Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique IDFM6rrXVVVkSEI6MtI9BR0w
Unique ID173992
Activity NameTank Painting/Lining Works
Added Dateأغسطس 10, 2009, 10:21 ص
Added Byadmin
Activity StatusTK_NotStart
WBS38684
Total Float312,0
Activity LocationNone
Est Weight1,0
Phys Complete Pct0,0
Calendar866
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration560,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Dateأكتوبر 30, 2009, 3:31 م
Planned Startيونيو 2, 2012, 8 ص
Actual StartNone
Activity IDCCF62PI010
Early Startيونيو 2, 2012, 8 ص
Late Startيوليو 17, 2012, 8 ص
Remaining Early Finishأغسطس 21, 2012, 4 م
Remaining Early Startيونيو 2, 2012, 8 ص
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDTMVGWFHLzU+6EWAW4VrTZw
Lock RemainingN
4
Last Modified Byadmin 
Planned Finishأغسطس 21, 2012, 4 م 
Actual FinishNone 
Activity TypeTT_Task 
Early Finishأغسطس 21, 2012, 4 م 
Late Finishأكتوبر 6, 2012, 4 م 
Remaining Late Finishأكتوبر 6, 2012, 4 م 
Remaining Late Startيوليو 17, 2012, 8 ص 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
560,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
1739900,0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
1739930,0 PR_FS