Project Cloud System

Job N° : 1260014

Task Detail

1
General Informations
Project22726
Global Unique IDTUeyJe+xS6W3qWBbERaKMw
Unique ID2908318
Activity NamePO placed - Gas Sweetening (Amine) System
Added Dateنوفمبر 25, 2013, 2:42 م
Added Byadmin
Activity StatusTK_NotStart
WBS307906
Total Float-528,0
Activity LocationNone
Est Weight0,0
Phys Complete Pct0,0
Calendar1183
Percent Complete TypeCP_Phys
Auto Compute ActualsN
Remaining Duration0,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Dateنوفمبر 25, 2013, 2:42 م
Planned Startيونيو 6, 2014, 4 م
Actual StartNone
Activity IDF2330
Early Startيونيو 6, 2014, 4 م
Late Startإبريل 1, 2014, 4 م
Remaining Early Finishيونيو 6, 2014, 4 م
Remaining Early Startيونيو 6, 2014, 4 م
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDWT4Cm6gNA0Szu0L6UAg7gw
Lock RemainingN
4
Last Modified Byadmin 
Planned Finishيونيو 6, 2014, 4 م 
Actual FinishNone 
Activity TypeTT_FinMile 
Early Finishيونيو 6, 2014, 4 م 
Late Finishإبريل 1, 2014, 4 م 
Remaining Late Finishإبريل 1, 2014, 4 م 
Remaining Late Startإبريل 1, 2014, 4 م 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDrtn 
Planned Duration
Original or Planned Duration
0,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
29083170,0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
29083200,0 PR_FS
إلى