Project Cloud System

Job N° : 1260014

Task Detail

1
General Informations
Project22726
Global Unique ID8+8RYPqETvO2VPVEEm1W+Q
Unique ID2908189
Activity NameReady for Shipment - Cables and Cable Trays
Added Dateنوفمبر 25, 2013, 2:42 م
Added Byadmin
Activity StatusTK_NotStart
WBS307882
Total Float2136,0
Activity LocationNone
Est Weight0,0
Phys Complete Pct0,0
Calendar19658
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration0,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Dateنوفمبر 25, 2013, 2:42 م
Planned Startنوفمبر 26, 2014, 8 ص
Actual StartNone
Activity IDJ1900
Early Startنوفمبر 26, 2014, 8 ص
Late Startأغسطس 20, 2015, 8 ص
Remaining Early Finishنوفمبر 26, 2014, 8 ص
Remaining Early Startنوفمبر 26, 2014, 8 ص
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDHYCx9hsAwkiOss1GLwr2Gw
Lock RemainingN
4
Last Modified Byadmin 
Planned Finishنوفمبر 26, 2014, 8 ص 
Actual FinishNone 
Activity TypeTT_Mile 
Early Finishنوفمبر 26, 2014, 8 ص 
Late Finishأغسطس 20, 2015, 8 ص 
Remaining Late Finishأغسطس 20, 2015, 8 ص 
Remaining Late Startأغسطس 20, 2015, 8 ص 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDrtn 
Planned Duration
Original or Planned Duration
0,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
29081880,0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
29081920,0 PR_FS
إلى