Project Cloud System

Job N° : 1260014

Task Detail

1
General Informations
Project22726
Global Unique IDB3egU7/MTPawUpI4gsckqg
Unique ID2907690
Activity NameInstrumentation & Telecomm - Methanol Injection System
Added Dateنوفمبر 25, 2013, 2:42 م
Added Byadmin
Activity StatusTK_NotStart
WBS307701
Total Float72,0
Activity LocationNone
Est Weight1,0
Phys Complete Pct0,0
Calendar22303
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration312,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Dateنوفمبر 25, 2013, 2:42 م
Planned Startيوليو 25, 2015, 8 ص
Actual StartNone
Activity IDM4132005
Early Startيوليو 25, 2015, 8 ص
Late Startأغسطس 4, 2015, 8 ص
Remaining Early Finishسبتمبر 7, 2015, 4 م
Remaining Early Startيوليو 25, 2015, 8 ص
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDQtW7rJLoU02GwjjheuVlBA
Lock RemainingN
4
Last Modified Byadmin 
Planned Finishسبتمبر 7, 2015, 4 م 
Actual FinishNone 
Activity TypeTT_Task 
Early Finishسبتمبر 7, 2015, 4 م 
Late Finishسبتمبر 17, 2015, 4 م 
Remaining Late Finishسبتمبر 17, 2015, 4 م 
Remaining Late Startأغسطس 4, 2015, 8 ص 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float40,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
312,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
29076920,0 PR_SS

Successors

6
  Task Id    Lag (day)     Succ Type  
29076850,0 PR_FS
إلى