Project Cloud System

Job N° : 1260014

Task Detail

1
General Informations
Project22726
Global Unique IDQ4t3Qhf5QdWSJLFYsbjeAQ
Unique ID2907289
Activity NameFirst Submittal of first Process Engineering Document acc. to DDS
Added Dateنوفمبر 25, 2013, 2:41 م
Added Byadmin
Activity StatusTK_NotStart
WBS307494
Total Float4656,0
Activity LocationNone
Est Weight0,0
Phys Complete Pct0,0
Calendar1183
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration0,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Dateنوفمبر 25, 2013, 2:41 م
Planned Startمارس 30, 2014, 4 م
Actual StartNone
Activity IDF5011
Early Startمارس 30, 2014, 4 م
Late Startنوفمبر 2, 2015, 4 م
Remaining Early Finishمارس 30, 2014, 4 م
Remaining Early Startمارس 30, 2014, 4 م
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDNone
Lock RemainingN
4
Last Modified Byadmin 
Planned Finishمارس 30, 2014, 4 م 
Actual FinishNone 
Activity TypeTT_FinMile 
Early Finishمارس 30, 2014, 4 م 
Late Finishنوفمبر 2, 2015, 4 م 
Remaining Late Finishنوفمبر 2, 2015, 4 م 
Remaining Late Startنوفمبر 2, 2015, 4 م 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDrtn 
Planned Duration
Original or Planned Duration
0,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
2907288240,0 PR_SS

Successors

6
  Task Id    Lag (day)     Succ Type  
2907290480,0 PR_FS
29072910,0 PR_FS