Project Cloud System

Job N° : 1260014

Task Detail

1
General Informations
Project22726
Global Unique IDve20ErIGQHettkJclWZ4eQ
Unique ID2907389
Activity NameFinal Documentation - Produced Water Treatment System and Evaporation Pond
Added Dateنوفمبر 25, 2013, 2:42 م
Added Byadmin
Activity StatusTK_NotStart
WBS307502
Total Float-32,0
Activity LocationNone
Est Weight1,0
Phys Complete Pct0,0
Calendar22303
Percent Complete TypeCP_Phys
Auto Compute ActualsN
Remaining Duration720,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Dateنوفمبر 25, 2013, 2:42 م
Planned Startسبتمبر 23, 2015, 8 ص
Actual StartNone
Activity IDM3940
Early Startسبتمبر 23, 2015, 8 ص
Late Startسبتمبر 19, 2015, 8 ص
Remaining Early Finishيناير 5, 2016, 4 م
Remaining Early Startسبتمبر 23, 2015, 8 ص
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDac50HUYpRE2jq6V0XUmITQ
Lock RemainingN
4
Last Modified Byadmin 
Planned Finishيناير 5, 2016, 4 م 
Actual FinishNone 
Activity TypeTT_Task 
Early Finishيناير 5, 2016, 4 م 
Late Finishديسمبر 31, 2015, 4 م 
Remaining Late Finishديسمبر 31, 2015, 4 م 
Remaining Late Startسبتمبر 19, 2015, 8 ص 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float384,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
720,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
29084230,0 PR_FF

Successors

6
  Task Id    Lag (day)     Succ Type  
29071380,0 PR_FS