | ||||||||||||||||
307719 | Instrumentation & Telecomm | ||||||||||||||||
307720 | Paiting & Insulation | ||||||||||||||||
307721 | 240 - GAS TREATMENT SYSTEM | ||||||||||||||||
307722 | Civil & Structural | ||||||||||||||||
307723 | Piping | ||||||||||||||||
307724 | Mechanical / Eq | ||||||||||||||||
307725 | Electrical | ||||||||||||||||
307726 | Paiting & Insulation | ||||||||||||||||
307727 | Instrumentation & Telecomm | ||||||||||||||||
307728 | Pre-commissioning | ||||||||||||||||
307729 | 450 - FUEL GAS SYSTEM | ||||||||||||||||
307730 | Civil & Structural | ||||||||||||||||
307731 | Piping | ||||||||||||||||
307732 | Electrical | ||||||||||||||||
307733 | Instrumentation & Telecomm | ||||||||||||||||
307734 | Paiting & Insulation | ||||||||||||||||
307735 | Pre -commissioning | ||||||||||||||||
307736 | Mechanical / Eq | ||||||||||||||||
307737 | 250 - GAS CONDITIONING (DEHYDRATION) SYSTEM | ||||||||||||||||
307738 | Piping | ||||||||||||||||
307739 | Civil & Structural | ||||||||||||||||
307740 | Pre-commissioning | ||||||||||||||||
307741 | Mechanical / Eq | ||||||||||||||||
307742 | Electrical | ||||||||||||||||
307743 | Instrumentation & Telecomm | ||||||||||||||||
307744 | Paiting & Insulation | ||||||||||||||||
307745 | 250 - GAS CONDITIONING (DEW POINTING) SYSTEM | ||||||||||||||||
307746 | Piping | ||||||||||||||||
307747 | Electrical | ||||||||||||||||
307748 | Instrumentation & Telecomm | ||||||||||||||||
307749 | Paiting & Insulation | ||||||||||||||||
307750 | Pre-commissioning | ||||||||||||||||
307751 | Civil & Structural | ||||||||||||||||
307752 | Mechanical /eq | ||||||||||||||||
307753 | 800 - MAIN POWER GENERATION SYSTEM | ||||||||||||||||
307754 | Piping | ||||||||||||||||
307755 | Paiting & Insulation | ||||||||||||||||
307756 | Pre-commissioning | ||||||||||||||||
307757 | Civil & Structural | ||||||||||||||||
307758 | Mechanical / Eq | ||||||||||||||||
307759 | Electrical | ||||||||||||||||
307760 | Instrumentation & Telecomm | ||||||||||||||||
307761 | 280 - GAS SWEETENING (AMINE) SYSTEM | ||||||||||||||||
307762 | Piping | ||||||||||||||||
307763 | Civil & Structural | ||||||||||||||||
307764 | Electrical | ||||||||||||||||
307765 | Instrumentation & Telecomm | ||||||||||||||||
307766 | Paiting & Insulation | ||||||||||||||||
307767 | Pre-commissioining | ||||||||||||||||
307768 | Mechanical / Eq | ||||||||||||||||
307769 | 620 - DIESEL OIL SYSTEM | ||||||||||||||||
307770 | Electrical | ||||||||||||||||
307771 | Instrumentation & Telecomm | ||||||||||||||||
307772 | Pre-commissioning | ||||||||||||||||
307773 | Civil & Structural | ||||||||||||||||
307774 | Paiting & Insulation | ||||||||||||||||
307775 | Piping | ||||||||||||||||
307776 | Mechanical / Eq | ||||||||||||||||
307777 | 410 - HEATING MEDIUM SYSTEM | ||||||||||||||||
307778 | Civil & Structural | ||||||||||||||||
307779 | Piping | ||||||||||||||||
307780 | Electrical | ||||||||||||||||
307781 | Instrumentation & Telecomm | ||||||||||||||||
307782 | Paiting & Insulation | ||||||||||||||||
307783 | Pre-commissioning | ||||||||||||||||
307784 | Mechanical / Eq | ||||||||||||||||
307785 | 200 - CONDENSATE STABILIZATION SYSTEM | ||||||||||||||||
307786 | Piping | ||||||||||||||||
307787 | Mechanical / Equipment | ||||||||||||||||
307788 | Electrical & Instrumentation & Telecommunication | ||||||||||||||||
307789 | Pre-Commissioning | ||||||||||||||||
307790 | Civil | ||||||||||||||||
307791 | Painting & Insulation | ||||||||||||||||
307792 | 200 - WATER / CONDENSATE SEPARATOR SYSTEM | ||||||||||||||||
307793 | Civil | ||||||||||||||||
307794 | Mechanical / Equipment | ||||||||||||||||
307795 | Piping | ||||||||||||||||
307796 | Electrical & Instrumentation & Telecommunication | ||||||||||||||||
307797 | Pre-Commissioning | ||||||||||||||||
307798 | Painting & Insulation | ||||||||||||||||
307799 | COMMON CPF | ||||||||||||||||
307800 | General Levelling | ||||||||||||||||
307801 | Fencing & Roads | ||||||||||||||||
307802 | Equipment Fundaments | ||||||||||||||||
307803 | Concrete Basement | ||||||||||||||||
307804 | Pipe rack | ||||||||||||||||
307805 | Evaporation Pond | ||||||||||||||||
307806 | PROCUREMENT | ||||||||||||||||
307807 | CIVIL, STRUCTURAL STEEL | ||||||||||||||||
307808 | 430 - LP/FP FLARE SYSTEM | ||||||||||||||||
307809 | LP/FP FLARE SKID | ||||||||||||||||
307810 | FLARE SYSTEM CONNECTION PIPING | ||||||||||||||||
307811 | 440 - PRODUCED WATER TREATMENT SYSTEM | ||||||||||||||||
307812 | PRODUCED WATER TREATMENT SKID | ||||||||||||||||
307813 | EVAPORATION POND | ||||||||||||||||
307814 | PRODUCED WATER TREATMENT SYSTEM PIPING | ||||||||||||||||
307815 | 440 - EVAPORATION POND | ||||||||||||||||
307816 | GENERAL | ||||||||||||||||
307817 | 420 - CHEMICAL INJECTION SYSTEM | ||||||||||||||||
307818 | CHEMICAL INJECTION PIPING | ||||||||||||||||
307819 | CHEMICAL INJECTION SKID | ||||||||||||||||
307820 | 200 - CONDENSATE STABILISATOR SYSTEM | ||||||||||||||||
307821 | CONDENSATE STABILISATION SKID | ||||||||||||||||
307822 | CONDENSATE PIPING | ||||||||||||||||
307823 | 210 - TEST SEPARATION AND METERING SYSTEM | ||||||||||||||||
307824 | 220 - GAS RECEPTION SYSTEM | ||||||||||||||||
307825 | 220 - GAS SEPARATION SYSTEM | ||||||||||||||||
307826 | 240 - GAS TREATMENT SYSTEM | ||||||||||||||||
307827 | 270 - GAS EXPORT AND METERING SYSTEM | ||||||||||||||||
307828 | 330 - CONDENSATE STORAGE AND METERING SYSTEM | ||||||||||||||||
307829 | CONDENSATE METERING SKID | ||||||||||||||||
307830 | CONDENSATE SYSTEM PIPING | ||||||||||||||||
307831 | CONDENSATE STORAGE SKID | ||||||||||||||||
307832 | 400 - COOLING MEDIUM (PROPANE) SYSTEM | ||||||||||||||||
307833 | 410 - HEATING MEDIUM SYSTEM | ||||||||||||||||
307834 | HEATING MEDIUM SKID | ||||||||||||||||
307835 | HEATING MEDIUM PIPING | ||||||||||||||||
307836 | 450 - FUEL GAS SYSTEM | ||||||||||||||||
307837 | FUEL GAS SUPPLY SYSTEM PIPING | ||||||||||||||||
307838 | FUEL GAS SUPPLY SYSTEM | ||||||||||||||||
307839 | 460 - METHANOL INJECTION SYSTEM | ||||||||||||||||
307840 | METHANOL INJECTION SKID | ||||||||||||||||
307841 | METHANOL PIPING | ||||||||||||||||
307842 | METHANOL STORAGE SKID | ||||||||||||||||
307843 | 480 - UTILITY MISCELLANEOUS SYSTEM | ||||||||||||||||
307844 | UTILITY MISCELLANEOUS SKIDS | ||||||||||||||||
307845 | AMINE PIPING | ||||||||||||||||
307846 | GLYCOL PIPING | ||||||||||||||||
307847 | PLANT & PIPING (INTERCONNECTING) | ||||||||||||||||
307848 | INERTGAS INTERCONNECTING PIPING | ||||||||||||||||
307849 | CONDENSATE INTERCONNECTING PIPING | ||||||||||||||||
307850 | METHANOL INJECTION INTERCONNECTING PIPING | ||||||||||||||||
307851 | INTERCONNECTING PIPING (BULK) | ||||||||||||||||
307852 | FLARE CONNECTING INTERCONNECTING PIPING | ||||||||||||||||
307853 | GAS INTERCONNECTING PIPING | ||||||||||||||||
307854 | CHEMICAL INJECTION INTERCONNECTING PIPING | ||||||||||||||||
307855 | PRODUCED WATER INTERCONNECTING PIPING | ||||||||||||||||
307856 | HEATING MEDIUM INTERCONNECTING PIPING | ||||||||||||||||
307857 | 110 - GAS WELLS SYSTEM | ||||||||||||||||
307858 | GAS WELLS SKID | ||||||||||||||||
307859 | 200 - WATER / CONDENSATE SEPARATOR SYSTEM | ||||||||||||||||
307860 | WATER / CONDENSATE SEPARATOR SKID | ||||||||||||||||
307861 | 232 - OFFGAS COMPRESSION SYSTEM | ||||||||||||||||
307862 | OFFGAS CONNECTION SKID | ||||||||||||||||
307863 | OFFGAS CONNECTION PIPING | ||||||||||||||||
307864 | 630 - INSTRUMENT AND PLANT AIR SYSTEM | ||||||||||||||||
307865 | PLANT AIR PIPING | ||||||||||||||||
307866 | INSTRUMENT AND PLANT AIR SYSTEM | ||||||||||||||||
307867 | INSTRUMENT AIR SYSTEM | ||||||||||||||||
307868 | 560 - OPEN DRAINS SYSTEM | ||||||||||||||||
307869 | CAMP | ||||||||||||||||
307870 | INSTRUMENTATION, CONTROL, ELECTRICAL | ||||||||||||||||
307871 | UPS 230V AC | ||||||||||||||||
307872 | LV SYSTEM 400V | ||||||||||||||||
307873 | PLANT COMMUNICATION AND VISUALIZATION SYSTEM | ||||||||||||||||
307874 | BATTERY SYSTEM 220V DC | ||||||||||||||||
307875 | LIGHTNING AND GROUNDING SYSTEM | ||||||||||||||||
307876 | FIELD INSTRUMENTS | ||||||||||||||||
307877 | FIELD CABLING | ||||||||||||||||
307878 | MV SYSTEM 6.6kV | ||||||||||||||||
307879 | FREQUENCY INVERTER | ||||||||||||||||
307880 | LV TRAFOS | ||||||||||||||||
307881 | ICSS SYSTEM | ||||||||||||||||
307882 | CABLES AND CABLE TRAYS | ||||||||||||||||
307883 | SMALL POWER SYSTEM | ||||||||||||||||
307884 | 640 - INERT GAS (NITROGEN) SYSTEM | ||||||||||||||||
307885 | NITROGEN SYSTEM PIPING | ||||||||||||||||
307886 | NITROGEN SYSTEM | ||||||||||||||||
307887 | 500 - INDUSTRIAL WATER SYSTEM | ||||||||||||||||
307888 | AQUIFER / PLANT WATER SYSTEM | ||||||||||||||||
307889 | PLANT WATER PIPING | ||||||||||||||||
307890 | 470 - CHLORINATION SYSTEM | ||||||||||||||||
307891 | CHLORINATION SYSTEM | ||||||||||||||||
307892 | CHLORINATION SYSTEM PIPING | ||||||||||||||||
307893 | 530 - FRESH/POTABLE/DEMINERALISED WATER SYSTEM | ||||||||||||||||
307894 | DEMIN WATER SYSTEM PIPING | ||||||||||||||||
307895 | DEMIN WATER SYSTEM | ||||||||||||||||
307896 | FRESH WATER SYSTEM | ||||||||||||||||
307897 | FRESH WATER SYSTEM PIPING | ||||||||||||||||
307898 | 570 - CLOSED DRAINS SYSTEM | ||||||||||||||||
307899 | CONNECTING PIPING | ||||||||||||||||
307900 | 710 - FIRE WATER SYSTEM | ||||||||||||||||
307901 | 660 - SEWAGE TREATMENT SYSTEM | ||||||||||||||||
307902 | VESSELS, OFF-PACKAGE | ||||||||||||||||
307903 | 830 - EMERGENCY POWER GENERATORS SYSTEM | ||||||||||||||||
307904 | 800 - MAIN POWER GENERATION SYSTEM | ||||||||||||||||
307905 | GAS TURBINE SYSTEM | ||||||||||||||||
307906 | 280 - GAS SWEETENING (AMINE) SYSTEM | ||||||||||||||||
307907 | 250 - GAS CONDITIONING (DEW POINTING) SYSTEM | ||||||||||||||||
307908 | 620 - DIESEL OIL SYSTEM | ||||||||||||||||
307909 | EQUIPMENT, OFF-PACKAGE | ||||||||||||||||
307910 | 250 - GAS CONDITIONING (DEHYDRATION) SYSTEM | ||||||||||||||||
307911 | 360 - WELL FLOWLINES SYSTEM | ||||||||||||||||
307912 | WELL HEAD FLOWLINES | ||||||||||||||||
307913 | METHANOL LINES | ||||||||||||||||
307914 | WELL FLOWLINES SKID | ||||||||||||||||
307915 | Structural Steel & Steel Plate | ||||||||||||||||
307916 | MIG WORKSHOP FABRICATION | ||||||||||||||||
307917 | COMMISSIONING, PERFORMANCE TEST | ||||||||||||||||
307918 | COMMISSIONING UTILITIES | ||||||||||||||||
307919 | COMMISSIONING GROUP A | ||||||||||||||||
307920 | COMMISSIONING GROUP B | ||||||||||||||||
307921 | COMMISSIONING GROUP C | ||||||||||||||||
307922 | COMMISSIONING GROUP D | ||||||||||||||||
307923 | COMMISSIONING GROUP E | ||||||||||||||||
307924 | COMMISSIONING GROUP F | ||||||||||||||||
307925 | COMMISSIONING WELL HEAD, FLOWLINES | ||||||||||||||||
307926 | COMMISSIONING ELECTRICAL, I&C EQUIPMENT | ||||||||||||||||
307927 | PERFORMANCE TEST | ||||||||||||||||
307929 | COMMISSIONING |