Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique IDXmE1C22xz06n+EXKLp9K0g
Unique ID174081
Activity NameTank Hydrotest
Added Dateأغسطس 10, 2009, 3:01 م
Added Byadmin
Activity StatusTK_NotStart
WBS38747
Total Float360,0
Activity LocationNone
Est Weight1,0
Phys Complete Pct0,0
Calendar866
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration197,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Dateأكتوبر 30, 2009, 3:31 م
Planned Startأغسطس 27, 2011, 8 ص
Actual StartNone
Activity IDCCF09TK020
Early Startأغسطس 27, 2011, 8 ص
Late Startأكتوبر 18, 2011, 8 ص
Remaining Early Finishسبتمبر 24, 2011, 1 م
Remaining Early Startأغسطس 27, 2011, 8 ص
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique ID3ubEYvN270CS52fMbNq42A
Lock RemainingN
4
Last Modified Byadmin 
Planned Finishسبتمبر 24, 2011, 1 م 
Actual FinishNone 
Activity TypeTT_Task 
Early Finishسبتمبر 24, 2011, 1 م 
Late Finishنوفمبر 15, 2011, 1 م 
Remaining Late Finishنوفمبر 15, 2011, 1 م 
Remaining Late Startأكتوبر 18, 2011, 8 ص 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
197,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
1740850,0 PR_FS
1740820,0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
1740830,0 PR_FS