Project Cloud System

Job N° : 1260014

Task Detail

1
General Informations
Project22726
Global Unique IDSd7p+gzZR8a4H5PHFYFonQ
Unique ID2908047
Activity NameTransport to Port of Export - Gas Wells System (Skid 4-6)
Added Dateنوفمبر 25, 2013, 2:42 م
Added Byadmin
Activity StatusTK_NotStart
WBS307858
Total Float-384,0
Activity LocationNone
Est Weight1,0
Phys Complete Pct0,0
Calendar1183
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration56,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Dateنوفمبر 25, 2013, 2:42 م
Planned Startمايو 16, 2015, 8 ص
Actual StartNone
Activity IDF5575
Early Startمايو 16, 2015, 8 ص
Late Startمارس 29, 2015, 8 ص
Remaining Early Finishمايو 22, 2015, 4 م
Remaining Early Startمايو 16, 2015, 8 ص
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDQCko4x10AEer6kRoij9Z7g
Lock RemainingN
4
Last Modified Byadmin 
Planned Finishمايو 22, 2015, 4 م 
Actual FinishNone 
Activity TypeTT_Task 
Early Finishمايو 22, 2015, 4 م 
Late Finishإبريل 4, 2015, 4 م 
Remaining Late Finishإبريل 4, 2015, 4 م 
Remaining Late Startمارس 29, 2015, 8 ص 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
56,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
29080380,0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
29080400,0 PR_FS
إلى