Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique IDna3oAvN+8ECE+xQiwfOh6Q
Unique ID171382
Activity NameFeed/Transfer/Booster Pumps: RFQ to Bid Evaluation
Added Dateأغسطس 4, 2009, 8:36 ص
Added Byadmin
Activity StatusTK_NotStart
WBS37437
Total Float542,0
Activity LocationNone
Est Weight1,0
Phys Complete Pct0,0
Calendar864
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration360,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Dateأكتوبر 30, 2009, 3:31 م
Planned Startمايو 18, 2010, 8 ص
Actual StartNone
Activity IDHPP01ME040
Early Startمايو 18, 2010, 8 ص
Late Startأغسطس 19, 2010, 2 م
Remaining Early Finishيوليو 19, 2010, 4 م
Remaining Early Startمايو 18, 2010, 8 ص
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDNone
Lock RemainingN
4
Last Modified Byadmin 
Planned Finishيوليو 19, 2010, 4 م 
Actual FinishNone 
Activity TypeTT_Task 
Early Finishيوليو 19, 2010, 4 م 
Late Finishأكتوبر 21, 2010, 2 م 
Remaining Late Finishأكتوبر 21, 2010, 2 م 
Remaining Late Startأغسطس 19, 2010, 2 م 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
360,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
1711900,0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
1713830,0 PR_FS
إلى