Project Cloud System

Job N° : 1260014

Task Detail

1
General Informations
Project22726
Global Unique IDDHO5CkQZTFKdNukJDKzR7g
Unique ID2907534
Activity NamePiping - Test Separation and Metering System
Added Dateنوفمبر 25, 2013, 2:42 م
Added Byadmin
Activity StatusTK_NotStart
WBS307581
Total Float960,0
Activity LocationNone
Est Weight1,0
Phys Complete Pct0,0
Calendar22303
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration704,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Dateنوفمبر 25, 2013, 2:42 م
Planned Startيناير 12, 2015, 8 ص
Actual StartNone
Activity IDM413502
Early Startيناير 12, 2015, 8 ص
Late Startيونيو 1, 2015, 8 ص
Remaining Early Finishإبريل 23, 2015, 4 م
Remaining Early Startيناير 12, 2015, 8 ص
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDKafKOV66k0yYNBXbTViKBA
Lock RemainingN
4
Last Modified Byadmin 
Planned Finishإبريل 23, 2015, 4 م 
Actual FinishNone 
Activity TypeTT_Task 
Early Finishإبريل 23, 2015, 4 م 
Late Finishسبتمبر 10, 2015, 4 م 
Remaining Late Finishسبتمبر 10, 2015, 4 م 
Remaining Late Startيونيو 1, 2015, 8 ص 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
704,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
29075360,0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
29075350,0 PR_FS