Project Cloud System

Job N° : 1260014

Task Detail

1
General Informations
Project22726
Global Unique ID4FSBz0klQdOtXUbM+En8XQ
Unique ID2907986
Activity NameReady for Shipment - Methanol injection interconnecting piping
Added Dateنوفمبر 25, 2013, 2:42 م
Added Byadmin
Activity StatusTK_NotStart
WBS307841
Total Float1000,0
Activity LocationNone
Est Weight0,0
Phys Complete Pct0,0
Calendar19658
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration0,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Dateنوفمبر 25, 2013, 2:42 م
Planned Startأكتوبر 27, 2014, 8 ص
Actual StartNone
Activity IDJ4230
Early Startأكتوبر 27, 2014, 8 ص
Late Startمارس 1, 2015, 8 ص
Remaining Early Finishأكتوبر 27, 2014, 8 ص
Remaining Early Startأكتوبر 27, 2014, 8 ص
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique ID31snhl9KdESWniwhstnmWg
Lock RemainingN
4
Last Modified Byadmin 
Planned Finishأكتوبر 27, 2014, 8 ص 
Actual FinishNone 
Activity TypeTT_Mile 
Early Finishأكتوبر 27, 2014, 8 ص 
Late Finishمارس 1, 2015, 8 ص 
Remaining Late Finishمارس 1, 2015, 8 ص 
Remaining Late Startمارس 1, 2015, 8 ص 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDrtn 
Planned Duration
Original or Planned Duration
0,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
29079850,0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
29079890,0 PR_FS
إلى