Project Cloud System

Job N° : 1260014

Task Detail

1
General Informations
Project22726
Global Unique IDLgy5pKfKSJeouwHYWxdf1Q
Unique ID2907927
Activity NameTransport to Port of Export - Condensate System Piping
Added Dateنوفمبر 25, 2013, 2:42 م
Added Byadmin
Activity StatusTK_NotStart
WBS307830
Total Float1784,0
Activity LocationNone
Est Weight1,0
Phys Complete Pct0,0
Calendar1183
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration56,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Dateنوفمبر 25, 2013, 2:42 م
Planned Startنوفمبر 20, 2014, 8 ص
Actual StartNone
Activity IDJ2275
Early Startنوفمبر 20, 2014, 8 ص
Late Startيوليو 1, 2015, 8 ص
Remaining Early Finishنوفمبر 26, 2014, 4 م
Remaining Early Startنوفمبر 20, 2014, 8 ص
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDEgH3ondsYEaNfJ4Cj+bigw
Lock RemainingN
4
Last Modified Byadmin 
Planned Finishنوفمبر 26, 2014, 4 م 
Actual FinishNone 
Activity TypeTT_Task 
Early Finishنوفمبر 26, 2014, 4 م 
Late Finishيوليو 7, 2015, 4 م 
Remaining Late Finishيوليو 7, 2015, 4 م 
Remaining Late Startيوليو 1, 2015, 8 ص 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
56,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
29079240,0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
29079250,0 PR_FS
إلى