Project Cloud System

Job N° : 1260014

Task Detail

1
General Informations
Project22726
Global Unique IDlpTDiargQTKHxwUc1qOguw
Unique ID2908299
Activity NameAt site - Vessels off-package
Added Dateنوفمبر 25, 2013, 2:42 م
Added Byadmin
Activity StatusTK_NotStart
WBS307902
Total Float1248,0
Activity LocationNone
Est Weight0,0
Phys Complete Pct0,0
Calendar1183
Percent Complete TypeCP_Phys
Auto Compute ActualsN
Remaining Duration0,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Dateنوفمبر 25, 2013, 2:42 م
Planned Startيوليو 29, 2015, 4 م
Actual StartNone
Activity IDM5510
Early Startيوليو 29, 2015, 4 م
Late Startيناير 1, 2016, 4 م
Remaining Early Finishيوليو 29, 2015, 4 م
Remaining Early Startيوليو 29, 2015, 4 م
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDgPsgg8KMl0KkWSRriWk5CA
Lock RemainingN
4
Last Modified Byadmin 
Planned Finishيوليو 29, 2015, 4 م 
Actual FinishNone 
Activity TypeTT_FinMile 
Early Finishيوليو 29, 2015, 4 م 
Late Finishيناير 1, 2016, 4 م 
Remaining Late Finishيناير 1, 2016, 4 م 
Remaining Late Startيناير 1, 2016, 4 م 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float1784,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDrtn 
Planned Duration
Original or Planned Duration
0,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
29082980,0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
إلى