Project Cloud System

Job N° : 1260014

Task Detail

1
General Informations
Project22726
Global Unique IDxJXyo1MqSa+kRog0GyLM0Q
Unique ID2907596
Activity NameErection - Field Cabling (1M nach Kabeltrassen - ROHRBR�CKENau�en MIG), kabeltrassen innen
Added Dateنوفمبر 25, 2013, 2:42 م
Added Byadmin
Activity StatusTK_NotStart
WBS307641
Total Float1840,0
Activity LocationNone
Est Weight1,0
Phys Complete Pct0,0
Calendar19658
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration300,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Dateنوفمبر 25, 2013, 2:42 م
Planned Startيناير 24, 2015, ظهراً
Actual StartNone
Activity IDJ2210
Early Startيناير 24, 2015, ظهراً
Late Startسبتمبر 11, 2015, ظهراً
Remaining Early Finishمارس 2, 2015, 4 م
Remaining Early Startيناير 24, 2015, ظهراً
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDlXCVI6iSn0Oi3+hLvf8wyA
Lock RemainingN
4
Last Modified Byadmin 
Planned Finishمارس 2, 2015, 4 م 
Actual FinishNone 
Activity TypeTT_Task 
Early Finishمارس 2, 2015, 4 م 
Late Finishأكتوبر 18, 2015, 4 م 
Remaining Late Finishأكتوبر 18, 2015, 4 م 
Remaining Late Startسبتمبر 11, 2015, ظهراً 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
300,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
29081520,0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
29075970,0 PR_FS
إلى