Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique IDJV2zdGTc/UiW7tthNQeX7g
Unique ID174639
Activity NameInstrument Cable: Manufacturing / Fabrication
Added Dateأغسطس 18, 2009, 1:43 م
Added Byadmin
Activity StatusTK_NotStart
WBS37384
Total Float276,0
Activity LocationNone
Est Weight1,0
Phys Complete Pct0,0
Calendar866
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration1184,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Dateأكتوبر 30, 2009, 3:31 م
Planned Startفبراير 10, 2011, 8 ص
Actual StartNone
Activity IDMKP03IC030
Early Startفبراير 10, 2011, 8 ص
Late Startمارس 22, 2011, ظهراً
Remaining Early Finishأغسطس 1, 2011, 4 م
Remaining Early Startفبراير 10, 2011, 8 ص
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDJzlmZS1hnk+EPlV4Incg2A
Lock RemainingN
4
Last Modified Byadmin 
Planned Finishأغسطس 1, 2011, 4 م 
Actual FinishNone 
Activity TypeTT_Task 
Early Finishأغسطس 1, 2011, 4 م 
Late Finishسبتمبر 11, 2011, ظهراً 
Remaining Late Finishسبتمبر 11, 2011, ظهراً 
Remaining Late Startمارس 22, 2011, ظهراً 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
1184,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
1746430,0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
1746400,0 PR_FS
إلى