Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique IDu17b7MSTUE2sBqLL41ENrw
Unique ID175172
Activity NamePumps Erection
Added Dateسبتمبر 7, 2009, 9:58 ص
Added Byadmin
Activity StatusTK_NotStart
WBS39096
Total Float856,0
Activity LocationNone
Est Weight1,0
Phys Complete Pct0,0
Calendar866
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration736,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Dateأكتوبر 30, 2009, 3:31 م
Planned Startإبريل 1, 2012, 8 ص
Actual StartNone
Activity IDCCA04ME010
Early Startإبريل 1, 2012, 8 ص
Late Startأغسطس 4, 2012, 8 ص
Remaining Early Finishيوليو 16, 2012, 4 م
Remaining Early Startإبريل 1, 2012, 8 ص
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDFOoedYjIRU2rTJVTRAn0Ug
Lock RemainingN
4
Last Modified Byadmin 
Planned Finishيوليو 16, 2012, 4 م 
Actual FinishNone 
Activity TypeTT_Task 
Early Finishيوليو 16, 2012, 4 م 
Late Finishنوفمبر 18, 2012, 4 م 
Remaining Late Finishنوفمبر 18, 2012, 4 م 
Remaining Late Startأغسطس 4, 2012, 8 ص 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float736,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
736,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
1751640,0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
1751690,0 PR_FF