Project Cloud System

Job N° : 1260014

Task Detail

1
General Informations
Project22726
Global Unique ID2CHY4ZIPRAKCLpt8lOKAjw
Unique ID2908294
Activity NamePurchasing - Vessels off-package
Added Dateنوفمبر 25, 2013, 2:42 م
Added Byadmin
Activity StatusTK_NotStart
WBS307902
Total Float1248,0
Activity LocationNone
Est Weight1,0
Phys Complete Pct0,0
Calendar1183
Percent Complete TypeCP_Phys
Auto Compute ActualsN
Remaining Duration616,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Dateنوفمبر 25, 2013, 2:42 م
Planned Startمايو 4, 2014, 8 ص
Actual StartNone
Activity IDF5460
Early Startمايو 4, 2014, 8 ص
Late Startأكتوبر 7, 2014, 8 ص
Remaining Early Finishيوليو 19, 2014, 4 م
Remaining Early Startمايو 4, 2014, 8 ص
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDQvc9dTQW6EWYuius5mP4TQ
Lock RemainingN
4
Last Modified Byadmin 
Planned Finishيوليو 19, 2014, 4 م 
Actual FinishNone 
Activity TypeTT_Task 
Early Finishيوليو 19, 2014, 4 م 
Late Finishديسمبر 22, 2014, 4 م 
Remaining Late Finishديسمبر 22, 2014, 4 م 
Remaining Late Startأكتوبر 7, 2014, 8 ص 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
616,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
29073670,0 PR_FF

Successors

6
  Task Id    Lag (day)     Succ Type  
29082950,0 PR_FS