Project Cloud System

Job N° : 1260014

Task Detail

1
General Informations
Project22726
Global Unique ID+ba4q/pMR9G0ZRnwnAfM9Q
Unique ID2907766
Activity NamePre-commissioning - Gas Sweetening (Amine) System
Added Dateنوفمبر 25, 2013, 2:42 م
Added Byadmin
Activity StatusTK_NotStart
WBS307767
Total Float-456,0
Activity LocationNone
Est Weight1,0
Phys Complete Pct0,0
Calendar22303
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration288,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Dateنوفمبر 25, 2013, 2:42 م
Planned Startسبتمبر 22, 2015, 8 ص
Actual StartNone
Activity IDM4131207
Early Startسبتمبر 22, 2015, 8 ص
Late Startيوليو 18, 2015, 8 ص
Remaining Early Finishنوفمبر 2, 2015, 4 م
Remaining Early Startسبتمبر 22, 2015, 8 ص
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDLJ743fZUcUS4N3W8FCw0gw
Lock RemainingN
4
Last Modified Byadmin 
Planned Finishنوفمبر 2, 2015, 4 م 
Actual FinishNone 
Activity TypeTT_Task 
Early Finishنوفمبر 2, 2015, 4 م 
Late Finishأغسطس 27, 2015, 4 م 
Remaining Late Finishأغسطس 27, 2015, 4 م 
Remaining Late Startيوليو 18, 2015, 8 ص 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
288,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
29077590,0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
29071360,0 PR_FS
29084170,0 PR_FS