Project Cloud System

Job N° : 1260014

Task Detail

1
General Informations
Project22726
Global Unique IDccndpKLGRbO6PoX6d0+Bdg
Unique ID2908027
Activity NameTransport to Port of Export - Interconnecting Piping 60%
Added Dateنوفمبر 25, 2013, 2:42 م
Added Byadmin
Activity StatusTK_NotStart
WBS307851
Total Float-88,0
Activity LocationNone
Est Weight1,0
Phys Complete Pct0,0
Calendar1183
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration56,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Dateنوفمبر 25, 2013, 2:42 م
Planned Startسبتمبر 12, 2014, 8 ص
Actual StartNone
Activity IDJ5375
Early Startسبتمبر 12, 2014, 8 ص
Late Startسبتمبر 1, 2014, 8 ص
Remaining Early Finishسبتمبر 18, 2014, 4 م
Remaining Early Startسبتمبر 12, 2014, 8 ص
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique ID1aEfqlna8ku1KDKAZ0mRbw
Lock RemainingN
4
Last Modified Byadmin 
Planned Finishسبتمبر 18, 2014, 4 م 
Actual FinishNone 
Activity TypeTT_Task 
Early Finishسبتمبر 18, 2014, 4 م 
Late Finishسبتمبر 7, 2014, 4 م 
Remaining Late Finishسبتمبر 7, 2014, 4 م 
Remaining Late Startسبتمبر 1, 2014, 8 ص 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
56,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
29080240,0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
29080250,0 PR_FS
إلى