Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique IDP2xlSjeB5EOigjzHcgS2YA
Unique ID174107
Activity NameTank Hydrotest
Added Dateأغسطس 10, 2009, 3:38 م
Added Byadmin
Activity StatusTK_NotStart
WBS38767
Total Float355,0
Activity LocationNone
Est Weight1,0
Phys Complete Pct0,0
Calendar866
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration197,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Dateأكتوبر 30, 2009, 3:31 م
Planned Startفبراير 23, 2012, 8 ص
Actual StartNone
Activity IDCCF91TK020
Early Startفبراير 23, 2012, 8 ص
Late Startإبريل 15, 2012, 11 ص
Remaining Early Finishمارس 22, 2012, 1 م
Remaining Early Startفبراير 23, 2012, 8 ص
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDiajzpGA4jUu0Nd8Wn400KQ
Lock RemainingN
4
Last Modified Byadmin 
Planned Finishمارس 22, 2012, 1 م 
Actual FinishNone 
Activity TypeTT_Task 
Early Finishمارس 22, 2012, 1 م 
Late Finishمايو 13, 2012, 4 م 
Remaining Late Finishمايو 13, 2012, 4 م 
Remaining Late Startإبريل 15, 2012, 11 ص 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
197,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
1741110,0 PR_FS
1741080,0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
1741090,0 PR_FS
1741120,0 PR_FS